Abstract
The purpose of active distribution networks (ADNs) is to provide effective control approaches for enhancing the operation of distribution networks (DNs) and greater accommodation of distributed generation (DG) sources. With the integration of DG sources into DNs, several operational problems have drawn attention such as overvoltage and power flow alteration issues. These problems can be dealt with by utilizing distribution network reconfiguration (DNR) and soft open points (SOPs). An SOP is a power electronic device capable of accurately controlling active and reactive power flows. Another significant aspect often overlooked is the coordination of protection devices needed to keep the network safe from damage. When implementing DNR and SOPs in real DNs, protection constraints must be considered. This paper presents an ADN reconfiguration approach that includes DG sources, SOPs, and protection devices. This approach selects the ideal configuration, DG output, and SOP placement and control by employing particle swarm optimization (PSO) to minimize power loss while ensuring the correct operation of protection devices under normal and fault conditions. The proposed approach explicitly formulates constraints on network operation, protection coordination, DG size, and SOP size. Finally, the proposed approach is evaluated using the standard IEEE 33-bus and IEEE 69-bus networks to demonstrate the validity.
THE efficiency and reliability of distribution networks (DNs) have been decreasing owing to the constant increase in electricity consumption. The performance of a DN becomes inefficient owing to the decrease in voltage and increase in power losses [
DG sources are grid-connected or standalone electric generation units located within DNs. The integration of DG sources into a DN leads to an improvement in the voltage profile, reliability amendments (such as service restoration and uninterrupted power supply), and enhanced efficiency [
In DNs, there are typically a few normally open points connecting nearby feeders. These normally open points (tie switches) can be closed (while opening other switches) to reshape the network topology [
Another solution to complementing DNR and DG sources is to employ power electronic devices. By placing these devices—specifically, soft open points (SOPs)—instead of normally open points in a DN, the network capacity can be more effectively used [
Several protection methodologies have been developed to limit the high DG penetration effects in DNs, utilizing both traditional and modified protection systems [
Reference [
In [
To the best of the authors’ knowledge, extremely limited research has been conducted on DNR with SOP integration while maintaining protection coordination to reduce power loss thus far. Rather, during the planning stages, DNR research has only focused on issues such as power losses, the voltage profile of each bus, and the size and placement of DG sources, whereas the impacts of protection systems are disregarded in the operational stage. Another noteworthy feature of the research is that it makes use of the existing protection systems (when determining the optimal network configuration and/or installing SOPs or DG sources in the DN) rather than investing in costly new protection equipment. This approach is consistent with the currently implemented real-world approach because changing the initial protective mechanism of a DN is both costly and technically complex. Furthermore, although the installation of SOPs in DNs does not require network reconfiguration, the current distributed protection system must be changed to allow these devices to cooperate with the SOPs. The simultaneous operation of the protection system with the SOPs has not been explicitly discussed before, and it is considered in this paper.
The remainder of this paper is organized as follows. In Section II, the model for SOPs is presented. Section III presents the mathematical problem formulation and constraints. and the methodology is presented in Section IV. Simulation results for IEEE 33-bus and IEEE 69-bus networks are discussed in Sections V and VI, respectively. Lastly, in Section VII, the conclusions are presented.
An SOP is a multipurpose power electronic device that replaces the tie-line switches between two buses in DNs as an active/reactive power flow control device. This paper utilizes a back-to-back VSC consisting of two insulated gate bipolar transistor (IGBT) based VSCs. On their DC sides, the VSCs are paired in series and share a common capacitor. Both VSCs generate voltage waveforms with the desired amplitude and phase angle on their own. This back-to-back form enables complete active power control through the DC link and an independent reactive power supply or intake at both VSC terminals [

Fig. 1 Power injection model for an SOP.
The terminal power injections of SOP are considered in this model, allowing the SOP to be directly coalesced into current power flow analysis. In this model, the SOP is regarded as a line between two feeders that can manage the magnitude and direction of the active power flow and control the reactive power but with different magnitudes and directions (,) with respect to the capacity and limits of the converters (). As a result, we can obtain:
(1) |
(2) |
(3) |
where and are the active power with different magnitudes and directions; is the active power loss of each converter in the
(4) |
(5) |
where is the loss coefficient of VSCs, which represents the internal power loss of individual components for SOP. The VSCs connected to the feeders restrict the
(6) |
(7) |
Under fault conditions, as suggested in [
The purpose of this paper is to determine the best configuration, DG size, and SOP location and control while guaranteeing that the existing protection devices continue to function properly in a coordinated manner. The objective function of this optimization process is defined to minimize the power loss of each line and the power losses of the connected VSCs.
(8) |
(9) |
where Plosses is the total active power loss in the DN; M is the number of branches; Zn is the impedance of line n; and In is the current flowing through line n. The control variables include the statuses of the switches (both tie and sectionalized) in the lines, the SOP location and control (the active power flow value and direction and the reactive power flow value injected or absorbed at both terminals), and the active power output of DG units into the DN.
After the DNR procedure, the network topology must be radial. This implies that all buses must be linked to the main substation and that there must be no network loops. Another constraint is the magnitudes of the voltages of the buses, which are usually set to be ±10% of the rated voltages. Because of security and thermal concerns, In should not surpass the limit of the branch current.
(10) |
(11) |
where , , and are the minimum voltage, bus voltage, and maximm voltage, respectively; and is the maximum current of line n.
To function properly during the DNR process, the operation and size of DG sources must be regulated by the following constraints.
The maximum and minimum capacities of the DG sources, i.e., and , respectively, restrict the DG size :
(12) |
(13) |
where is the load at bus n; NDG is the number of DG sources; Nbus is the number of buses; and PDG,i is the size of the
(14) |
The existence of DG sources and SOPs and the implementation of DNR cause the line current to change. The DG sources and SOPs in the DN help notably decrease power losses and enhance the voltage profile of each bus, but they could have adverse effects on the protection and coordination of the DN if no protection constraints are considered. If the new line current following a new configuration or the installation of SOPs surpasses the ratings of the protection devices installed in the network, they will trip and cut the supply of the protection zone. Miscoordination of the primary protection and backup protection device can also be a repercussion when the constraints of the protection are not considered with the DNR procedure.
To minimize erroneous tripping and protection blinding, the protection of the new configuration must be able to separate the faulty area. In practice, network operators prefer to avoid expensive expenditures by avoiding the modification of current protection measures [
Suppose that the branch current surpasses the pick-up current of the relay or recloser or the operating current of the fuse under normal operating conditions. To prevent the damage to equipment, the protection equipment must be able to isolate the overloaded region quickly. To consider overloaded conditions, the overload factor (OLF) is considered and formulated as:
(15) |
where Ip is the operational pick-up current of the protection device.
To prevent the operation failure under fault conditions, the minimum fault current must be greater than the rated Ip of the protection device. Owing to this constraint, the protection device can identify the problem and isolate the faulty area. The constraint avoids protection blindness, which would result in a portion of the DN being left uncovered and unprotected.
(16) |
The coordination among series-connected protection devices under fault conditions is necessary and has multiple criteria. It is essential to determine the main and backup functions of each protection device to avoid unnecessary outages in DNs. Furthermore, from the perspective of fault current alterations, the effects of DG sources and SOPs on the DN must be adequately considered. Four types of coordination among protection devices are examined: fuse-fuse, relay-fuse, relay-downstream, and relay-relay coordinations.
The primary fuse must act first to isolate the problem before the backup fuse may operate in the concept of protection coordination. The clearing time of the main fuse must be less than 75% of the minimum melting time (MMT) of the backup fuse.
(17) |
where is the maximum clearing time (MCT) of the main fuse; and is the MMT of the backup fuse.
A coordination time interval (CTI) is considered between the trip time of the downstream protection (primary protection) and the relay as the backup. If the main protection device fails, the CTI guarantees that the backup device will act and eradicate the fault within the shortest possible period, ensuring the selectivity as:
(18) |
where tfuse is the trip time of the downstream protection device; and top is the relay operating time. The operational characteristic or time-current characteristic (TCC) of the relay may be mathematically defined using the following equation, per IEC and ANSI/IEEE standards:
(19) |
where , , and L are the constants established by the standards defining different types of inverse time relays. According to (20), the term PSM denotes the plug setting multiplier, which is the ratio of the fault current to the pick-up current of the relay .
(20) |
The reclosers feature two trip modes: fast and delayed (slow) trip modes with varying speeds. The fast trip mode protects downstream fuses from temporary disturbances and faults. The delayed trip mode is configured as backup protection in the case where the fuses fail to operate. The coordination of the recloser setting is set to the initial network configuration, and the changes made by DNR may affect relay-downstream coordination. The following constraint must be used to guarantee recloser coordination with other protection devices in the optimization process to find the optimal configuration while the coordination constraint remains satisfied.
The coordination requirements of a downstream fuse and a recloser on the upstream side are as follows.
The MMT of the fuse must be at least k times longer than the time of fast operation tfast.
(21) |
Furthermore, the slow mode of the closer, , must be larger than the MCT of main fuse with a predesignated CTI.
(22) |
The basic guidelines for proper relay coordination can be summarized as follows.
Pair relays have the same operational characteristics in series with one another whenever it is possible. Ip needed to run the relay in front must always be equal to or less than the primary current required to operate the relay behind it. To ensure that the circuit breaker closest to the problem opens first, an adequate time interval is considered between the relays that control the circuit breakers in the DN. The CTI between each relay time setting must be sufficiently long to ensure that the upstream relays cannot operate before the circuit breaker closer to the fault location has tripped and cleared the fault [
(23) |
where and are the operation time of the backup and main relays, respectively.
The purpose of the proposed approach is to obtain the optimal network configuration, SOP placement and performance, and DG output while maintaining protection constraints. In this paper, the DG sources are assumed to be privately owned; therefore, their positions have been specified and fixed. Additionally, if a fault occurs at the end of a radial line, the DG may become an island and must be removed from the network, as specified by the IEEE 1547 standard. A flowchart and process framework of the proposed approach is shown in

Fig. 2 Flowchart and process framework of proposed approach.
To establish the value of the objective function, the backward/forward sweep power flow (BFLF) technique [
The proposed approach is validated with standard IEEE 33-bus and IEEE 69-bus networks.

Fig. 3 Single-line diagram of IEEE 33-bus network.
Although any protection scheme can be used to assess the practicality of the protection constraints, the positions of the protection devices are depicted according to [
A three-phase-to-ground fault is considered for the maximum fault current in the short-circuit calculation at the location of each protection device. However, regarding the minimum fault current, a line-to-line fault is in the protected region of the bus, where there is smaller fault current. In fault situations, the load current is not considered. The load flow analysis, rating of protection device, and operation time in initial network are listed in
Protection device | Current setting (A) | Load current (A) | The maximum short-circuit current (A) | MCT (s) | top |
---|---|---|---|---|---|
Relay | 316 | 210.35 | 5200 | ||
F1 | 30 | 18.10 | 4870 | 0.0168 | 0.317 |
F2 | 80 | 48.49 | 3619 | 0.0522 | 0.474 |
F3 | 80 | 50.58 | 1081 | 0.4457 | 4.095 |
F4 | 100 | 58.39 | 1914 | 0.2411 | 1.390 |
Five case studies are conducted using the IEEE 33-bus network. Cases 1 and 2 only incorporate DNR and are evaluated without SOP and DG integrations, whereas cases 3 and 4 are evaluated with SOP integration. Case 5 is tested with the simultaneous integration of SOPs and DG sources. Protection constraints are used in cases 2, 4, and 5, whereas they are not considered in cases 1 and 3.
Case 1 studies the implementation of DNR without protection constraints using PSO. The open switch (7, 9, 14, 32, 37) combinations, active power loss (139.55 kW), and the minimum voltage (0.9375 p.u.) of the buses are listed in
Protection device | Load current (A) | 25% overload (A) | The maximum fault current (A) | The minimum fault current (A) | Status |
---|---|---|---|---|---|
F1 (30 A) | 67.77 | 84.72 | 4861 | 466.73 | Open |
F2 (80 A) | 48.28 | 60.35 | 3619 | 1552.00 | Closed |
F3 (80 A) | 46.18 | 57.72 | 1078 | 800.00 | Closed |
F4 (100 A) | 10.55 | 13.19 | 1907 | 1714.00 | Closed |
The protection constraints are taken into account during optimization in case 2, and the results are summarized in
Protection device | Load current (A) | 25% overload (A) | The maximum fault current (A) | The minimum fault current (A) | Status |
---|---|---|---|---|---|
F1 (30 A) | 23.52 | 29.17 | 4861 | 736 | Closed |
F2 (80 A) | 48.45 | 60.56 | 3619 | 1552 | Closed |
F3 (80 A) | 46.96 | 58.69 | 1078 | 800 | Closed |
F4 (100 A) | 54.68 | 68.34 | 1907 | 535 | Closed |
Case 3 investigates the performance of the IEEE 33-bus network when implementing an SOP combined with DNR. Owing to its high cost, one SOP is considered in this paper and is installed in place of one of the tie-line switches. The addition of the SOP adds three additional control variables (P, Q1, and Q2) to the optimization problem. Each VSC in the SOP has the maximum capacity of 1 MVA. As mentioned in Section II, the SOP will trip almost instantly under fault conditions, which is why it is considered as an open switch in short-circuit calculations.
Open switch | Ploss (kW) | The minimum voltage (p.u.) | SOP performance |
---|---|---|---|
7, 9, 14, 36, SOP at 37 | 95.7 | 0.9545 |
MW, Mvar, Mvar |
The results in
Protection device | Load current (A) | 25% overload (A) | Status |
---|---|---|---|
F1 (30 A) | 64.14 | 80.18 | Open |
F2 (80 A) | 60.36 | 75.46 | Closed |
F3 (80 A) | 48.10 | 60.13 | Closed |
F4 (100 A) | 10.42 | 13.02 | Closed |
In case 4, the optimization procedure is performed in the same way as shown in case 3 with one distinction: protection constraints are considered, and all instances in which the safety restrictions are not retained will be removed. The results show that, for practical applications, the optimization with the protection constraints is preferable, as shown by the results in
Open switch | Ploss (kW) | The minimum voltage (p.u.) | SOP performance |
---|---|---|---|
10, 12, 17, 33, SOP at 37 | 116.7 | 0.947 |
MW, Mvar, Mvar |
Protection device | Load current (A) | 25% overload(A) | The maximum fault current (A) | The minimum fault current (A) | MCT (s) | trelay (s) |
---|---|---|---|---|---|---|
F1 (30 A) | 23.70 | 29.7 | 4877 | 876 | 0.0168 | 0.317 |
F2 (80 A) | 63.90 | 79.8 | 3630 | 1563 | 0.0522 | 0.474 |
F3 (80 A) | 53.10 | 66.3 | 1080 | 706 | 0.4660 | 4.090 |
F4 (100 A) | 46.26 | 57.8 | 1911 | 615 | 0.2460 | 1.390 |
Case 5 investigates the incorporation of DNR and an SOP into an ADN with protection constraints. Because electronically interfaced DG sources are restricted in their fault current contributions and are not subject to protection concerns, synchronous-machine-type DG sources are used in this paper. The DG sources are assumed to inject only active power. Three DG sources are considered, which are connected to buses 31, 32, and 33 [
Open switch | Ploss(kW) | The minimum voltage (p.u.) | DG output (MW) | SOP performance |
---|---|---|---|---|
10, 31, 33, 34, and SOP at 37 | 60.07 | 0.9746 |
(DG31), (DG32),
|
MW, Mvar, Mvar |
The fault-current level has increased owing to DG penetration. This increase is caused by the decreased fault impedances resulting from the parallel circuits created by the DG sources. The minimum fault current has also increased compared with those for previous cases, thus melting the fuse and isolating the faulty area in the network. The coordination between all protection devices still exists within the range of fault current. This demonstrates that the use of even a modest and low-rated SOP device instead of a tie switch substantially improves the overall network performance and outweighs its drawbacks.
The results in
Protection device | Load current (A) | 25% overload (A) | Under the maximum fault | Under the minimum fault | Status | ||||
---|---|---|---|---|---|---|---|---|---|
The maximum fault current (A) | MCT (s) | trelay (s) | The minimum fault current (A) | MCT (s) | trelay (s) | ||||
F1 (30 A) | 23.79 | 29.74 | 5953 | 0.015 | 0.317 | 1571 | 0.120 | 8.64 | Closed |
F2 (80 A) | 48.08 | 60.10 | 4597 | 0.038 | 0.492 | 1685 | 0.192 | 2.87 | Closed |
F3 (80 A) | 36.80 | 46.00 | 2866 | 0.076 | 4.620 | 3063 | 0.512 | 5.41 | Closed |
F4 (100 A) | 23.17 | 28.96 | 2991 | 0.108 | 1.532 | 1175 | 0.598 | 9.23 | Closed |

Fig. 4 Optimal configuration.
The grid (bus 1), DG31, DG32, and DG33 all send fault current to the fault location. The proposed approach also eliminates the impact of sympathetic tripping. When a fault occurs at F4, a large fault current from the DG source positioned on bus 31 might cause F3 to operate incorrectly, particularly if the DG capacity is large. However, the incorrect operation is avoided in this case since the DG size is optimized, and F4 may act as the primary protection owing to the protection constraints with a sufficient CTI, isolating the faulty location before the other protection mechanisms kick in. Compared with the initial configuration, the proposed approach considering protection restrictions, appropriate DG size, and SOP control has considerably increased the minimum bus voltage. The introduction of DNR, the DG sources, and the SOPs has resulted in a noticeable improvement in the bus voltage.
Type | Open switch | Ploss (kW) |
---|---|---|
Case 1 | 7, 9, 14, 32, 37 | 139.50 |
Case 2 | 11, 13, 32, 33, 37 | 181.10 |
Case 3 | 7, 9, 14, 36, SOP at 37 | 95.70 |
Case 4 | 10, 12, 17, 33, SOP at 37 | 116.70 |
Case 5 | 10, 31, 33, 34, SOP at 37 | 60.07 |
[ | 7, 9, 14, 32, 37 | 139.50 |
[ | 11, 13, 32, 33, 37 | 181.10 |
[ | 7, 9, 14, 36, SOP at 37 | 93.91 |
The IEEE 69-bus network is investigated next, with 69 buses, 68 selectionizing switches, and five tie switches (69, 70, 71, 72, 73). The initial configuration is presented in

Fig. 5 Initial configuration of IEEE 69-bus network with five switches.
Based on the initial configuration of the network, the positions of the protection devices are indicated in accordance with [
If the main and backup fuses and the recloser cannot segregate a fault, the main relay serves as the subsequent protection layer. Therefore, the main relay is coordinated with the slow mode of the recloser. The TDS of the relay is 0.9 s, whereas the TDS of the recloser is 0.08 s and 1.7 s in the fast and slow modes, respectively. For a recloser in the fast mode, the coordination factor k should be 1.25. A CTI of 0.2 s is considered to coordinate fuses with the slow mode of the recloser.
Moreover, the coordination of the relay with its downstream devices is achieved with the same CTI. With this setting, the protection devices in the initial configuration will function correctly and synchronously in the event of a system fault. Tables
Protection device | IL (A) | 25% overload (A) | If,max (A) | tfast (s) | MMT (s) | k | tslow (s) | MCT (s) | CTI |
---|---|---|---|---|---|---|---|---|---|
F6 (40 A) | 2.08 | 2.60 | 2019 | 0.0122 | 0.026 | 2.17 | 0.259 | 0.046 | 0.213 |
F7 (30 A) | 3.24 | 4.05 | 1674 | 0.0133 | 0.023 | 1.76 | 0.283 | 0.041 | 0.242 |
F8 (40 A) | 20.41 | 25.51 | 1674 | 0.0133 | 0.038 | 2.89 | 0.283 | 0.061 | 0.220 |
Protection device | IL (A) | 25% overload (A) | If,max (A) | The maxmum operation time(s) | trelay (s) | CTI |
---|---|---|---|---|---|---|
F1 (10 A) | 5.13 | 6.41 | 4557 | 0.0138 | 0.2482 | 0.2344 |
F2 (80 A) | 47.78 | 59.72 | 4553 | 0.0380 | 0.2485 | 0.2105 |
F3 (20 A) | 10.32 | 12.90 | 4557 | 0.0149 | 0.2482 | 0.2344 |
F4 (6 A) | 2.51 | 3.14 | 2909 | 0.0137 | 0.4527 | 0.4391 |
F5 (200 A) | 105.23 | 131.54 | 2848 | 0.1532 | 0.4676 | 0.3144 |
Recloser | 44.10 | 55.12 | 2848 | 0.2266 | 0.4676 | 0.2410 |
The results for case 6 are presented in
Open switch | (kW) | The minimum voltage (p.u.) | DG output (MW) | SOP performance |
---|---|---|---|---|
12, 13, 56, 69, SOP at 73 | 28.025 | 0.9784 |
0.298 (DG60), 1.200 (DG61), 0.202 (DG62) | MW, Mvar,Q2 = 0.49 Mvar |
Protection device | IL (A) | 25% overload (A) | (A) | (A) | k | CTI | Status |
---|---|---|---|---|---|---|---|
Relay (336 A) | 144.14 | 180.17 | 6003 | ||||
F1 (10 A) | 5.12 | 6.40 | 6002 | 986 | 0.230 | Closed | |
F2 (80 A) | 76.58 | 95.73 | 6000 | 249 | 0.216 | Open | |
F3 (20 A) | 27.70 | 34.63 | 6002 | 827 | 0.230 | Open | |
F4 (6 A) | 2.47 | 3.08 | 3377 | 2419 | 0.496 | Closed | |
F5 (200 A) | 3.09 | 3.87 | 3294 | 1938 | 0.411 | Closed | |
Recloser (67 A) | 23.19 | 28.98 | 3294 | 1519 | 0.302 | Closed | |
F6 (40 A) | 2.04 | 2.55 | 2229 | 1812 | 1.84 | 0.209 | Closed |
F7 (30 A) | 3.16 | 3.96 | 1815 | 1315 | 1.56 | 0.235 | Closed |
F8 (40 A) | 0 | 0 | 1815 | 827 | 2.56 | 0.218 | Closed |
According to the optimal operation results of IEEE 69-bus network with SOPs and DG source in
Open switch | Ploss (kW) | The minimum voltage (p.u.) | DG output (MW) | SOP performance |
---|---|---|---|---|
13, 45, 69, 72, SOP at 73 | 48.48 | 0.9742 |
0.20 (DG60), 0.39 (DG61), 0.91 (DG62) | MW, Mvar, Mvar |

Fig. 6 Optimal configuration of IEEE 69-bus network.
Protection device | Load current (A) | 25% overload (A) | Status |
---|---|---|---|
Relay (336 A) | 142.58 | 178.66 | Closed |
F1 (10 A) | 5.12 | 6.40 | Closed |
F2 (80 A) | 47.78 | 59.72 | Closed |
F3 (20 A) | 8.16 | 10.20 | Closed |
F4 (6 A) | 2.48 | 3.10 | Closed |
F5 (200 A) | 38.02 | 47.73 | Closed |
Recloser (67 A) | 39.78 | 49.88 | Closed |
F6 (40 A) | 2.06 | 2.57 | Closed |
F7 (30 A) | 3.20 | 4.01 | Closed |
F8 (40 A) | 17.51 | 21.90 | Closed |
Protection device | If,max (A) | tfast (s) | MMT (s) | k | tslow (s) | MCT (s) | CTI (s) |
---|---|---|---|---|---|---|---|
F6 (40 A) | 2642 | 0.0112 | 0.0157 | 1.4026 | 0.238 | 0.0330 | 0.205 |
F7 (30 A) | 2068 | 0.0121 | 0.0153 | 1.2671 | 0.257 | 0.0319 | 0.225 |
F8 (40 A) | 2068 | 0.0121 | 0.0254 | 2.1004 | 0.257 | 0.0448 | 0.212 |
Protection device | (A) | The maximum operation time (s) | trelay (s) | CTI |
---|---|---|---|---|
F1 (10 A) | 5668 | 0.0137 | 0.2443 | 0.2307 |
F2 (80 A) | 5665 | 0.0294 | 0.2445 | 0.2151 |
F3 (20 A) | 5668 | 0.0143 | 0.2443 | 0.2301 |
F4 (6 A) | 4276 | 0.0136 | 0.4227 | 0.4091 |
F5 (200 A) | 4231 | 0.0767 | 0.4355 | 0.3588 |
Recloser (67 A) | 4231 | 0.2189 | 0.4355 | 0.2166 |
This paper presents a comprehensive framework using a new power electronic device, SOP, to enable the most efficient system configuration for improved ADN utilization, mitigate the adverse effects of DG, and consider the existing protection restrictions. In the presence of DG sources, DNR may result in wasteful tripping, longer downtime, and equipment failure for DNs. This paper aims to determine the network topology with the lowest power loss while maintaining the coordination of protection devices. Protection restrictions in terms of the operation and coordination of protection devices are clearly specified without the need to change the current protection systems.
The proposed approach is validated using IEEE 33-bus and IEEE 69-bus networks. Simulation results show that DNR has an obvious impact on the protection system. When DNR is used without considering the protection limits, configurations that are not viable for use in real-world DNs are developed. Despite a higher power loss than the ideal design without the protection limitation, the proposed approach provides the best configuration, DG sizes, and SOP placement and control, thereby allowing protection devices to function correctly. In addition to the advantages mentioned above, SOP control and presence assist in determining the optimal reconfiguration and controlling power flow over the network to achieve the desired results. Since DG penetration is increasing on a daily basis and upgrading old protection systems is both costly and complicated, the recommended solution could assist in achieving the best possible performance of DNs.
References
M. Siavash, C. Pfeifer, A. Rahiminejad et al., “Reconfiguration of smart distribution network in the presence of renewable DG’s using GWO Algorithm,” IOP Conference Series: Earth and Environmental Science, vol. 83, no. 1, p. 012003, Jul. 2017. [Baidu Scholar]
W. Mohd, Dahalan, and H. Mokhlis, “Network reconfiguration for loss reduction with distributed generations using PSO,” in Proceedings of 2012 IEEE International Conference on Power and Energy (PECon), Kota Kinabalu, Malaysia, Dec. 2012, pp. 823-828. [Baidu Scholar]
V. Farahani, B. Vahidi, and H. A. Abyaneh, “Reconfiguration and capacitor placement simultaneously for energy loss reduction based on an improved reconfiguration method,” IEEE Transactions on Power Systems, vol. 27, no. 2, pp. 587-595, Feb. 2011. [Baidu Scholar]
A. F. Nematollahi, A. Dadkhah, O. A. Gashteroodkhani et al., “Optimal sizing and siting of DGs for loss reduction using an iterative-analytical method,” Journal of Renewable and Sustainable Energy, vol. 8, no. 5, p. 055301, Sept. 2016. [Baidu Scholar]
S. Jazebi, S. H. Hosseinian, and B. Vahidi, “DSTATCOM allocation in distribution networks considering reconfiguration using differential evolution algorithm,” Energy conversion and Management, vol. 52, no. 7, pp. 2777-2783, Jul. 2011. [Baidu Scholar]
I. Diaaeldin, S. A. Aleem, A. El-Rafei et al., “Optimal network reconfiguration in active distribution networks with soft open points and distributed generation,” Energies, vol. 12, no. 21, p. 4172, Nov. 2019. [Baidu Scholar]
S. Zhang, H. Cheng, D. Wang et al., “Distributed generation planning in active distribution network considering demand side management and network reconfiguration,” Applied Energy, vol. 228, pp. 1921-1936, Oct. 2018. [Baidu Scholar]
Q. Qi, J. Wu, L. Zhang et al., “Multi-objective optimization of electrical distribution network operation considering reconfiguration and soft open points,” Energy Procedia, vol. 103, pp. 141-146, Dec. 2016. [Baidu Scholar]
C. Wang, G. Song, P. Li et al., “Optimal siting and sizing of soft open points in active electrical distribution networks,” Applied Energy, vol. 189, pp. 301-309, Mar. 2017. [Baidu Scholar]
M. R. Dorostkar-Ghamsari, M. Fotuhi-Firuzabad, M. Lehtonen et al., “Value of distribution network reconfiguration in presence of renewable energy resources,” IEEE Transactions on Power Systems, vol. 31, no. 3, pp. 1879-1888, Aug. 2015. [Baidu Scholar]
M. Zarei and A. Zangeneh, “Multi-objective optimization model for distribution network reconfiguration in the presence of distributed generations,” International Transactions on Electrical Energy Systems, vol. 27, no. 12, pp. 1-18, Dec. 2017. [Baidu Scholar]
W. Cao, J. Wu, N. Jenkins et al., “Benefits analysis of soft open points for electrical distribution network operation,” Applied Energy, vol. 165, pp. 36-47, Mar. 2016. [Baidu Scholar]
Q. Qi and J. Wu, “Increasing distributed generation penetration using network reconfiguration and soft open points,” Energy Procedia, vol. 105, pp. 2169-2174, May 2017. [Baidu Scholar]
Y. Ahmed, Hatata, and A. Lafi, “Ant lion optimizer for optimal coordination of DOC relays in distribution systems containing DGs,” IEEE Access, vol. 6, pp. 72241-72252, Nov. 2018. [Baidu Scholar]
M. Norshahrani, H. Mokhlis, A. A. Bakar et al., “Progress on protection strategies to mitigate the impact of renewable distributed generation on distribution systems,” Energies, vol. 10, no. 11, p. 1864, Nov. 2017. [Baidu Scholar]
N. Bayati, A. Dadkhah, S. H. H. Sadeghi et al., “Considering variations of network topology in optimal relay coordination using time-current-voltage characteristic,” in Proceedings of 2017 IEEE International Conference on Environment and Electrical Engineering and 2017 IEEE Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Europe), Milan, Italy, Jun. 2017, pp. 1-5. [Baidu Scholar]
S. K. Bhattacharya and S. K. Goswami, “Distribution network reconfiguration considering protection coordination constraints,” Electric Power Components and Systems, vol. 36, no. 11, pp. 1150-1165, Oct. 2008. [Baidu Scholar]
B. Khorshid-Ghazani, H. Seyedi, B. Mohammadi-Ivatloo et al., “Reconfiguration of distribution networks considering coordination of the protective devices,” IET Generation, Transmission & Distribution, vol. 11, no. 1, pp. 82-92, Jan. 2017. [Baidu Scholar]
H. Zhan, C. Wang, Y. Wang et al., “Relay protection coordination integrated optimal placement and sizing of distributed generation sources in distribution networks,” IEEE Transactions on Smart Grid, vol. 7, no. 1, pp. 55-65, Apr. 2015. [Baidu Scholar]
M. Baranski and J. Voss, “Non-intrusive appliance load monitoring based on an optical sensor,” in Proceedings of 2003 IEEE Bologna Power Tech Conference Proceedings, Bologna, Italy, Jun. 2003, pp. 267-274. [Baidu Scholar]
M. N. A. Rahim, H. Mokhlis, A. H. A. Bakar et al., “Protection coordination toward optimal network reconfiguration and DG sizing,” IEEE Access, vol. 7, pp. 163700-163718, Nov. 2019. [Baidu Scholar]
V. Fathi, H. Seyedi, and B. M. Ivatloo, “Reconfiguration of distribution systems in the presence of distributed generation considering protective constraints and uncertainties,” International Transactions on Electrical Energy Systems, vol. 30, no. 5, pp. 1-25, May 2020. [Baidu Scholar]
M. B. Shafik, H. Chen, G. I. Rashed et al., “Adequate topology for efficient energy resources utilization of active distribution networks equipped with soft open points,” IEEE Access, vol. 7, pp. 99003-99016, Jul. 2019. [Baidu Scholar]
Q. Qi, J. Wu, and C. Long, “Multi-objective operation optimization of an electrical distribution network with soft open point,” Applied Energy, vol. 208, pp. 734-744, Sept. 2017. [Baidu Scholar]
W. Cao, J. Wu, N. Jenkins et al., “Operating principle of Soft Open Points for electrical distribution network operation,” Applied Energy, vol. 164, pp. 245-257, Feb. 2016. [Baidu Scholar]
A. Aithal, G. Li, J. Wu et al., “Performance of an electrical distribution network with soft open point during a grid side AC fault,” Applied Energy, vol. 227, pp. 262-272, Oct. 2018. [Baidu Scholar]
M. Kezunovic, “Fundamentals of power system protection,” The Electrical Engineering Handbook, Academic Press, pp. 787-803, Jan. 2005. [Baidu Scholar]
S. Kawambwa, R. Mwifunyi, D. Mnyanghwalo et al., “An improved backward/forward sweep power flow method based on network tree depth for radial distribution systems,” Journal of Electrical Systems and Information Technology, vol. 8, no. 1, pp. 1-18, Dec. 2021. [Baidu Scholar]
S&C Electric Company. (2022, Nov.). TCC fuse. [Online]. Available: https://www.sandc.com /en/products–services/products/positrol-fuse-links/#Product%20Details [Baidu Scholar]
R. S. Rao, K. Ravindra, K. Satish et al., “Power loss minimization in distribution system using network reconfiguration in the presence of distributed generation,” IEEE Transactions on Power Systems, vol. 28, no. 1, pp. 317-325, Jan. 2012. [Baidu Scholar]