Abstract
The variability of the output power of distributed renewable energy sources (DRESs) that originate from the fast-changing climatic conditions can negatively affect the grid stability. Therefore, grid operators have incorporated ramp-rate limitations (RRLs) for the injected DRES power in the grid codes. As the DRES penetration levels increase, the mitigation of high-power ramps is no longer considered as a system support function but rather an ancillary service (AS). Energy storage systems (ESSs) coordinated by RR control algorithms are often applied to mitigate these power fluctuations. However, no unified definition of active power ramps, which is essential to treat the RRL as AS, currently exists. This paper assesses the various definitions for ramp-rate RR and proposes RRL method control for a central battery ESS (BESS) in distribution systems (DSs). The ultimate objective is to restrain high-power ramps at the distribution transformer level so that RRL can be traded as AS to the upstream transmission system (TS). The proposed control is based on the direct control of the ΔP/Δt, which means that the control parameters are directly correlated with the RR requirements included in the grid codes. In addition, a novel method for restoring the state of charge (SoC) within a specific range following a high ramp-up/down event is proposed. Finally, a parametric method for estimating the sizing of central BESSs (BESS sizing for short) is developed. The BESS sizing is determined by considering the RR requirements, the DRES units, and the load mix of the examined DS. The BESS sizing is directly related to the constant RR achieved using the proposed control. Finally, the proposed methodologies are validated through simulations in MATLAB/Simulink and laboratory tests in a commercially available BESS.
PHOTOVOLTAICS (PVs) and wind turbines are currently the two most popular distributed renewable energy sources (DRESs). Nevertheless, despite their highly beneficial nature and the ever-decreasing installation costs, their penetration into modern power systems causes a series of technical issues that are mainly related to the intermittent and volatile nature [
Concerning this issue, the European Union Commission regulation 2016/631 [
Additionally, it is worth noting that different RRL requirements are applied globally. For instance, the Australian Market Operator requests at least a 3%/min RRL [
Clearly, many different RRL requirements are applied globally. Another noteworthy fact is that although high-power ramps can be easily identified visually, in existing grid codes, no unified definition of active power ramps exists [
However, due to the ever-increasing DRES penetration, several small-scale DRESs are connected to DSs, which considerably affects overall grid stability [
Several methods have been used to smooth output power fluctuations of DRESs. These methods can be classified into three categories: ① moving average (MA) based methods [
Concerning optimal energy storage system (ESS) sizing for RRL, many research works are reported in the literature. Several studies propose ESS sizing methods based on the specific characteristics of DRES technology. For instance, in [
The scope of this paper is to develop a holistic method for provisioning of RRL as AS from DSs to the upstream TS. To achieve this objective, the following tasks are performed. The various definitions used to calculate active power ramps are first assessed. A method for controlling the BESSs installed at POI with TS is then developed, which aims to restrain the power ramps toward TS. The proposed control method is complemented by restoring the SoC. Finally, a novel parametric method for BESS sizing is proposed. The contributions of this paper can be summarized as follows.
1) The available definitions for computing active power ramps are compared, and the most suitable definition for RES applications is proposed.
2) A control method for central BESSs aiming at restraining high-power ramps toward TS is proposed. A unique advantage of the proposed control method is that it does not require averaging functions or filters. The proposed control method in fact restrains RRs by directly calculating and controlling the RR (imposed by the adopted grid code definition/requirement), thus ensuring that actual ramps will never exceed the maximum permissible limits.
3) A method for restoring SoC is developed. The novelty of this method is that the maximum SoC restoration time can be defined parametrically while always respecting the RRL of output power. Therefore, the method can be altered to satisfy the unique requirements of each storage technology. It also has a low computational burden since it is based on simple arithmetic operations without any control loops.
4) A novel parametric method for BESS sizing is proposed. The distinct advantage of the developed method is that the required BESS sizing for RRL is determined without the need for long-term measurements at POI. Accordingly, the proposed method is based solely on the power variation characteristics of the individual loads and DRESs connected to the examined DS. The proposed method receives the size of the interconnection transformer, the types and sizes of the DRESs and loads that are connected to the DS, and the maximum imposed by the TSO. Using these inputs and the representative generation and consumption profiles, the proposed method quickly computes the required BESS for RRL.
It is worth noting that the proposed methods for SoC restoration and BESS sizing present high novelty, as no similar methods have been reported so far. Finally, because the proposed methods for BESS control, SoC restoration, and sizing is built around the definition of RR, a complete framework that facilitates the provision of RRL as AS from DSs to the upstream TS is provided.
The remainder of this paper is structured as follows. Section II presents the definitions of RRL. Section III presents the control of central BESS for RRL, and Section IV describes the BESS control method for SoC restoration. Section V presents the proposed method for BESS sizing. Section VI describes the validation of the proposed method through simulations and laboratory tests. Finally, Section VII summarizes the major contributions and concludes the paper.
Although it is easy to visually identify ramps, there is no consensus on the accepted formal mathematical definition of a ramp event. Each paper or report uses a different computational method depending on the scope of the study. In [
One difficulty arises from the definition of the current and past instants. The time interval is crucial to define the ramp. Choosing a setting value depends on the type of ramp that must be detected. Another difficulty is that when using some definitions, only two discrete points are compared, which in turn neglects the power behavior inside the period between those points in time. In [
1) Definition 1 (Def. 1): a ramp event is considered to occur at the start of an interval if the magnitude of the increase or decrease in the power measured at time ahead of the interval is greater than a predefined threshold Tr:
(1) |
2) Definition 2 (Def. 2): a ramp event considers the minimum and maximum values of the measurements between the two endpoints (inclusive):
(2) |
Def. 2 avoids the issue of neglecting whatever occurs within the period between the present moment and the past moment. However, this results in the detection of ramps for longer periods. Besides, both definitions make it impossible to filter ramps caused by fast events. This can be observed in

Fig. 1 Power variation computation for a 1 min window according to three definitions. (a) . (b) . (c) .
3) Definition 3 (Def. 3): another definition that avoids these issues is described in [
(3) |
(4) |
A ramp event occurs if one of two following conditions are fulfilled:
(5) |
(6) |
Hence, it is obvious that the power variation is:
(7) |
A ramp is identified when or .
These three definitions are compared when applied to the variations in the PV power profiles shown in

Fig. 2 Comparison of RR definitions. (a) Variations in PV power profile. (b) Power variations measured using each definition.
Def. 2 clearly produces the highest variations. Def. 1, which compares two instant values separated by 60 s, produces slightly lower results. Def. 3 compares the current measurement with the average over the past 120 s, resulting in notably smaller power variations. The plot on the right in
Definition | Number of periods with active ramp | Percentage of time (%) |
---|---|---|
Def. 1 | 7722 | 21.2 |
Def. 2 | 12714 | 34.9 |
Def. 3 | 6294 | 17.3 |
In this paper, Def. 3 is proposed as the most suitable for calculating ramp-ups and ramp-downs. Using the mean value in a rolling window as the past value produces a more robust RR calculation that is less affected by the instantaneous value of the power at the start of the interval. Nevertheless, for the remainder of the papers, Def. 1 is used for the following reasons: ① most of the existing grid codes adopt Def. 1 to compute the RR since calculating only the power difference between the two instants is more straight-forward; ② Def. 1 is more sensitive in detecting high-power ramps; ③ if the length of the rolling window is close to zero, Def. 3 is equivalent to Def. 1. Thus, if RRL is achieved using Def. 1, it is ensured that RRL is also attained by Def. 3. Def. 2 is not considered as a suitable choice since it does not provide any means of filtering ramps caused by fast events.
To comply with the TSO-imposed RRL, the integration of a central BESS is proposed, which is located near the DS transformer (DST) so as to provide RRL as AS to the upstream TS. RRL is provided as long as the measured RR at POI is less than the maximum permissible value. In this sense, the BESS control should generate a power profile for specific selectable RR. We propose a more suitable method for directly controlling RR of DRES output power. This is critical because all grid codes on RRL are expressed by . At this point, we should note that the use of the maximum RR as a parameter in the BESS controller ensures that the proposed method is directly applicable to all requirements irrespective of the RR definition used. The clear advantage of the proposed method over others that use an LPF or MA function is that, in the latter cases, no clear relationship exists between the cutoff frequency of the LPF or the time interval of the averaging function with the required RRL. In addition, by properly selecting , it is possible to absorb any high-power variations, which appear between the start and end points of the analysis window.
The topology and the overall control scheme of BESS RR are depicted in

Fig. 3 Topology and overall control scheme of BESS RR.

Fig. 4 Main control block for producing smoothed active power profile.
An effective ESS should be complemented by SoC restoration control. The aim of this control is to restore the SoC to a predefined range, so that the BESS is always capable of smoothing ramp-ups and ramp-downs. This paper proposes a novel SoC restoration control method, which aims to restore SoC to 50% without violating the maximum RRL. To achieve this, the proposed SoC restoration control method modifies by adding/subtracting , as shown in

Fig. 5 Proposed control and value of dead-band.
can be calculated as:
(8) |
(9) |
(10) |
is set equal to half the total BESS capacity. Following the deactivation of the SoC control, the BESS power will not instantly become zero, but will continue decreasing with the same RR until it becomes zero. The time interval between the deactivation of the SoC control and the moment at which the PBESS becomes zero determines the dead-band :
(11) |
(12) |
Thus, the recovery control is deactivated at the SoC level of . Without this dead-band, SoC oscillates infinitely around the reference SoC. The novelty of the proposed control method is that: ① it is embedded in the RR control method, and therefore, the maximum RR is always respected; ② the maximum SoC restoration time is calculated based on the BESS energy and desired RR and then inserted into the control method; in this way, it can be predetermined; and ③ the computation burden is really low since it is based on simple arithmetic operations.
The proposed BESS sizing method considers a DS consisting of both DRES units and loads. This provides a fast way to estimate the required size without the need for long-term measurements at POI, which is based on the power variation characteristics of individual loads or DRESs. Therefore, a set of parameters, e.g., , , , , , and RRM, is identified that affects the BESS sizing.
, , and can be easily identified, since they are known parameters. Nevertheless, the values of , , and are to be defined based on the typical load and DRES profiles. The physical meanings of and are that the load (or DRES) power for most of the time within a year, e.g., 99% of the time, does not vary from zero up to the nominal power but rather remains within a range equal to or . To derive the analytical expression for estimating the required BESS sizing, a 4-step method is used, which is explained in detail as follows. Note that

Fig. 6 BESS sizing methodology.
Step 1: the rated power of DST and the installed DRES are and , respectively. The worst-case scenario regarding the power variation at the POI is a theoretical step change equal to , as shown in
(13) |
where is a function of , and expresses the DRES penetration in relation to the rated power of the DST (), which varies from 0 to 1. The RRL is calculated as:
(14) |
Step 2: it is considered that the load within the DS does not vary from zero to the maximum installed power. Step 2 is illustrated schematically in
(15) |
Step 3: the real power variation is considered not to be in the form of a step change but rather that of a ramp with the maximum rate equal to RRM, as shown in
(16) |
Step 4: finally, since the BESS must be able to absorb or release energy at any time, the total energy of the BESS is twice the energy calculated from (16) and is calculated as:
(17) |
To calculate the maximum power that the BESS must provide to perform RR control, it is necessary to calculate the maximum power mismatch that might appear while varies with RRM and with as:
(18) |
, , and significantly depend on the type and size of the DRES and load. Therefore, in this paper, a parametrical analysis based on real DRES and load data is presented.
Type of load | RRM,min(%/min) | RRM,max(%/min) | ||||
---|---|---|---|---|---|---|
Domestic load | 0.87 | 0.94 | 50 | 60 | ||
Industrial load | 0.57 | 0.65 | 25 | 35 | ||
PV | 0.31 | 0.48 | 30 | 40 | ||
WTG | 0.23 | 0.26 | 55 | 65 |
In
(19) |
(20) |
(21) |
The proposed methods are validated through simulations in MATLAB/Simulink and laboratory tests. The laboratory configuration consists of a 12-kWh 3-ph BESS from Fenecon (model: Pro 9-12), which uses lithium iron phosphate (LiFePO4) batteries. The grid is simulated using a Regenerative AC Grid Simulator (from Cinergia). Finally, an oscilloscope is used to capture the BESS voltage, current, and power. The active power reference signals of BESS are directly fed to the Pro 9-12 BESS via the Fenecon energy management system (FEMS) used to control online monitoring of BESS [
Initially, the proposed RR control is validated by means of simulations. The power at POI presents high fluctuation according to the yellow curve in

Fig. 7 Validation of RR control through simulations. (a) Simulation input power, smoothed reference power, and smoothed actual power. (b) BESS power.

Fig. 8 Validation of RR control by means of laboratory tests. (a) Input power, reference power, and smoothed actual power. (b) Reference BESS power and smoothed actual BESS power. (c) RR with and without proposed RR control.
To highlight the superiority of the proposed RR control, we compare its performance with the two most commonly used methods for RRL, i.e., LPF and MA. The most effective way to perform such a comparison is using a simple linear profile such as the one shown by

Fig. 9 Comparison of RRL methods. (a) Active power profile. (b) Calculated RR.
Through the proposed RR control, a constant RR is achieved, since RR is a control parameter. However, using the LPF or the MA method, there is a significant delay in the response because of the so-called “memory effect”. The parameters of these methods cannot be directly correlated with the desired maximum RR, which leads to extensive over-smoothing and eventually to a significantly larger BESS sizing and reduced battery lifespan.
In this subsection, the proposed control method for SoC restoration is tested. In this case, the step profile indicated by the yellow curve in

Fig. 10 Proposed SoC restoration control. (a) Input power and smoothed power. (b) BESS power. (c) SoC.
To evaluate the performance of the proposed method for BESS sizing, comparisons with a deterministic method are conducted. For this purpose, a detailed analytical simulation model in MATLAB/Simulink is implemented to generate power profiles at the POI (DS-TS). Further details concerning the analytical model can be found in [

Fig. 11 Power profile. (a) Domestic load profile. (b) Industrial load profile. (c) PV power profile. (d) WTG power profile.
Based on these power profiles, the total power at the POI can be synthesized to generate different test cases. The following test cases are considered and examined.
1) Case 1: 25% DRES penetration, 100% PV, 50% domestic loads, and 50% industrial loads.
2) Case 2: 50% DRES penetration, 100% PV, 50% domestic loads, and 50% industrial loads.
3) Case 3: 75% DRES penetration, 100% PV, 50% domestic loads, and 50% industrial loads.
4) Case 4: 50% DRES penetration, 50% PV, 50% WTG, and 100% domestic loads.

Fig. 12 Output power profile, BESS power, and hourly BESS energy for cases 1-4. (a) POI and BESS power for case 1. (b) Hourly BESS energy for case 1. (c) POI and BESS power for case 2. (d) Hourly BESS energy for case 2. (e) POI and BESS power for case 3. (f) Hourly BESS energy for case 3. (g) POI and BESS power for case 4. (h). Hourly BESS energy for case 4.
Case | BESS size estimation (kWh) | Smoothing percentage (%) | The maximum actual BESS size (kWh) |
---|---|---|---|
Case 1 | The minimum: 529 | 99.6 | 785 |
The maximum: 1043 | 100.0 | ||
Case 2 | The minimum: 1060 | 99.7 | 1929 |
The maximum: 2165 | 100.0 | ||
Case 3 | The minimum: 1993 | 99.5 | 4623 |
The maximum: 4164 | 99.8 | ||
Case 4 | The minimum: 1204 | 98.5 | 2372 |
The maximum: 2280 | 99.7 |
In addition to the BESS size estimation, the proposed method provides the means for estimating the BESS converter power rating. The respective results are presented in
Case | BESS power estimation (kW) | Percentage of time within a year (%) | Actual BESS power (kW) |
---|---|---|---|
Case 1 | 22.333 | 99.8 | 22.54 |
Case 2 | 25.363 | 100.0 | 24.82 |
Case 3 | 40.200 | 99.8 | 41.87 |
Case 4 | 37.116 | 99.3 | 43.48 |
The proposed method is proven to be accurate and be a useful tool for estimating the BESS size and the respective costs during the project design phase. The significance of the proposed method stems from the fact that the BESS size can be estimated by determining only the mixture of load and DRES. Since in this paper, RRL is considered as AS provided at the TS level and not as a system support function, the capacity estimation is rather on the safe side. The BESS size and estimated power rating can be further reduced if a simultaneity factor is used. However, this is not considered in this paper.
In this paper, a holistic method is proposed for the provision of RR control as AS from DS to the upstream TS. To achieve this objective, methodologies for sizing and properly controlling a central BESS are proposed. Specifically, various definitions included in the grid codes for identifying and measuring a ramp event are presented and compared. The RR control method proposed in this paper is based on the control of , which is adapted to the RR definition and requirements, ensuring that the actual ramp will never exceed the maximum limits imposed. In addition, the RR control is complemented with a method for restoring the SoC. The novelty of this method is that the maximum SoC restoration time can be parametrically defined, while always respecting the output power RRL. Therefore, it can be combined with the proposed control method. Furthermore, it can be adjusted to the unique characteristics of each storage technology. Finally, a novel parametric method for estimating the required BESS capacity and the power rating of the BESS converter is proposed.
The applicability of the proposed method for RRL control is validated through simulations and laboratory experiments, and comparisons with conventional methods are performed. Validation results reveal that the proposed method for RRL control can efficiently restrain RRs. The proposed method outperforms conventional methods based on LPF and MA. In addition, the proposed method for BESS sizing can correctly identify the size of the required BESS without using long-term measurements at the POI, which are difficult to obtain.
Our analysis verifies that the proposed method constitutes a holistic method that can be used to facilitate the provision of RRL as AS from DS to TS. Through the proposed method, RRL can be integrated into future AS markets as a tradable quantity.
Nomenclature
Symbol | —— | Definition |
---|---|---|
—— | Energy absorbed-released for state of charge (SoC) restoration | |
—— | Energy absorbed-released for ramp-rate (RR) limitation (RRL) | |
—— | Actual power variation | |
—— | The maximum power variation for defining a high-power ramp event | |
—— | Charging-discharging power for SoC restoration | |
—— | Power variations computed with definitions 1, 2, and 3 | |
—— | Rate of change of active power | |
—— | SoC dead-band | |
—— | Time window for RR computation | |
—— | The maximum SoC restoration time | |
—— | Duration of rolling window (averaging time) | |
—— | Battery energy storage system (BESS) energy absorbed | |
—— | BESS energy released | |
—— | BESS capacity | |
—— | Distributed renewable energy source (DRES) power variation coefficient | |
—— | Photovoltaic (PV) power variation coefficient | |
—— | Wind turbine generator (WTG) power variation coefficient | |
—— | Domestic load power variation coefficient | |
—— | Industrial load power variation coefficient | |
—— | Load power variation coefficient | |
—— | DRES penetration level coefficient | |
L1, L2 | —— | Upper and lower bounds for ramp event |
p | —— | Instantaneous active power |
—— | BESS power | |
Pin | —— | Active power measurement at point of interconnection (POI) |
Pout | —— | Smoothed reference power |
Psmooth | —— | Smoothed active power |
, | —— | Active and reactive reference power |
RRL | —— | RRL |
—— | The maximum negative RRL | |
—— | The maximum positive RRL | |
—— | The maximum RR measured at POI | |
—— | The maximum RR of domestic load | |
—— | The maximum RR of industrial load | |
—— | The maximum RR of PV | |
—— | The maximum RR of WTG | |
—— | Rated power of distribution transformer | |
—— | DRES power | |
—— | Threshold for ramp event identification | |
u1 | —— | Portion of PV load in DRES mixture |
u2 | —— | Portion of WTG load in DRES mixture, |
w1 | —— | Portion of domestic load in load mixture |
w2 | —— | Portion of industrial load in load mixture, |
References
G. C. Kryonidis, E. O. Kontis, T. A. Papadopoulos et al., “Ancillary services in active distribution networks: a review of technological trends from operational and online analysis perspective,” Renewable and Sustainable Energy Review, vol. 147, p. 111198, Sept. 2021. [Baidu Scholar]
Y. Huo and G. Gruosso, “A novel ramp-rate control of grid-tied PV-battery systems to reduce required battery capacity,” Energy, vol. 210, p. 118433, Nov. 2020. [Baidu Scholar]
F. Blaabjerg, A. Sangwongwanich, and Y. Yang, “Chapter 6 – flexible power control of photovoltaic systems,” in Advances in Renewable Energies and Power Technologies, Amsterdam: Elsevier, 2018, pp. 207-229. [Baidu Scholar]
Y. Wang, N. Zhang, C. Kang et al., “An efficient approach to power system uncertainty analysis with high dimensional dependencies,” IEEE Transactions on Power Systems, vol. 33, no. 3, pp. 2984-2994, May 2018. [Baidu Scholar]
C. S. Demoulias, K.-N. D. Malamaki, S. Gkavanoudis et al., “Ancillary services offered by distributed renewable energy sources at the distribution grid level: an attempt at proper definition and quantification,” Applied Sciences–Basel, vol. 10, no. 20, pp. 1-36, Oct. 2020. [Baidu Scholar]
C. S. Demoulias, “Ancillary services provision in terminal distribution systems,” in Encyclopedia of Electrical and Electronic Power Engineering, Oxford: Elsevier, 2023, pp. 411-424. [Baidu Scholar]
Commission Regulation (EU). (2016, Apr.). Establishing a network code on requirements for grid connection of generators. [Online]. Available: https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=OJ:JOL_2016_112_R_0001 [Baidu Scholar]
ENTSO-E. (2018, Jan.). Automatic connection/reconnection and admissible rate of change of active power ENTSO-E guidance document for national implementation of conditions for automatic connection/reconnection after incidental disconnection. [Online]. Available: https://eepublicdownloads.entsoe.eu/clean-documents/Network%20codes%20documents/NC%20RfG/IGD_Conditions_for_automatic_reconnection_final.pdf [Baidu Scholar]
G. D’Amico, F. Petroni, and S. Vergine, “Ramp rate limitation of wind power,” Energies, vol. 15, no. 16, p. 5850, Sept. 2022. [Baidu Scholar]
Y. Zhang, Z. Duan, and X. Liu, “Comparison of grid code requirements with wind turbine in China and Europe,” in Proceedings of 2010 Asia-Pacific Power and Energy Engineering Conference, Chengdu, China, Mar. 2010, pp. 1-10. [Baidu Scholar]
K.-N. Malamaki, S. I. Gkavanoudis, U. Mushtaq et al. (2018, Aug.). D1.1 description of the metrics developed for the quasi-steady-state operation and report on the review of the respective current grid codes. [Online]. Available: https://cordis.europa.eu/project/id/764090/results [Baidu Scholar]
V. Gevorgian and S. Booth. (2013, May). Review of PREPA technical requirements for interconnecting wind and solar generation. [Online]. Available: https://www.nrel.gov/docs/fy14osti/57089.pdf [Baidu Scholar]
C. Bogdan-Ionut, K. Tamas, T. Remus et al., “Power ramp limitation capabilities of large PV power plants with active power reserves,” IEEE Transactions on Sustainable Energy, vol. 8, no. 2, pp. 573-581, Mar. 2017. [Baidu Scholar]
K. N. D. Malamaki, F. Casado-Machado, M. Barragan-Villarejo et al., “Ramp-rate limitation of distributed renewable energy sources via supercapacitors,” IEEE Transactions on Industrial Application, vol. 58, no. 6, pp. 7581-7594, Nov. 2022. [Baidu Scholar]
IEEE, “Contribution to bulk system control and stability by distributed energy resources connected at distribution network,” IEEE PES, New York, Tech. Rep. TR22, 2017. [Baidu Scholar]
S. Koohi-Kamali, N. Rahim, and H. Mokhlis, “Smart power management algorithm in microgrid consisting of photovoltaic, diesel, and battery storage plants considering variations in sunlight, temperature, and load,” Energy Conversion and Management, vol. 84, pp. 562-582, Aug. 2014. [Baidu Scholar]
T. Kanehira, A. Takahashi, J. Imai et al., “A comparison of electric power smoothing control methods for distributed generation systems,” Electrical Engineering in Japan, vol. 193, no. 4, pp. 49-57, Sept. 2015. [Baidu Scholar]
A. Saez-de-Ibarra, E. Martinez-Laserna, and D.-I. Stroe, “Sizing study of second life Li-ion batteries for enhancing renewable energy grid integration,” IEEE Transactions on Industrial Application, vol. 52, no. 6, pp. 4999-5008, Nov. 2016. [Baidu Scholar]
J. Sachs, B. Müller, K. Tom et al., “Filter-based PV power smoothing control for island hybrid energy systems with high PV penetration,” in Proceedings of 2014 IEEE International Conference on Automation Science and Engineering, New Taipei, China, Aug. 2014, pp. 872-877. [Baidu Scholar]
I. de la Parra, J. Marcos, M. García et al., “Control strategies to use the minimum energy storage requirement for PV power ramp-rate control,” Solar Energy, vol. 111, pp. 332-343, Jan. 2015. [Baidu Scholar]
I. de la Parra, J. Marcos, M. García et al., “Storage requirements for PV power ramp-rate control in a PV fleet,” Solar Energy, vol. 118, pp. 426-440, Aug. 2105. [Baidu Scholar]
S. Sukumar, M. Marsadek, K. Agileswari et al., “Ramp-rate control smoothing methods to control output power fluctuations from solar photovoltaic (PV) sources – a review,” Journal of Energy Storage, vol. 20, pp. 218-229, Dec. 2018. [Baidu Scholar]
K.-N. D. Malamaki, F. Casado-Machado, M. Barragan-Villarejo et al., “Ramp-rate control of DRES employing supercapacitors in distribution systems,” in Proceedings of 2021 International Conference of Smart Energy Systems and Technologies (SEST), virtual meeting, Dec. 2021, pp. 1-10. [Baidu Scholar]
J. Cao, W. Du, H. Wang et al., “Optimal sizing and control strategies for hybrid storage system as limited by grid frequency deviations,” IEEE Transactions on Power Systems, vol. 33, no. 5, pp. 5486-5495, Sept. 2018. [Baidu Scholar]
Y. Liu, W. Du, L. Xiao et al., “A method for sizing energy storage system to increase wind penetration as limited by grid frequency deviations,” IEEE Transactions on Power Systems, vol. 31, no. 1, pp. 729-737, Jan. 2016. [Baidu Scholar]
V. T. Nguyen and J. W. Smith, “Virtual capacity of hybrid energy storage systems using adaptive state of charge range control for smoothing renewable intermittency,” IEEE Access, vol. 8, pp. 126951-126964, Jan. 2020. [Baidu Scholar]
K. Lappalainen and S. Valkealahti, “Sizing of energy storage systems for ramp rate control of photovoltaic strings,” Renewable Energy, vol. 196, pp. 1366-1375, Aug. 2022. [Baidu Scholar]
D. Alvaro, R. Arranz, and J. A. Aguado, “Sizing and operation of hybrid energy storage systems to perform ramp-rate control in PV power plants,” International Journal of Electrical Power & Energy Systems, vol. 107, pp. 589-596, May 2019. [Baidu Scholar]
Y. Yang, S. Bremner, C. Menictas et al., “Battery energy storage system size determination in renewable energy systems: a review,” Renewable and Sustainable Energy Reviews, vol. 91, pp. 109-125, Aug. 2018. [Baidu Scholar]
H. Tahir, D.-H. Park, S.-S. Park et al., “Optimal ESS size calculation for ramp rate control of grid-connected microgrid based on the selection of accurate representative days,” International Journal of Electrical Power & Energy Systems, vol. 139, p. 108000, Jul. 2022. [Baidu Scholar]
A. Abbassi, M. A. Dami, and M. Jemli, “A statistical approach for hybrid energy storage system sizing based on capacity distributions in an autonomous PV/wind power generation system,” Renewable Energy, vol. 103, pp. 1-10, Apr. 2017. [Baidu Scholar]
M. Huber, D. Dimkova, and T. Hamacher, “Integration of wind and solar power in Europe: assessment of flexibility requirements,” Energy, vol. 69, pp. 236-246, May 2014. [Baidu Scholar]
K.-N. Malamaki, S. I. Gkavanoudis, S. Giazitzis et al. (2021, Jul.). D1.7 Final report (after feedback form lab tests) presenting: the reactive power control algorithm for converter-interfaced DRES/BESS, the analytical tool for parametric BESS sizing for low-frequency power smoothing and the analytical tool for the evaluation of the converter operational losses due to exchange of reactive power. [Online]. Available: https://cordis.europa.eu/project/id/764090/results [Baidu Scholar]
A. Shekhar, S. Venu, K.-N. Malamaki et al. (2021, Jul.). D6.2 report on the laboratory tests. [Online]. Available: https://cordis.europa.eu/project/id/764090/results [Baidu Scholar]