Abstract
This paper proposes a distribution locational marginal pricing (DLMP) based bi-level Stackelberg game framework between the internet service company (ISC) and distribution system operator (DSO) in the data center park. To minimize electricity costs, the ISC at the upper level dispatches the interactive workloads (IWs) across different data center buildings spatially and schedules the battery energy storage system temporally in response to DLMP. Photovoltaic generation and static var generation provide extra active and reactive power. At the lower level, DSO calculates the DLMP by minimizing the total electricity cost under the two-part tariff policy and ensures that the distribution network is uncongested and bus voltage is within the limit. The equilibrium solution is obtained by converting the bi-level optimization into a single-level mixed-integer second-order cone programming optimization using the strong duality theorem and the binary expansion method. Case studies verify that the proposed method benefits both the DSO and ISC while preserving the privacy of the ISC. By taking into account the uncertainties in IWs and photovoltaic generation, the flexibility of distribution networks is enhanced, which further facilitates the accommodation of more demand-side resources.
Strategy set of distribution system operator (DSO)
Set of receiving buses of branch lines with the same sending bus j
Set of all branch lines in distribution network
Set of locations of data centers ()
Index of binary extension method slice
, j, k Indices of buses in distribution network
Set of all buses in distribution network
Index of time slots
Set of time slots
Dual variable of nodal active power balance constraint as well as distribution locational marginal pricing
Dual variable of nodal reactive power balance constraint
Dual variable of voltage drop constraint of each branch
, , , Dual variables of second-order cone programming relaxation constraint
, Dual variables of lower/upper grid power factor limitation constraints
, Dual variables of bus voltage magnitudes constraints
, Dual variables of branch current magnitudes constraints
Dual variable of the maximum power demand constraint
Number of active servers in data center building (DCB)
Stored electric energy of bettary energy storage system (BESS)
Payoff function of upper level
Payoff function of lower level
Squared current magnitude of branch (i, j)
Total arriving workloads in DCB
, , , Dual variables
Total active power load of DCB
, Active and reactive power outputs of photovoltaic (PV)
, Charging and discharging active power of BESS
, Active and reactive net electric power
The maximum demand for electric power
, Active and reactive power on branch (i, j)
, Provided active and reactive power of data center park (DCP) by independent system operator (ISO)
Reactive power output of static var generation (SVG)
, Binary variables indicating charging and discharging states of BESS
Squared voltage magnitude
, Auxiliary variables
, Nonnegative control parameters between 0 and 1
Time slot
, Charging and discharging efficiencies of BESS
, Uncertainties of parameters and
Number of days to settle the maximum demand price
Power factor of DCP
The maximum number of servers
Purchased electricity price of DSO
The maximum demand price of DSO
Designed power usage efficiency (PUE) of a DCB
The maximum delay time
Rated energy of BESS
A non-negative integer
Upper bound of current magnitude of branch (i, j)
Service rate of a server
, Predicted and uncertain workloads in front-end server
Big positive constant
, Idle and peak active power of a server
, Basic active and reactive power loads
The maximum active charging or discharging power of BESS
The maximum net electric power
Reactive power capacity of SVG
, Resistance and reactance of branch (i, j)
Apparent power capacity of PV
, The minimum and maximum states-of-charge
(SOCs) of BESS
, Day-ahead predicted and uncertain active power output curves of PV
, Lower and upper voltage bounds
CLOUD computing is gaining momentum, driven by the development of social networks, big data, and the Internet of Things. To effectively process these massive workloads and provide reliable computing services, major internet service companies (ISCs) have built extensive data centers. With the expansion of data centers, their energy consumption has grown rapidly, most of which are used for processing workloads and corresponding cooling systems. On a global scale, the annual electric power consumption of data centers reached around 3% in 2016 [
The traditional methods to block out network congestion are expanding the power capacity or network reconfiguration [
The thermal loads, BESSs, and electric vehicle charging stations are temporal demand-side resources, which can be dispatched in different time slots for congestion management. Different from temporal demand-side resources, the arriving workloads at the front-end server can be dispatched both temporally and spatially through the data network. According to the processing deadlines, the arriving workloads mainly include the delay-tolerant batch workloads (BWs) and delay-sensitive interactive workloads (IWs) [
In reality, data centers had participated in demand response in history. For example, on July 22, 2011, hundreds of data centers cut power demands for emergency demand response and helped avoid a wide-area blackout throughout North America [
In the electricity market, the distribution networks for general industrial and commercial users are usually managed by the distribution system operators (DSOs), which are powered by the electricity utilities, e.g., independent system operators (ISOs). In terms of the DSO, the most effective method is scheduling all the available demand-side resources in a centralized manner. However, it is unrealistic for the DSO to gain access and control of all devices in the distribution network, particularly considering users’ data privacy. To address this challenge, researchers have explored the use of the non-cooperative Stackelberg game theory, which models interactions between energy suppliers and consumers as leaders and followers [
These studies seldom consider security issues such as network congestion and voltage issues in distribution networks. In [
Multiple uncertainties such as those in renewable generation and workloads can lead to uncontrollable distribution network congestion and other security issues that increase system risk and operation costs. It is crucial to incorporate such uncertainties into operation models to enhance the applicability of the proposed method in motivating DCBs to support grid security. Stochastic optimization (SO) [
Compared with previous works, this paper proposes a DLMP-based equilibrium optimization strategy for DCP with spatial-temporal demand-side resources. The contributions of this paper are as follows.
1) A bi-level Stackelberg game framework is proposed to motivate multiple DCBs with demand-side resources to support the grid security, where the ISC with multiple DCBs is seen as a leader and DSO is seen as a follower.
2) Both the temporal and spatial demand-side resources of multiple DCBs are considered to be scheduled in the game strategy. The uncertainties in arriving workload and PV generations are modeled into RO format to verify the applicability of the proposed strategy in motivating DCBs to support grid security.
3) The radial distribution network is modeled by Disflow equations with the second-order cone programming (SOCP) formulation. To solve the bi-level operation problem, the strong duality equation of the SOCP problem is derived. The bilinear terms are addressed by the binary expansion method, thus converting the bi-level operation problem to a single-level mixed-integer second-order cone programming (MISOCP) problem, which can be solved by commercial solvers.
The rest of this paper is organized as follows. Section II presents the problem formulation, including the framework of DLMP-based equilibrium optimization strategy and the upper-level and lower-level dispatching models. Section III presents the model reformulation and solution method. Section IV presents the case studies on a modified IEEE 33-bus system. Conclusions are drawn in Section V.
The basic structure of the problem in this paper includes three stakeholders: ISC, DSO, and ISO, as shown in

Fig. 1 Operation framework for ISC, DSO, and ISO.
1) Only DCBs are seen as the flexible loads in the distribution network of DCP. Other loads are seen to be fixed, and there are no distributed generations except PV generation in DCBs.
2) The coupling of multiple energy systems, e.g., electric power and natural gas, is neglected in the DCP.
To this end, the bi-level Stackelberg game model is formulated as:
(1) |
where ; and . Let be the optimal strategies of each player, the equilibrium solution can be solved by:
(2) |
Remark 1: this paper assumes that multiple DCBs are managed by a single ISC. Therefore, the proposed bilevel problem is indeed a one-leader and one-follower Stackelberg game, where the equilibrium solution remains the same regardless of who serves as the leader or follower. Additionally, since the optimization of multiple DCBs with integer variables is non-convex, the ISC is set as the leader while the DSO is the follower for computational tractability.
As the leader at the upper level, ISC manages several DCBs. The electric power load (EL) of these DCBs consists of IT energy consumption, e.g., servers, memory, communication, and storage devices, as well as other ancillary energy consumption, e.g., air conditioning, lighting. Power usage efficiency (PUE) is generally used to illustrate the relationship between IT energy consumption and ancillary energy consumption, which is defined as the ratio of total energy consumption to IT energy consumption [
(3a) |
s.t.
(3b) |
(3c) |
(3d) |
(3e) |
(3f) |
(3g) |
(3h) |
(3i) |
(3j) |
(3k) |
(3l) |
(3m) |
(3n) |
(3o) |
(3p) |
(3q) |
(3r) |
(3s) |
If the uncertainties of PV generations and arriving IWs in the front-end servers are not considered, then , . However, their uncertainties would affect the decision-making of ISC. The detailed robust models are provided in Appendix A.
As the follower in the bi-level framework, DSO receives the net power from the upper-level model and optimizes the power flow to ensure the economic and secure energy supply under the TPT policy. It is assumed that the cost of the maximum demand in a settlement cycle such as a month is decided by a typical day. The distribution network is typically considered a radial network to be modeled by DistFlow [
(4a) |
s.t.
(4b) |
(4c) |
(4d) |
(4e) |
(4f) |
(4g) |
(4h) |
(4i) |
(4j) |
(4k) |
(4l) |
Note that the variables in the brackets are dual variables of constraints. The objective function (4a) aims at minimizing the total electricity cost of the DCP. Constraints (4b)-(4f) state the nodal active and reactive power balance. Constraint (4g) formulates the voltage drop of each branch. Constraint (4h) indicates SOCP relaxation. Constraint (4i) represents the limitation of grid power factors by ISO. Constraints (4j) and (4k) limit the magnitudes of bus voltages and branch currents, respectively. Constraint (4) indicates the maximum demand for grid power.
Based on the framework proposed in Section II, DLMPs derived from the dual multipliers of the lower-level distribution system operation model should be provided for consumers including all DCBs. According to the dual theorem of the convex SOCP problem [
(5a) |
s.t.
(5b) |
(5c) |
(5d) |
(5e) |
(5f) |
(5g) |
(5h) |
(5i) |
(5j) |
(5k) |
(5l) |
(5m) |
Equations (
Since the primal problem and the dual problem of the lower level are both convex, the strong duality equality holds:
(6) |
Then, the bi-level problem (2) can be equivalently transformed into the following single-level problem:
(7) |
Note that the above single-level problem has the bilinear terms , which cannot be solved directly by commercial solvers such as CPLEX and GUROBI. To deal with the bilinear terms, a binary expansion (BE) scheme is used to discretize one of the continuous variables and convert the non-linear problem into an MILP problem [
The basic idea of BE method in this paper is to approximate the continuous decision values by a set of discrete values , where is a non-negative integer that decides the number of slices. As satisfies the constraint (3q), the discrete approximation can be expressed as:
(8) |
where is a binary variable. Multiplying both sides of (8) by , and defining , we can obtain:
(9) |
(10) |
(11) |
where is large enough for constraint (10) and constraint (11) to be relaxed when and , respectively, e.g., . Then, (6) becomes:
(12) |
Finally, the single-level problem (7) is approximately equivalent to the following MISOCP problem, which can be solved by commercial solvers.
(13) |
This section uses a modified IEEE 33-bus radial distribution network with four DCBs located at buses 18, 22, 25, and 33 in four regions with different colors to illustrate the DCP power system, as shown in

Fig. 2 Structure of DCP power system with four DCBs.
To make the expression more concise, some indices of variables and constants are neglected in this subsection. The base voltage and base apparent power are considered to be 12.66 kV and 10 MVA, respectively. The power factor is limited to 0.8. The voltage limits at each bus are 0.9 p.u. and 1.1 p.u., respectively [

Fig. 3 Daily basic EL curve, front-end IW curve, and PV curve.

Fig. 4 Daily electricity prices.
Component | Parameter | Value | Component | Parameter | Value |
---|---|---|---|---|---|
EL | [4000, 4000, 3000, 3000] | BESS | [0.95, 0.95, 0.95, 0.95] | ||
[4, 4, 4, 4] requests per second | [0.95, 0.95, 0.95, 0.95] | ||||
[100, 100, 100, 100]W |
[0.1, 0.1, 0.1, 0.1] | ||||
[200, 200, 200, 200]W | [0.9, 0.9, 0.9, 0.9] | ||||
[1.35, 1.4, 1.4, 1.35] | [0.5, 0.5, 0.5, 0.5] | ||||
0.5 s | [100, 80, 80, 100]kW | ||||
[1.2, 1.2, 1.2, 1.2]MW | [250, 200, 200, 250]kWh | ||||
PV | [150, 120, 120, 150]kVA | SVG | [50, 50, 50, 50]kvar |
In an electricity market where information is completely private, every entity has to make the strategy individually, which could adversely affect the profits of others. On the contrary, in a completely public electricity market, it needs to collect all entities’ information in the centralized optimization, making it easy to be attacked when the information is leaked. To illustrate the advantages of the proposed equilibrium optimization in benefiting both DSO and ISC in terms of economy and privacy protection, three cases and their subcases are set for comparison, as summarized in
Case | Subcase | Entity | Price | Demand-side resource |
---|---|---|---|---|
Case 1 | Subcase 1.1 | DSO | TPT | None |
Subcase 1.2 | ISC | TPT | All | |
Case 2 | Subcase 2.1 | DSO | TPT | Without IW |
Subcase 2.2 | DSO | TPT | All | |
Subcase 2.3 | ISC | TPT | All | |
Case 3 | Subcase 3.1 | Both | TPT | All |
Subcase 3.2 | Both | DLMPs | All | |
Subcase 3.3 | Both | DLMPs | Without BESS | |
Subcase 3.4 | Both | DLMPs | Without IW |
1) Case 1: Individual Optimization
Subcase 1.1: DSO optimizes the power flow without considering the net power of all DCBs.
Subcase 1.2: ISC optimizes all DCBs without considering the park distribution network power flow, then DSO takes the net power of all DCBs and optimizes the power flow.
2) Case 2: Centralized Optimization
Subcase 2.1: DSO optimizes the power flow considering demand-side resources except for IWs in DCBs.
Subcase 2.2: DSO optimizes the power flow considering all demand-side resources in DCBs.
Subcase 2.3: ISC optimizes all demand-side resources in DCBs considering the park distribution network power flow.
3) Case 3: Equilibrium Optimization
Subcase 3.1: ISC games with DSO using the proposed strategy by the electricity prices from ISO. All demand-side resources are considered.
Subcase 3.2: ISC games with DSO using the proposed strategy by DLMPs. All demand-side resources are considered.
Subcase 3.3: ISC games with DSO using the proposed strategy by DLMPs. BESS is not considered a flexible resource.
Subcase 3.4: ISC games with DSO using the proposed strategy by DLMPs. IWs are not considered flexible resources.
In Case 1, the ISC optimizes four DCBs based on electricity prices from ISO. As shown in

Fig. 5 Bus voltages in Case 1 at time slot 18.

Fig. 6 Arriving IWs of DCBs in Case 1.

Fig. 7 Branch currents in Case 1 at time slot 18.
To ensure the distribution network security, i.e., without off-limit of voltages or congestion, the temporal and spatial demand responses are considered in Case 2 with centralized optimization. In terms of DSO, Subcase 2.1 mainly utilizes BESS as the temporal demand-side resource together with PV and SVG to support voltage and manage congestion, while Subcase 2.2 adds the IWs as flexible EL to provide spatial flexibility. In terms of ISC, Subcase 2.3 utilizes all the demand-side resources to minimize the electricity cost. Taking time slot 18 as an example, given the different objective functions compared with Subcases 2.1 and 2.2, ISC in Subcase 2.3 seeks less cost only if the bus voltages and branch currents are within the limit as shown in

Fig. 8 Bus voltages in Case 2 at time slot 18.

Fig. 9 Branch currents in Case 2 at time slot 18.
To protect the privacy of DCBs and alleviate the congestion, the proposed strategy is used in Case 3.
As shown in

Fig. 10 Bus voltages in comparison with Subcases 2.2, 3.1, and 3.2. (a) Bus voltages in a day. (b) Bus voltages at time slot 18.

Fig. 11 Branch currents in comparison with Subcases 2.2, 3.1, and 3.2. (a) Branch currents in a day. (b) Branch currents at time slot 18.

Fig. 12 DLMPs of active power in a day.
The ISC with four DCBs needs to pay additional costs for network loss, voltage support, and branch congestion to DSO when being powered with the electricity prices from ISO in Case 1, Case 2, and Subcase 3.1. These additional costs can be shared equally with basic EL on other buses. In contrast, these additional costs are already added to the DLMPs in Subcase 3.2, i.e., the shared extra cost is zero.
In terms of DSO, it is a precondition to keep all bus voltages within a safe level and make branches uncongested. The electric power costs of ISC and DSO with centralized optimization (Subcase 2.2) and equilibrium optimization (Subcases 3.1 and 3.2) are compared in
Stakeholder | Cost type | Cost (1 | ||
---|---|---|---|---|
Subcase 2.2 | Subcase 3.1 | Subcase 3.2 | ||
DSO | Grid power cost | 5.1047 | 5.4874 | 5.1223 |
Capacity cost | 0.5248 | 0.5639 | 0.5282 | |
Total cost | 5.6295 | 6.0513 | 5.6505 | |
Extra cost | 0.7606 | 1.2211 | 0.7711 | |
ISC | Net power cost | 2.0671 | 2.0284 | 2.3495 |
Shared extra cost | 0.2541 | 0.4021 | 0.0000 | |
Total cost | 2.3212 | 2.4305 | 2.3495 |
In terms of ISC, the centralized optimization in Subcase 2.2 is also the most economic strategy, of which the cost is 4.497% less than that in Subcase 3.1 and 1.205% less than that in Subcase 3.2, respectively. Compared with the increase in energy costs in Subcase 3.2, privacy is much more important for ISC. Take time slot 18 as an example, where the DLMP at time slot 18 is relatively higher than in other time slots due to the peak of EL, as shown in

Fig. 13 Net power of four DCBs in three subcases at time slot 18.

Fig. 14 Grid power of distribution network in three subcases.
In addition, although with the same TPT prices, the increased cost of ISC in Subcase 3.1 than that in Subcase 2.2 mainly results from the shared extra cost coming from the grid loss. However, the DLMP-based equilibrium game eliminates such drawbacks both for DSO and ISC. Compared with Subcase 3.1 without DLMPs, the proposed strategy in Subcase 3.2 saves 6.62% and 3.33% cost for DSO and ISC, respectively. In other words, the proposed strategy can incentivize more flexible users in the park to interact with the grid while preserving users’ privacy, to enhance the cost-effectiveness and operational security of the distribution network.
In equilibrium optimization, the types of demand-side resources can also affect the economy of both DSO and ISC. It should be noted that the capacity of BESS is not very large in practice in these case studies with economic consideration. In this modified distribution network, random dispatching of IWs would render the optimization infeasible. The proportion of arriving IWs is taken as 20%, 30%, 30%, and 20% of the base loads in four DCBs in Subcase 3.4, respectively. The comparison of electric power costs with different resources in Subcases 3.2, 3.3, and 3.4 are provided in
Stakeholder | Cost type | Cost (1 | ||
---|---|---|---|---|
Subcase 3.2 | Subcase 3.3 | Subcase 3.4 | ||
DSO | Grid power cost | 5.1223 | 5.1415 | 5.2100 |
Capacity cost | 0.5282 | 0.5311 | 0.5599 | |
Total cost | 5.6505 | 5.6726 | 5.7699 | |
Extra cost | 0.7711 | 0.8079 | 0.8080 | |
ISC | Net power cost | 2.3495 | 2.3954 | 2.4921 |
Shared extra cost | 0.0000 | 0.0000 | 0.0000 | |
Total cost | 2.3495 | 2.3954 | 2.4921 |
As shown in
The net power of DCBs is influenced by the arrival of IWs and PV generations, which are inherently uncertain in reality. According to the robust model in Appendix A, the parameters and control the robustness of the problem. For the sake of simplicity, it is assumed that and are taken as the same value . In addition, the uncertain parameter and parameter are seen as the same in this subsection. As shown in
Uncertainty (%) | Cost of DSO (1 | Cost of ISC (1 | ||||
---|---|---|---|---|---|---|
5 | 5.6505 | 5.7099 | 5.7682 | 2.3495 | 2.4326 | 2.4692 |
8 | 5.6505 | 5.7323 | 5.8224 | 2.3495 | 2.4556 | 2.5454 |
10 | 5.6505 | 5.7682 | 5.9123 | 2.3495 | 2.4692 | 2.6378 |

Fig. 15 Analysis of DLMPs and net power at time slot 18. (a) DLMPs with different uncertainties and . (b) Net power with different uncertainties and . (c) DLMPs with different Γ and 10% uncertainty. (d) Net power with different Γ and 10% uncertainty.
Under the same uncertainty, the increased value of the robustness control parameter means the solution is more conservative, thus worsening the scenario with a higher cost. Taking 10% uncertainty at as an example, as shown in
It is worth noting that if the level of uncertainty continues to increase, there may be no feasible solutions in the equilibrium optimization because some constraints of DSO may not be satisfied. For example, when uncertainty is 40% and , the optimization is infeasible. Under this circumstance, the price-incentivized demand response of DCBs is not suitable for the system.
The problem in the Subcase 3.2 consists of 21073 continuous variables and 864 binary variables. Massive binary variables might lead to computational difficulties. To demonstrate the scalability and computational performance of the proposed strategy, two additional test cases on the modified IEEE 69-bus system and 123-bus system are implemented. Detailed data can be found in [
The number of continuous and binary variables and the computational time with the proposed strategy are provided in
System | Number of DCBs | Number of continuous variables | Number of binary variables | Time (s) |
---|---|---|---|---|
IEEE 33-bus | 4 | 21073 | 864 | 3444.7 |
IEEE 69-bus | 4 | 42673 | 864 | 12790.5 |
IEEE 123-bus | 4 | 69673 | 864 | 14477.6 |
IEEE 33-bus | 5 | 21481 | 1080 | 4905.7 |
IEEE 33-bus | 6 | 26636 | 1296 | 6085.5 |
The paper develops a DLMP-based bi-level Stackelberg game framework between ISC and DSO in the DCP. At the upper level, ISC minimizes the electricity cost of all DCBs by dispatching IWs, BESS, SVG, and PV both temporally and spatially. The uncertainties of arriving IWs and PV generations for DCBs are considered and modeled using uncertainty sets. At the lower level, DSO minimizes the total electricity cost while satisfying the security-constrained operation of the distribution network. The model of proposed DLMP-based equilibrium optimization strategy is converted to a single-level MISOCP model using the strong duality theorem and binary expansion method.
A few numerical cases are studied on a modified IEEE 33-bus radial distribution network with four DCBs. Regarding DSO, the proposed strategy can stimulate the use of more flexible resources to support voltages and alleviate the distribution network congestion. Compared with centralized optimization, the DLMP-based equilibrium optimization strategy also reduces the cost of ISC by scheduling spatial and temporal demand-side resources with less exchanged information, which protects the privacy of the ISC. In addition, the proposed strategy can effectively accommodate the load-source uncertainties. Computational performance analysis has validated the scalability of the proposed strategy. The simulation results demonstrate that the proposed strategy offers a mutually beneficial solution for both DSO and ISC.
In future research, the cooperative game with an incentive-compatible mechanism among multiple ISCs in the distribution network will be an interesting topic.
Appendix
Appendix A presents robust optimization. and , which are the uncertainties of parameters and , are limited in the uncertainty set and , respectively. According to the robust theorem presented in [
(A1) |
(A2) |
where and are to control the robustness against the uncertainty of and , respectively.
References
R. Danilak. (2017, Dec.). Why energy is a big and rapidly growing problem for data centers? [Online]. Available: https://www.forbes.com/sites/forbestechcouncil/2017/12/15/why-energy-is-a-big-and-rapidly-growing-problem-for-data-centers/?sh=3c06f8845a30 [Baidu Scholar]
E. Masanet, A. Shehabi, N. Lei et al., “Recalibrating global data center energy-use estimates,” Science, vol. 367, no. 6481, pp. 984-986, Feb. 2020. [Baidu Scholar]
WikiLeaks. (2018, Oct.). Amazon Atlas. [Online]. Available: https://wikileaks.org/amazon-atlas/ [Baidu Scholar]
Starhub. (2022, Jul.). A trusted and reliable data center partner to meet your businesses’ evolving demands. [Online]. Available: https://www.starhub.com/business/products-and-services/hosting-my-business/data-centre.html [Baidu Scholar]
Z. Liu, H. Yu, R. Liu et al., “Configuration optimization model for data-center-park-integrated energy systems under economic, reliability, and environmental considerations,” Energies, vol. 13, no. 2, p. 448, Jan. 2020. [Baidu Scholar]
J. Zhao, A. Arefi, A. Borghetti et al., “Indices of congested areas and contributions of customers to congestions in radial distribution networks,” Journal of Modern Power Systems and Clean Energy, vol. 10, no. 3, pp. 656-666, May 2022. [Baidu Scholar]
N. C. Koutsoukis, D. O. Siagkas, P. S. Georgilakis et al., “Online reconfiguration of active distribution networks for maximum integration of distributed generation,” IEEE Transactions on Automation Science and Engineering, vol. 14, no. 2, pp. 437-448, Apr. 2017. [Baidu Scholar]
L. Bai, J. Wang, C. Wang et al., “Distribution locational marginal pricing (DLMP) for congestion management and voltage support,” IEEE Transactions on Power Systems, vol. 33, no. 4, pp. 4061-4073, Jul. 2018. [Baidu Scholar]
X. Yan, C. Gu, X. Zhang et al., “Robust optimization-based energy storage operation for system congestion management,” IEEE Systems Journal, vol. 14, no. 2, pp. 2694-2702, Jun. 2020. [Baidu Scholar]
B. S. K. Patnam and N. M. Pindoriya, “DLMP calculation and congestion minimization with EV aggregator loading in a distribution network using bilevel program,” IEEE Systems Journal, vol. 15, no. 2, pp. 1835-1846, Jun. 2021. [Baidu Scholar]
Z. Zhao, Y. Liu, L. Guo et al., “Locational marginal pricing mechanism for uncertainty management based on improved multi-ellipsoidal uncertainty set,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 4, pp. 734-750, Jul. 2021. [Baidu Scholar]
X. Yan, C. Gu, F. Li et al., “LMP-based pricing for energy storage in local market to facilitate PV penetration,” IEEE Transactions on Power Systems, vol. 33, no. 3, pp. 3373-3382, May 2018. [Baidu Scholar]
M. Chen, C. Gao, M. Song et al., “Internet data centers participating in demand response: a comprehensive review,” Renewable and Sustainable Energy Reviews, vol. 117, p. 109466, Jan. 2020. [Baidu Scholar]
Q. Sun, C. Wu, Z. Li et al., “Colocation demand response: joint online mechanisms for individual utility and social welfare maximization,” IEEE Journal on Selected Areas in Communications, vol. 34, no. 12, pp. 3978-3992, Dec. 2016. [Baidu Scholar]
China Daily. (2022, Mar.). Western regions to gain computing power. [Online]. Available: https://global.chinadaily.com.cn/a/202203/17/WS6 2329784a310fd2b29e51734.html [Baidu Scholar]
C. Jiang, C. Tseng, Y. Wang et al., “Optimal pricing strategy for data center considering demand response and renewable energy source accommodation,” Journal of Modern Power Systems and Clean Energy, vol. 11, no. 1, pp. 345-354, Jan. 2023. [Baidu Scholar]
H. Wang, J. Huang, X. Lin et al., “Proactive demand response for data centers: a win-win solution,” IEEE Transactions on Smart Grid, vol. 7, no. 3, pp. 1584-1596, May 2016. [Baidu Scholar]
Z. Yang, M. Ni, and H. Liu, “Pricing strategy of multi-energy provider considering integrated demand response,” IEEE Access, vol. 8, pp. 149041-149051, Aug. 2020. [Baidu Scholar]
J. Zhang, X. Huang, and R. Yu, “Optimal task assignment with delay constraint for parked vehicle assisted edge computing: a Stackelberg game approach,” IEEE Communications Letters, vol. 24, no. 3, pp. 598-602, Mar. 2020. [Baidu Scholar]
X. Wu and A. J. Conejo, “Distribution market including prosumers: an equilibrium analysis,” IEEE Transactions on Smart Grid, vol. 14, no. 2, pp. 1495-1504, Feb. 2022. [Baidu Scholar]
H. Sekhavatmanesh and R. Cherkaoui, “A novel decomposition solution approach for the restoration problem in distribution networks,” IEEE Transactions on Power Systems, vol. 35, no. 5, pp. 3810-3824, Sept. 2020. [Baidu Scholar]
S. Fattaheian-Dehkordi, M. Tavakkoli, A. Abbaspour et al., “An incentive-based mechanism to alleviate active power congestion in a multi-agent distribution system,” IEEE Transactions on Smart Grid, vol. 12, no. 3, pp. 1978-1988, May 2021. [Baidu Scholar]
Z. Chen, L. Wu, and Z. Li, “Electric demand response management for distributed large-scale internet data centers,” IEEE Transactions on Smart Grid, vol. 5, no. 2, pp. 651-661, Mar. 2014. [Baidu Scholar]
Z. Ding, L. Xie, Y. Lu et al., “Emission-aware stochastic resource planning scheme for data center microgrid considering batch workload scheduling and risk management,” IEEE Transactions on Industry Applications, vol. 54, no. 6, pp. 5599-5608, Nov.-Dec. 2018. [Baidu Scholar]
X. Yan, C. Gu, X. Zhang et al., “Robust optimization-based energy storage operation for system congestion management,” IEEE Systems Journal, vol. 14, no. 2, pp. 2694-2702, Jun. 2020. [Baidu Scholar]
T. Chen, Y. Zhang, X. Wang et al., “Robust workload and energy management for sustainable data centers,” IEEE Journal on Selected Areas in Communications, vol. 34, no. 3, pp. 651-664, Mar. 2016. [Baidu Scholar]
C. Duan, W. Fang, L. Jiang et al., “Distributionally robust chance-constrained approximate AC-OPF with Wasserstein metric,” IEEE Transactions on Power Systems, vol. 33, no. 5, pp. 4924-4936, Sept. 2018. [Baidu Scholar]
Z. Yuan, P. Li, Z. Li et al., “Data-driven risk-adjusted robust energy management for microgrids integrating demand response aggregator and renewable energies,” IEEE Transactions on Smart Grid, vol. 14, no. 1, pp. 365-377, Jan. 2023. [Baidu Scholar]
D. Bertsimas and M. Sim, “The price of robustness,” Operations Research, vol. 52, no. 1, pp. 35-53, Feb. 2004. [Baidu Scholar]
J. Wei, Y. Zhang, J. Wang et al., “Distribution LMP-based demand management in industrial park via a bi-level programming approach,” IEEE Transactions on Sustainable Energy, vol. 12, no. 3, pp. 1695-1706, Jul. 2021. [Baidu Scholar]
J. Wan, X. Gui, R. Zhang et al., “Joint cooling and server control in data centers: a cross-layer framework for holistic energy minimization,” IEEE Systems Journal, vol. 12, no. 3, pp. 2461-2472, Sept. 2018. [Baidu Scholar]
T. Xu, T. Ding, O. Han et al., “Counterpart and correction for strong duality of second-order conic program in radial networks,” IEEE Transactions on Power Systems, vol. 37, no. 5, pp. 4117-4120, Sept. 2022. [Baidu Scholar]
W. Liu, S. Chen, Y. Hou et al., “Optimal reserve management of electric vehicle aggregator: discrete bilevel optimization model and exact algorithm,” IEEE Transactions on Smart Grid, vol. 12, no. 5, pp. 4003-4015, Sept. 2021. [Baidu Scholar]
G. Chen, H. Zhang, H. Hui et al., “Scheduling thermostatically controlled loads to provide regulation capacity based on a learning-based optimal power flow model,” IEEE Transactions on Sustainable Energy, vol. 12, no. 4, pp. 2459-2470, Oct. 2021. [Baidu Scholar]
Shanghai Municipal People’s Government. (2020, Dec.). Notice of Shanghai Municipal Development and Reform Commission on reducing electricity prices for large industries in Shanghai. [Online]. Available: https://www.shanghai.gov.cn/nw49248/20201204/82b0c749089345e1aa55f68672b9ebbd.html [Baidu Scholar]
Z. Yang. (2022, May). Optimal DLMP-based equilibrium dispatching strategy of spatial-temporal demand-side resources in data center park. [Online]. Available: https://dx.doi.org/10.21227/axfq-bq57 [Baidu Scholar]