Abstract
With the increasing penetration of local renewable energy and flexible demand, the system demand is more unpredictable and causes network overloading, resulting in costly system investment. Although the energy storage (ES) helps reduce the system peak power flow, the incentive for ES operation is not sufficient to reflect its value on the system investment deferral resulting from its operation. This paper designs a dynamic pricing signal for ES based on the truncated strategy under robust operation corresponding to the network charge reduction. Firstly, the operation strategy is designed for ES to reduce the total network investment cost considering the uncertainties of flexible load and renewable energy. These nodal uncertainties are converted into branch power flow uncertainties by the cumulant and Gram-Charlier expansion strategy. Then, a time of use (ToU) pricing scheme is designed to guide the ES operation reflecting its impact on network investment based on the long-run investment cost (LRIC) pricing scheme. The proposed ToU LRIC method allocates the investment costs averagely to network users over the potential curtailment periods, which connects the ES operation with network investment. The curtailment amount and the distribution of power flow are assessed by the truncated strategy considering the impact of uncertainties. As demonstrated in a Grid Supply Point (GSP) distribution network in the UK, the network charges at the peak time reduce more than 20% with ES operation. The proposed method is cost-reflective and ensures the fairness and efficiency of the pricing signal for ES.
WITH the ambitious target to reduce CO2 emissions, the global renewable energy capacity is predicted to rise sharply to 43% of total installed capacity over the next five years [
The energy storage (ES) can help the network accommodate more renewable energy by shifting the peak over time and mitigating the uncertainties, which potentially defers the network investment [
In the severe case, there will be more curtailment in the system, bringing forward system reinforcement and increasing operation costs. The ES operation can directly impact the system investment decisions. Therefore, it is significant to set accurate pricing signals to incentivise the efficient use of existing networks. In distribution networks, the long-run incremental cost (LRIC), i.e., the charging for network cost, is widely used in the UK [
Although ES can enhance the capacity with a reduced investment cost of the system, it cannot receive sufficient incentives from the system operator. Therefore, it is significant to design effective and efficient network charges to promote ES. Currently, the pricing schemes are designed only for the traditional generation and load, which purely withdraw or inject power from/into power systems. Since the ES has both features of load and generation, the existing LRIC pricing scheme based on the impact of nodes on annual peak power flow of system is inappropriate to capture the ES operation in hours [
The contributions of this paper are concluded as follows.
1) The traditional flat-rate single-point LRIC is extrapolated into a ToU LRIC to ensure the fairness of the pricing scheme to network users by respecting time-variant impact on systems.
2) The truncated strategy based dynamic incentives guiding ES operation is designed to reduce the total network charges. Thus, the existing spare capacity of the system can effectively accommodate increasing renewable energy and loads.
3) A robust operation strategy is designed for ES to minimize the investment cost under uncertainties.
The rest of this paper is organized as follows. Section II designs the ES operation model to reduce the system LRIC. Section III designs a TOU LRIC for the renewable energy and loads. They are demonstrated on a local GSP distribution network in Section IV. Section V draws conclusions.
In this section, the ES is operated to reduce the system network charges, incentivise the efficient use of existing systems, and recover the investment from network users. The ES operation is designed to minimize the peak branch power flow under uncertainties, which is quantified by system LRIC reduction [
LRIC is a forward network pricing scheme, which is widely used in the UK. To accommodate more generation and demands and allocate the incurred network investment costs to users appropriately, the LRIC evaluates the network investment costs and then charges customers according to their incremental impact on system peak power flow via an incremental approach. This method reflects both the distance and utilization levels of each customer. In the LRIC scheme, the future investment cost is only related to the peak power flow and unused capacity of the system. Then, the LRIC is allocated to network users according to their contributions to the annual change of system peak power flow. The network investment horizon is calculated in (1) and (2) and the present value of the network is evaluated in (3).
(1) |
(2) |
(3) |
where is the capacity of branch ; is the peak power flow of branch l; is the number of years that power flow grows from to with a given load growth rate ; is the present value of the asset with discount rate ; and is the asset cost.
The incremental cost is conducted for the customer to evaluate its contribution to the change in the present value of the network. The investment horizon and present value are updated with nodal energy injection in (4) and (5), respectively. The change in the present value of branches is calculated in (6) and the network charge from branch is shown in (7). The sensitivity factor between nodal power injection and change of branch power flow [
(4) |
(5) |
(6) |
(7) |
(8) |
where and are the new reinforcement year and new present value of asset, respectively, which are affected by the nodal injection at node ; is the power flow change along the circuit due to the nodal injection ; is the incremental cost of branch over its lifespan due to the nodal injection; is the annuity factor; and is the sensitivity factor of branch power flow in the DistFlow model.
The objective of ES operation is to reduce the peak power flow to increase the penetration of renewable energy, which is reflected as the minimization of system LRIC. The objective function and constraints are listed as (9) and (10)-(12), respectively, which are derived from the traditional LRIC scheme. In (9), the total LRIC of the system is the summation of the nodal LRIC from nodes. In (10), the nodal LRIC of node is the summation of its network charges from L branches.
(9) |
s.t.
(10) |
(11) |
(12) |
where is the daily start-up SoC of ES; ( ) is the SoC of ES at time ; and are the energy amounts for ES charging and discharging at time , respectively; is the original power flow of branch at time without ES operation; is the power flow of branch at time with ES operation; and is the uncertainty set of probabilistic power flow calculated based on load and generation uncertainties by the cumulant and Gram-Charlier expansion strategy [
The constraints for branch power flow, SoC, and ES operation (i.e., charging or discharging) are listed as follows.
(13) |
(14) |
(15) |
(16) |
where and are the charging and discharging efficiencies of ES at time , respectively; is the sensitivity factor of branch power flow at time ; and is an integer indicating the location of ES.
(17) |
(18) |
where is the ES capacity; and are the lower and upper limits of , respectively; and is the uncertainty set of .
(19) |
(20) |
(21) |
(22) |
where is the rate limit of ES operation; and is the binary integer, which ensures that there is no conflict between the charging and discharging processes.
Since the probabilistic power flow during the potential curtailment periods has a significant impact on the ES operation, the conservativeness should be considered when choosing the uncertainty set. Since the uncertainty range during non-potential curtailment periods is of relatively low importance, a budgeted uncertainty set is selected, which can lower the boundaries to achieve the extreme value during these periods. Since is decided by the end SoC of the previous day, it is designed as an interval set. Equations (
(25) |
(26) |
where is the forecasting value of power flow derived from the predicted load of branch at time ; is the power flow derived from the load uncertainty of branch at time ; and are the parameters representing the desired conservation level of the ES operator; is the forecasting value of the initial SoC; and is the deviation.
To speed up the solution time, (11) should be linearized. Derived from (11), can be described as:
(27) |
Because of the change of with respect to the change of is small (5% of the forecasting value), the exponent can be linearized to accelerate the calculation, as shown in

Fig. 1 Linearization of .
Therefore, can be further derived as:
(28) |
where is the linearization factor.
To capture the influence of ES on the network investment cost and guide its operation, a dynamic pricing scheme named ToU LRIC is designed based on LRIC. The ToU LRIC is designed for each branch to allocate the LRICs of branches from a single peak time to potential curtailment periods. Then, the ToU LRICs of branches are aggregated to the node based on the nodal contribution to the curtailment periods.
Originally, the LRICs are allocated to network users according to their contributions to annual peak power flow. However, although the peak value is the key driver for the reinforcement, the investment can be deferred if the curtailment of load or generation is low. In year , the annual investment cost () equals annuity curtailment cost (), as shown in (29) and (30), which means the curtailment cost will be higher in the following year and the system should be reinforced.
(29) |
(30) |
where is the curtailment cost of branch l in year .
It is assumed that the annual power flow follows the normal distribution, and the variance of power flow and increase rate of load are constant. The probability distribution functions (PDFs) of annual power flows in the current year and year are shown in

Fig. 2 PDFs of annual power flows in current year and year .
The curtailment can be calculated by the PDF of the annual power flow in year , as shown in the shadow area in
(31) |
(32) |
(33) |
where is the peak power flow of branch e in year ; is the unit curtailment cost of branch ; is the total curtailment cost of branch ; is the curtailment amount of branch ; is the distribution function of ; and and are the mean and variance of the distribution of the annual power flow of branch in year .
As shown in
The power flow above the potential curtailment level will shoulder the investment cost in the current year. Therefore, the load level difference between and of branch can be derived as:
(34) |
where is the mean of the distribution of the annual power flow of branch in the current year.
Thus, in the current year, the potential curtailment level can be determined by applying the difference from the current peak power flow as (35). The power flow above the potential curtailment level is the potential curtailment in the current year.
(35) |
Therefore, the original LRIC price can be increased to the ToU LRIC of branch by extrapolating the allocation of the current LRIC from a single peak time to the potential curtailment periods. Therefore, by aggregating ToU LRIC of branch, the nodal ToU LRIC of node n can be calculated as:
(36) |
The ToU incentives for ES are determined by the difference of nodal ToU LRICs under original power flows and new power flows with ES operation. The ToU LRIC difference resulting from ES operation is the ToU incentive signal for ES, which is denoted as ToU LRICe.
The flow chart in

Fig. 3 Flow chart of whole process of proposed method.
The proposed pricing models with ES operation are demonstrated in a GSP distribution network in the UK, as shown in

Fig. 4 GSP area test system.
To simplify the analysis, the following assumptions are adopted: ① the loss of ES is 10%; ② the minimum and maximum SoC levels are 0.2 and 0.8, respectively; ③ the maximum charging and discharging rates are 2 MW/h with the capacity of 6 MWh; ④ the start-up SoC is ; ⑤ the uncertainty set of the load is assumed to be between of the predicted value.
Branches 11 and 24 have the largest capacity (50 MW), accommodating the renewable generation connected at busbars 1005 and 1013. The capacity of branch 23 is 6.5 MW, which connects busbars 1006 and 1007. The detailed branch data and parameters can be achieved from [
The ES operation is to minimize the system LRIC, which is determined by the deterministic and robust models. The difference between the results of these two models is analyzed and compared. In

Fig. 5 SoC of ES with deterministic and robust models.
With the deterministic model, ES charges from 00:00 to 11:00 and 15:00 to 16:00. The maximum charging rate is 1.0 MW/h at 00:00. The maximum discharging rate is 1.44 MW/h at 20:00. Correspondingly, the SoC achieves the maximum value of 0.8 at 12:00 and 18:00.
With the robust model, the charging and discharging periods are similar to those with the deterministic model. The maximum charging rate is 1.14 MW/h at 00:00. The discharging period is from 18:00 to 22:00 with the maximum discharging rate of 1.13 MW/h at 20:00. The start-up SoC is 0.25, which is a severe condition for ES operation. The SoC reaches 0.8 at 18:00 with the robust model. Because of the conservativeness of the robust model, the charging or discharging amount for ES is flatter.

Fig. 6 Power flow of branch 3 with deterministic and robust models in severe scenario.
Since the impact of ES is small on branch 23, the difference of the power flows with and without the ES operation is small. The robust and deterministic models can reduce the peak power flows to 7.64 MW and 7.66 MW at 21:00, respectively.
The differences in the impact of the robust and deterministic models on the reduction of peak power flow of different branches are shown in
Branch No. | Reduction difference (MW) |
---|---|
2 | 0.21 |
3 | 0.28 |
16 | -0.01 |
17 | -0.01 |
23 | 0.02 |
Note: the positive values mean the reduction of the peak power flow with the robust model is higher than that with the deterministic model and the negative ones mean the opposite.
Branch No. | Time horizon (year) | ||
---|---|---|---|
Scenario ① | Scenario ② | Scenario ③ | |
2 | 13.5 | 14.2 | 14.6 |
3 | 12.0 | 12.6 | 13.2 |
16 | 8.1 | 8.1 | 8.1 |
17 | 12.3 | 12.3 | 12.2 |
23 | 22.6 | 22.7 | 22.8 |

Fig.7 LRICs of branches to load at different busbars.
The total LRICs of D1006 and D1007 and the generation at busbar 1011 (denoted as G1011) are listed in
Scenario | LRIC () | ||
---|---|---|---|
D1006 | D1007 | G1011 | |
① | 9783.0 | 8502.6 | -8503.5 |
② | 9535.9 | 8423.1 | -8424.0 |
③ | 9411.0 | 8383.7 | -8384.6 |
Note: the positive values mean the loads should pay the use of network charges and the negative ones mean the peak power flow can be reduced and the generation will get paid.
To extrapolate the LRIC allocation from a single peak time to the ToU level, the potential curtailment level of each branch is shown in
Branch No. | Curtailment (MW) | Branch No. | Curtailment (MW) |
---|---|---|---|
1 | 9.6 | 13 | 8.0 |
2 | 18.9 | 14 | 10.4 |
3 | 19.7 | 15 | 10.3 |
4 | 5.6 | 16 | 8.7 |
5 | 7.6 | 17 | 8.1 |
6 | 2.9 | 18 | 3.4 |
7 | 2.2 | 19 | 3.4 |
8 | 3.4 | 20 | 3.6 |
9 | 3.4 | 21 | 3.6 |
10 | 3.2 | 22 | 7.8 |
11 | 24.1 | 23 | 6.3 |
12 | 8.7 | 24 | 8.1 |
The ToU LRICs of the nodes are aggregated from the ToU LRIC of the branches based on their contributions to the system peak power flow.

Fig. 8 ToU LRIC of branch 3 in a year.

Fig. 9 ToU LRIC of branch 3 on day 34.
The ToU LRICs of D1006 without and with ES operation are aggregated from branches, as shown in

Fig. 10 ToU LRICs of D1006. (a) Without ES operation. (b) With ES operation.
The original LRIC cannot reflect the ES operation due to the single peak time. The ToU LRIC improves this situation by extrapolating the single time point to multiple periods, which shows the dynamic incentives over its daily operation period. The incentives for ES operation are determined by the difference between the original ToU LRIC without ES operation and the ToU LRICe with ES operation at the node of ES location. On day 34, the incentives for ES operation are shown in

Fig. 11 Incentives for ES operation on day 34.
In this paper, a dynamic pricing scheme is designed for ES and network users based on LRIC. With the proposed robust optimization method, the time to reinforcement can be deferred by ES operation. Through extensive demonstration, the following conclusions are obtained.
1) The truncated strategy can accurately reflect branch curtailment and can efficiently quantify the curtailment amount under uncertainties.
2) The ToU LRIC is fairer for network users to share the investment cost and capture its impact on network investment.
3) The network charges at peak time is reduced by more than 20% with the ES operation, which is more efficient to allocate the network investment cost to network users.
4) The robust optimization based ES operation can produce a better performance to reduce the system LRIC under severe uncertainty conditions. It is beneficial for system operators to defer system investments, whilst accommodating more uncertain renewable energies. It also benefits load and renewable generation to have lower network charges.
References
I. E. Agency. (2021, Jun.). IEA: renewable electricity set to grow 40% globally by 2022. [Online]. Available: https://www.carbonbrief.org/iea-renewable-electricity-set-to-grow-40-globally-by-2022 [Baidu Scholar]
E. Mearns. (2021, Jun.). UK wind constraint payments. [Online]. Available: http://euanmearns.com/uk-wind-constraint-payments [Baidu Scholar]
S. Teleke, M. E. Baran, A. Q. Huang et al., “Control strategies for battery energy storage for wind farm dispatching,” IEEE Transactions on Energy Conversion, vol. 24, no. 3, pp. 725-732, Jun. 2009. [Baidu Scholar]
A. Shahmohammadi, R. Sioshansi, A. J. Conejo et al., “Market equilibria and interactions between strategic generation, wind, and storage,” Applied Energy, vol. 220, pp. 876-892, Nov. 2017. [Baidu Scholar]
N. Li and K. W. Hedman, “Economic assessment of energy storage in systems with high levels of renewable resources,” IEEE Transactions on Sustainable Energy, vol. 6, no. 3, pp. 1103-1111, Aug. 2015. [Baidu Scholar]
Y. Zhang, N. Rahbari-Asr, J. Duan et al., “Day-ahead smart grid cooperative distributed energy scheduling with renewable and storage integration,” IEEE Transactions on Sustainable Energy, vol. 7, no. 4, pp. 1739-1748, Jun. 2016. [Baidu Scholar]
D. Bertsimas and M. Sim, “The price of robustness,” Operations Research, vol. 52, no. 1, pp. 35-53, Feb. 2004. [Baidu Scholar]
A. Ben-Tal, L. El Ghaoui, and A. Nemirovski, Robust Optimization. Princeton, USA: Princeton University Press, 2009. [Baidu Scholar]
W. Zheng, W. Wu, B. Zhang et al., “Robust reactive power optimization and voltage control method for active distribution networks via dual time-scale coordination,” IET Generation, Transmission & Distribution, vol. 11, no. 6, pp. 1461-1471, Mar. 2017. [Baidu Scholar]
J. J. Roberts, A. M. Cassula, J. L. Silveira et al., “Robust multi-objective optimization of a renewable based hybrid power system,” Applied Energy, vol. 223, pp. 52-68, Apr. 2018. [Baidu Scholar]
H. Zhao, B. Wang, X. Wang et al., “Active dynamic aggregation model for distributed integrated energy system as virtual power plant,” Journal of Modern Power Systems and Clean Energy, vol. 8, no. 5, pp. 831-840, Sept. 2020. [Baidu Scholar]
L. Zhou, F. Li, C. Gu et al., “Cost/benefit assessment of a smart distribution system with intelligent electric vehicle charging,” IEEE Transactions on Smart Grid, vol. 5, no. 2, pp. 839-847, Mar. 2014. [Baidu Scholar]
H. Ye, J. Wang, and Z. Li, “MIP reformulation for max-min problems in two-stage robust SCUC,” IEEE Transactions on Power Systems, vol. 32, no. 2, pp. 1237-1247, May 2017. [Baidu Scholar]
S. Wang, K. Wang, F. Teng et al., “An affine arithmetic-based multi-objective optimization method for energy storage systems operating in active distribution networks with uncertainties,” Applied Energy, vol. 223, pp. 215-228, Sept. 2018. [Baidu Scholar]
Anu Singla, Kanwardeep Singh, Vinod Kumar Yadav et al., “Optimization of distributed solar photovoltaic power generation in day-ahead electricity market incorporating irradiance uncertainty,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 3, pp. 545-560, May 2021. [Baidu Scholar]
F. Li and D. L. Tolley, “Long-run incremental cost pricing based on unused capacity,” IEEE Transactions on Power Systems, vol. 22, no. 4, pp. 1683-1689, Oct. 2007. [Baidu Scholar]
U.S. Department of Energy. (2021, Jun.). Grid energy storage. [Online]. Available: https://energy.gov/2013 [Baidu Scholar]
R. de Sa Ferreira, L. A. Barroso, P. Rochinha Lino et al., “Time-of-use tariff design under uncertainty in price-elasticities of electricity demand: a stochastic optimization approach,” IEEE Transactions on Smart Grid, vol. 4, no. 4, pp. 2285-2295, Apr. 2013. [Baidu Scholar]
X. Yan, C. Gu, F. Li et al., “Network pricing for customer-operated energy storage in distribution networks,” Applied Energy, vol. 212, pp. 283-292, Feb. 2018. [Baidu Scholar]
A. Schellenberg, W. Rosehart, and J. Aguado, “Cumulant-based probabilistic optimal power flow (P-OPF) with Gaussian and gamma distributions,” IEEE Transactions on Power Systems, vol. 20, no. 2, pp. 773-781, May 2005. [Baidu Scholar]
M. E. Baran and F. F. Wu, “Network reconfiguration in distribution systems for loss reduction and load balancing,” IEEE Transactions on Power Delivery, vol. 4, no. 2, pp. 1401-1407, Apr. 1989. [Baidu Scholar]
L. Bai, J. Wang, C. Wang et al., “Distribution locational marginal pricing (DLMP) for congestion management and voltage support,” IEEE Transactions on Power Systems, vol. 33, no. 4, Jul. 2018. [Baidu Scholar]
X. Xu, J. Li, Z. Xu et al., “Enhancing photovoltaic hosting capacity—a stochastic approach to optimal planning of static var compensator devices in distribution networks,” Applied Energy, vol. 238, pp. 952-962, Jan. 2019. [Baidu Scholar]
P. Zhang and S. T. Lee, “Probabilistic load flow computation using the method of combined cumulants and Gram-Charlier expansion,” IEEE Transactions on Power Systems, vol. 19, pp. 676-682, Feb. 2004. [Baidu Scholar]
M. Fan, V. Vittal, G. T. Heydt et al., “Probabilistic power flow studies for transmission systems with photovoltaic generation using cumulants,” IEEE Transactions on Power Systems, vol. 27, pp. 2251-2261, Apr. 2012. [Baidu Scholar]
C. Gu, F. Li, and Y. He, “Enhanced long-run incremental cost pricing considering the impact of network contingencies,” IEEE Transactions on Power Systems, vol. 27, no. 1, pp. 344-352, Jul. 2012. [Baidu Scholar]
X. Yan, C. Gu, X. Zhang et al., “Robust optimization-based energy storage operation for system congestion management,” IEEE Systems Journal, vol. 14, no. 2, pp. 2694-2702, Aug. 2020. [Baidu Scholar]