Abstract
The increasing flexibility of active distribution systems (ADSs) coupled with the high penetration of renewable distributed generators (RDGs) leads to the increase of the complexity. It is of practical significance to achieve the largest amount of RDG penetration in ADSs and maintain the optimal operation. This study establishes an alternating current (AC)/direct current (DC) hybrid ADS model that considers the dynamic thermal rating, soft open point, and distribution network reconfiguration (DNR). Moreover, it transforms the optimal dispatching into a second-order cone programming problem. Considering the different control time scales of dispatchable resources, the following two-stage dispatching framework is proposed.
① The day-ahead dispatch uses hourly input data with the goal of minimizing the grid loss and RDG dropout. It obtains the optimal 24-hour schedule to determine the dispatching plans for DNR and the energy storage system. ② The intraday dispatch uses 15 min of input data for 1-hour rolling-plan dispatch but only executes the first 15 min of dispatching. To eliminate error between the actual operation and dispatching plan, the first 15 min is divided into three 5-min step-by-step executions. The goal of each step is to trace the tie-line power of the intraday rolling-plan dispatch to the greatest extent at the minimum cost. The measured data are used as feedback input for the rolling-plan dispatch after each step is executed. A case study shows that the comprehensive cooperative ADS model can release the line capacity, reduce losses, and improve the penetration rate of RDGs. Further, the two-stage dispatching framework can handle source-load fluctuations and enhance system stability.
WITH the establishment of the goals of “carbon emission peak and carbon neutrality goals”, a large number of flexible resources, such as renewable distributed generators (RDGs), energy storage systems (ESSs), and microgrids, have been connected to distribution systems, thus making such systems more flexible but uncertain with regard to the source, network, and load [
Scholars have conducted numerous studies on the uncertainties of ADSs by utilizing stochastic programming, robust optimization, and interval notation. Stochastic programming generally assumes that random variables obey a given probability distribution (for example, assuming that the WT and PV forecasting errors obey a normal distribution [
The flexibility of the adjustment to the network structure is improved with the connection of a feeder terminal unit, which can accomplish distribution network reconfiguration (DNR) [
The optimized operation of dispatchable resources in an AC/DC hybrid ADS occurs on different time scales and must be separately considered. For example, DNR and an ESS cannot be frequently implemented, typically at the hour level at best [
Functionality | DNR [ | SOP [ | DTR [ | AC/DC [ | Proposed model |
---|---|---|---|---|---|
Increased RDG accommodation | √ | √ | √ | √ | |
Reconfigurable architecture | √ | √ | |||
Real-time power control | √ | √ | √ | ||
Expanded transfer capability | √ | √ |
Difference | Reference | Proposed model |
---|---|---|
Single time scale |
[ | |
Day-ahead & real-time |
[ | |
Multiple time scales |
[ | √ |
Minimized network loss and RDG dropout (economic dispatch) |
[ | √ |
Minimized network loss and voltage fluctuation (safety dispatch) |
[ | √ |
1) A wide majority of papers, which focused on the network flexibility of AC/DC hybrid ADSs, did not build a comprehensive model, particularly considering the DNR, SOP, and DTR together, which may allow the ADS to be safer and more economic, and accept more RDGs.
2) The dispatching framework has not balanced the contradiction between economic and safety dispatching; in particular, it has not achieved a balance between the maximum number of accommodated RDGs and the voltage stability.
3) With the increase in dispatchable resources in AC/DC hybrid ADSs, the time scales of different resources and the dispatching framework need to be further refined. Moreover, the error between the actual operation and optimal plan caused by model mismatches must be solved using the framework.
Thus, a novel two-stage optimal dispatching framework for comprehensive cooperative AC/DC hybrid ADSs is proposed herein. The contributions of this study are summarized as follows.
1) A comprehensive cooperative ADS model that considers DNR, SOPs, DTR, and AC/DC hybridization is proposed. This model can release the line capacity, reduce losses, and improve the penetration rate of RDGs.
2) A novel two-stage framework for an AC/DC hybrid ADS, which considers the aforementioned dispatchable resources applied at different time scales, is introduced. The day-ahead dispatch outputs the hour-level optimization for DNR and the ESSs. The intraday dispatch provides a minute-level optimization of the remaining dispatchable resources. To further reduce the operation frequency of DNR, a time consolidation method based on Fisher segmentation is introduced. A threshold is set to check the difference between the day-ahead and intraday forecasts of the RDGs and the load to determine whether to start the intraday dispatch.
3) The intraday dispatch is decomposed into two parts, namely, the rolling-plan and real-time feedback dispatches, to overcome the deviation between the actual operation and optimization results, and accomplish economic and safety dispatching. The rolling-plan dispatch has the same objective (to minimize the network loss and RDG dropout) as the day-ahead dispatch but optimizes for the next hour instead of a day. The rolling-plan dispatch is only implemented for the first 15 min in the above optimal scheduling result and it continues to optimize for the next hour and rolls again. Once an overvoltage is detected in the next hour of the rolling-plan dispatch, the aforementioned plan is reoptimized through safety dispatching, i.e., minimizing the network loss and voltage fluctuation. Real-time feedback dispatch divides the 15 min operation in the rolling-plan dispatch into three steps for execution (5 min each). The goal of this execution strategy is to follow the rolling-plan dispatch and minimize changes in the decision variables. The optimized value is replaced with the measured result to form closed-loop feedback after each step is completed to allow eliminating the error in each step.
The remainder of this paper is organized as follows. In Section II, the two-stage dispatching framework for AC/DC hybrid ADSs is presented. In Sections III and IV, the details of the day-ahead and intraday dispatches and solutions are described, respectively. In Section V, simulation and discussion are presented. Finally, this paper is concluded in Section VI.
In consideration of the cost, lines with numerous DC sources can first be transformed into DC feeders, and some tie lines in an AC distribution system can be gradually replaced with SOPs. The connection between the AC and DC grids uses a VSC, as shown in

Fig. 1 Typical structure of an AC/DC hybrid ADS.
The DisFlow model [
(1) |
(2) |
s.t.
(3) |
(4) |
The power flow in the DC grid based on the DisFlow model [
(5) |
(6) |
s.t.
(7) |
(8) |
The variables have the same meanings as those in the AC grid, except for , which represents the power flow injected into the
(9) |
(10) |
(11) |
Equations (
RDGs, ESSs, and the SVC, which can be dispatched, are connected to the ADS. They should satisfy the following constraints, the details of which can be found in [
(12) |
(13) |
(14) |
(15) |
(16) |
(17) |
(18) |
(19) |
(20) |
Equations (
The power flow injected into the DC grid is the power flowing out of the AC grid through the VSC. Thus, the VSC model consists of an equivalent resistance, reactance, and ideal VSC, as shown in

Fig. 2 VSC model.
(21) |
(22) |
The VSC can control only any two of these quantities: the active power, reactive power, voltage on the AC side, and voltage on the DC side. The control [
The SOP, a flexible power electronic device, can be used as a dispatchable source to realize fast power control on both sides [
(23) |
(24) |

Fig. 3 Two-port SOP model.
The SOP controls two VSCs. In general, the control method is as follows. One VSC realizes DC voltage control, whereas the other VSC realizes power control, i.e., - control [
The maximum line capacity is typically calculated using a fixed set of conservative weather assumptions (STR value), which leads to conservative operational limits. If real-time weather conditions are considered, the maximum line capacity should be regarded as the independent constraint in (25), which is called the DTR value.
(25) |
Thus, (25) is the line capacity considering the DTR value. is not a decision variable but a variable based on micrometeorology. With large-scale access to RDGs, the line is more likely to be overloaded, and the use of DTR technology can potentially improve the practicality and flexibility of the capacity at certain special time (such as during overloading).
The variable is introduced to describe the on-off state of a branch, and a large number (M) [
(26) |
If , i.e., branch is closed, (26) equals (3). Otherwise, if , i.e., branch is opened, . Thus, (26) changes into . Considering that , herein, is set to balance the contradiction between the solution rate and the Big M method requirements. The current constraint is expressed as follows.
(27) |
Therefore, the decision variable for DNR is the topology.
Given that the topology after DNR should be radial, the limits of the radial topology are as follows.
(28) |
When power flows from node i to node j, , and node i is considered superior to node j. If the power flow is reversed, . If no power flow occurs between the nodes, . Thus, the first term limit is that only one of and can be 1. The second term limit is that all nodes except the one connected to the substation have only one superior node. The third term limit is that any node connected to the substation does not have a superior node.
Considering that the optimization operations of dispatchable resources in an ADS are applied at different time scales, herein, a two-stage dispatch framework is proposed, which contains day-ahead dispatch and intraday dispatch. This framework divides the time scale into hour (day-ahead dispatch) and minute (intraday dispatch) levels to meet the requirements of the controllable variables in the ADS at different time scales. The intraday dispatch (15 min) is divided into three execution steps (5 min each) to reduce the deviation between the actual operation and optimal plan. The framework is illustrated in

Fig. 4 Dispatching framework for AC/DC hybrid ADSs.
The day-ahead dispatch optimizes the operations for the next 24 hours using input data with a time slot of 1 hour . It maximizes the topology and other controllable variables, namely , by setting an economic goal (i.e., minimizing the system loss and RDG waste). To reduce the effect of DNR on the system, the day-ahead dispatch divides 24 hours into several periods, and each period only performs DNR.
Given that the forecasted data used as the input data for the day-ahead dispatch may be very close to the intraday input data (i.e., the fluctuations in the RDGs and load are small), the intraday dispatch is not required in that situation. Therefore, the framework performs a judgment every 15 min in day-ahead dispatch to determine whether the current moment enters the intraday schedule. This judgment is based on the difference between the day-ahead and intraday input data.
The intraday dispatch is divided into two parts: rolling-plan dispatch and real-time feedback dispatch [
The rolling-plan dispatch can optimize the remaining dispatchable resources in multiple stages; however, it only executes the optimization results of the first stage. For example, it optimizes the next 1 hour in four stages (each is a stage), as shown in
In addition, the framework refines the execution of the first stage, called the real-time feedback dispatch, to resolve the deviation of the actual operation from the plan. In the real-time feedback dispatch, the tie-line power between the ADS and upper grid follows the first step of the rolling-plan dispatch and minimizes the changes in the controllable variables. Finally, the real-time feedback dispatch replaces the optimized values with the measured data in 5 min, thus forming closed-loop feedback to reduce bias.
In this regard, the framework optimizes dispatchable resources into an appropriate time scale and minimizes the effect of uncertainty through the real-time feedback dispatch to ensure the economic and safe operation of the ADS. The details are presented in the following sections.
The forecasting data of the RDGs and load in a 1-hour time slot are used as input data for the day-ahead dispatch. Combined with the AC/DC hybrid ADS model presented in Section II-A, the day-ahead dispatch of the decision variables is obtained. In addition, the relaxation from the initial model to a second-order cone programming (SOCP) problem is presented in this section. Finally, time consolidation is proposed to reduce the DNR time.
An ADS can realize the active control of resources in a network and maximize RDG access. Thus, the objective is to minimize the network loss and RDG dropout as follows.
(29) |
(30) |
(31) |
Note that the losses of the VSC and SOP are not considered here. If they are considered, the loss (i.e., is only added to (29). Here, and are the loss coefficients of the SOP [
The day-ahead dispatch, i.e., (30), with the limits in (1), (3)-(5), (7)-(24), and (26)-(28), is a mixed-integer nonconvex and nonlinear problem. It can be transformed into an SOCP problem via convex relaxation [
1) The constraints in (4) and (8) can be relaxed to:
(32) |
(33) |
2) The capacity constraints of the VSC and SOP, i.e., (22) and (24), are changed into cone rotation constraints as follows.
(34) |
(35) |
Thus, the initial day-ahead dispatch is transformed into (36).
(36) |
This equation is an SOCP problem and can be solved using commercial software such as CPLEX and GUROBI.
If the DNR is considered hourly, finding a solution to (36) becomes time-consuming and affects the system frequency. If the changes in the RDG output and load between two consecutive hours are minimal, no DNR is required, thereby reducing the aforementioned effect and improving the solving rate. Thus, herein, time consolidation is conducted and DNR is performed at a divided time. Further, optimal merging is proposed at the temporal order using Fisher segmentation [
1) An equivalent load is determined. The forecast for the RDGs is regarded as a negative load and added to the power demand. The equivalent load is obtained as in the day-ahead dispatch. Here, is the equivalent load demand of the ADS between hours and.
2) Dispersion is determined. The equivalent loads are assumed to be divided into k segments, and is the set of time-dividing points, where . Thus, the equivalent loads are divided into , , , . The dispersion (called a similar diameter) between the equivalent loads within the
(37) |
(38) |
Essentially, the smaller the is, the smaller the dispersion in the data within a time segment will be.
3) Time division is determined. The segments, in which the dispersion in the equivalent load within each segment is the smallest and that between segments is the largest, are identified as follows.
(39) |
The forecasts of the RDGs and load in 15 min are used as the input data for the intraday dispatch. The dispatch for DNR and the ESSs is fixed with the day-ahead dispatching result; thus, the intraday decision variables are . The rolling-plan dispatch builds an optimal dispatching plan for for the next hour but only executes the first 15 min. The real-time feedback dispatch divides 15 min into three 5-min steps and uses the measured data as the input after each step to reduce the deviation between actual operation and the optimized dispatching plan.
The intraday rolling-plan dispatch smooths the large fluctuations in the RDGs and loads to achieve economic dispatch, which has the same objective as the day-ahead dispatch, as shown in (40). The differences between the two are as follows. ① The input data of the rolling-plan dispatch include a 15-min time slot, which is more accurate. ② The optimization period is 1 hour rather than 1 day, which is more suitable for the fluctuations in the RDGs and load. ③ The dispatch for DNR and the ESSs is not optimized in the rolling-plan dispatch.
(40) |
where is the optimization cycle, i.e., 1 hour in this study; and is the AC time slot of the rolling-plan dispatch, i.e., 15 min. The other variables are the same as those in (29).
In the rolling-plan dispatch, the overvoltage caused by the fluctuations in the RDGs must be solved because they become increasingly serious with the increase of RDG penetration [
(41) |
To maintain voltage stability, the determination of an overvoltage does not use a threshold [0.93,1.07] but a margin [
In this manner, the rolling-plan dispatch provides a four-step optimal plan for the next hour at 15-min intervals. To prevent disturbances from accumulating in the four steps, the rolling-plan dispatch only executes the first 15 min (first step) [
The severe fluctuations in the input data caused by sudden meteorological changes can be addressed by shortening the optimization cycle and time slot. However, the actual operation of an ADS may not be completely consistent with the optimized scheme because of acquisition and model errors. Therefore, the real-time feedback dispatch decomposes the first step of the rolling-plan dispatch (15 min) into three 5-min steps and feeds the measured data back to each step, thereby dynamically adjusting the decision variables.
The real-time feedback dispatch is not meant to change the rolling-plan dispatch; instead, it is meant to adjust the output of the decision variables within a shorter time scale on the basis of the measured data. Therefore, the objective of each 5-min step is to minimize the changes in the decision variables and reduce the effect on the upper power grid caused by fluctuations, which is shown as follows.
(42) |
After each step is completed, the optimization plan for the decision variables is replaced with the measured data. Thus, the decision variables are corrected in time through the feedback of the measured data to form closed-loop optimal control. After the three 5-min steps are completed, a day-ahead dispatch is performed to determine whether the intraday dispatch should enter at . This cycle is repeated, as shown in
To test the model and dispatching framework, two test systems, from simple to complex, have been built: ① a simple AC/DC hybrid test system; and ② a 51-node AC/DC hybrid ADS with RDGs, an SOP, an SVC, and ESSs. The proposed model is implemented with the YALMIP optimization toolbox [
Test system 1 is a simple AC/DC hybrid system that converts part of the AC overhead line into a DC line (called Line 2), as shown in

Fig. 5 Test system 1: simple AC/DC hybrid system.
Test system 2 is a 51-node AC/DC hybrid ADS formed by one IEEE 33-node AC grid [

Fig. 6 Test system 2: 51-node AC/DC hybrid ADS.
From bus | To bus | R (Ω) | From bus | To bus | R (Ω) |
---|---|---|---|---|---|
34 | 35 | 0.493 | 44 | 45 | 0.541 |
35 | 36 | 0.366 | 45 | 46 | 0.591 |
36 | 37 | 0.381 | 46 | 47 | 0.378 |
38 | 39 | 0.819 | 47 | 48 | 0.746 |
39 | 40 | 0.187 | 49 | 50 | 0.708 |
41 | 42 | 0.711 | 50 | 51 | 0.683 |
42 | 43 | 1.044 | 44 | 51 | 1.289 |
43 | 44 | 0.374 |
Bus | Power (kW) | Bus | Power (kW) | Bus | Power (kW) | Bus | Power (kW) |
---|---|---|---|---|---|---|---|
34 | 100 | 40 | 90 | 45 | 40 | 50 | 60 |
35 | 90 | 41 | 80 | 46 | 40 | 51 | 40 |
37 | 60 | 42 | 80 | 47 | 80 | ||
38 | 60 | 43 | 80 | 48 | 100 | ||
39 | 100 | 44 | 80 | 49 | 80 |
The maximum transfer capability was determined primarily by the line thermal and node voltage limits [

Fig. 7 Lowest node voltage at different load levels in test system 1. (a) Lowest node voltage. (b) DTR value.
No. | (m/s) | () | () | () | DTR (MW) |
---|---|---|---|---|---|
STR | 0.50 | 0 | 40.0 | 100 | 12.0 |
DTR1 | 1.36 | 12.60 | 18.7 | 100 | 13.6 |
DTR2 | 5.06 | 30.34 | 26.8 | 100 | 23.7 |
As shown in
In this case, a complex system, i.e., test system 2, is considered and three models are compared: ① the model used in this study (No. 1); ② a model without an SOP (No. 2); and ③ a model without an SOP and a DNR (No. 3). The day-ahead input [

Fig. 8 Hourly forecasts of load, PV output, and WT output.
No. | Time division | Branch open | Power loss (kWh) |
---|---|---|---|
1 | 00:00-10:00 | 6-7; 10-11; 9-15 | 370.42 |
10:00-18:00 | 6-7; 8-9; 9-15 | ||
18:00-24:00 | 6-7; 10-11; 9-15 | ||
2 | 00:00-10:00 | 6-7; 13-14; 15-16 | 433.21 |
10:00-18:00 | 6-7; 12-13; 9-15 | ||
18:00-24:00 | 7-8; 13-14; 15-16 | ||
3 | 500.11 |
The power loss of the system is reduced by 25.9% (No. 1) and 13.4% (No. 2) compared with the No. 3 model. This is due to the following reasons. ① The power flow can be transferred at a large scale through DNR and has various directions. If DNR is absent, the power flow can only passes through a fixed topology, which may cause significant loss at the node and line near the upper grid. For example, at 05:00-07:00, a large amount of power provided by VSC3 flows into Node 33 through branches 33-18 because of DNR, thereby reducing the power demand of the branch where Node 33 is located in the upper power grid and decreasing losses. ② The SOP can adjust the active and reactive power and quickly respond to the fluctuations to maintain economic operation, whereas DNR can only change once in a time segment. For example, at 08:00-10:00, the active power of the SOP is from Nodes 22 to 12, whereas the others are opposite in the same time segment (00:00-10:00) to achieve optimal operation. By contrast, DNR could only choose one topology in the same segment, thus causing more losses than the SOP. In summary, DNR can optimize the power flow of the entire topology and entire day, whereas the SOP can optimize the power flow in the region where it is located in real time. The synergy between the two can reduce the loss better.
When the loads are light, the RDGs will change the power flow, thus raising the voltage of the access point and even causing an overvoltage. Herein, the load ratio is fixed to the minimum value for the entire day, i.e., 27%, thus causing the RDGs to output at the maximum, i.e., 100%, without considering the ESSs and SVC. This extreme case is considered to study the influence on RDG penetration. The highest voltages of test system 2 at different RDG penetration levels are shown in

Fig. 9 Highest voltage at different RDG penetration levels.
Evidently, the highest voltage occurs at Node 41, and it increases to 1.07 p.u. when the maximum DG capacity of the base case is 186 kW (penetration level is about 55 %). DNR could alleviate the overvoltage in the base case. When the maximum DG capacity increases to 240 kW (penetration level is approximately 71%), Node 41 experiences an overvoltage. The AC/DC hybrid system with an SOP and DNR could address this overvoltage because of the reactive power control from the VSC and SOP. The maximum DG capacity increases to 674 kW (penetration level is approximately 200%), and the highest voltage is approximately 1.05 p.u.. RDG penetration level could not increase at this time because of the capacity limit of VSC3. If this limit is relaxed, the RDG penetration level could increase to approximately 290%.
On the basis of the day-ahead input data, random fluctuations of ±30% and ±20% [

Fig. 10 Intraday 15 min input data of WTs, PVs, and load at 08:00-10:00.

Fig. 11 Optimized active power of SOP and VSC.
To check the switching between the intraday safety dispatch and the economic dispatch of the framework, the RDG penetration level is set to be 147.8% and at 09:15. The voltages at Nodes 25 and 41 are 0.968 p.u. and 1.31 p.u., respectively, going into the safety dispatch. The node voltages for economic dispatch and safety dispatch at 09:15 are shown in

Fig. 12 Node voltages for economic dispatch and safety dispatch at 09:15.
To verify the real-time feedback dispatch, a disturbance within ±5% and ±10% is randomly added to the input data of rolling-plan dispatch as the actual data, and the framework is used for dispatching to obtain the power of the tie line, as shown in

Fig. 13 Power of tie line for disturbances of ±5% and ±10% at 08:00-10:00.
Next, the accuracy of the relaxation is confirmed. For day-ahead dispatching, rolling-plan economic dispatch and safety dispatch, the objectives in (29), (40), and (41) are all increasing functions with the current, and their relaxation accuracy has been proven in [

Fig. 14 Relaxation gap of real-time feedback dispatch for a disturbance of ±10%.
To test the computational performance of the model and algorithm, test systems 1 (9 nodes), 2 (51 nodes), and 3 (118 nodes) have been utilized. Test systems 1 and 2 have been mentioned in Section V-A; test system 3 uses the modified IEEE 118-node model, whose parameters are given in [
Test system | Scenario 1 | Scenario 2 | Scenario 3 | |||
---|---|---|---|---|---|---|
Time (s) | Max gap (1 | Time (s) | Max gap (1 | Time (s) | Max gap (1 | |
1 | 492 | 5.92 | 6.03 | 2.37 | 3.76 | 5.38 |
2 | 6236 | 9.78 | 17.82 | 8.78 | 4.23 | 9.01 |
3 | 12537 | 6.42 | 22.32 | 6.04 | 6.05 | 4.86 |
The maximum relaxation gaps of different models in
The time of different dispatching scenarios for diverse systems indicates the following. ① As the size of the test system increases, the computation time also increases for each dispatch. ② For the intraday rolling-plan dispatch (Scenario 2) and real-time feedback dispatch (Scenario 3), the computation time is less than 1 min, which is much shorter than the scheduling interval (5 min). ③ For the day-ahead dispatch (Scenario 1), the computation time rapidly increases as the scale of the system increases. This is understandable because day-ahead scheduling creates huge variables for DNR as the test system increases in size. This is also acceptable because the day-ahead dispatch is used to obtain a plan for DNR and the ESSs for the next 24 hours, which means that superior real-time performance is not required.
Additionally, the same experimental conditions and model but with 32 GB of RAM have been used to test the effect of different hardware conditions on the day-ahead dispatch time. The results in three test system reveal that the computation time is reduced by 42.7%, 58.3%, and 71.2%, respectively. Essentially, the time of the day-ahead dispatch could be effectively reduced with an improvement in computer performance. Therefore, with the construction of a big data power platform, the computation time can be considerably reduced as compared to that with a PC. Thus, the proposed method has good engineering applicability.
This study focuses on the uncertainty in a network and established an AC/DC hybrid ADS model considering the DTR, DNR, and SOP. The optimal operation of this ADS is realized through a two-stage scheduling framework of day-ahead and intraday dispatches. The case study shows that the combination of the DTR and AC/DC hybrid system can expand the transmission capacity and alleviate node overvoltage. The synergistic optimization of the SOP and DNR can improve the absorption capacity of RDGs and reduce the line loss. The two-stage optimal dispatching framework can adapt to fluctuations in the RDGs and loads; additionally, it can improve the consumption of RDGs. Intraday feedback dispatching sends the measured data as feedback to track the rolling-plan dispatching plan, thus making the system more suitable for uncertainty.
NOMENCLATURE
Symbol | —— | Definition |
---|---|---|
A. | —— | Indexes |
, | —— | Indexes of nodes connected to the |
—— | Indexes of nodes connected to the | |
—— | Index of nodes in AC grid | |
l | —— | Index of lines in AC and DC grids |
—— | Index of nodes in DC grid | |
S | —— | Index of nodes in AC and DC grids |
B. | —— | Sets |
—— | Sets of branches with the | |
, | —— | Sets of branches with the |
, | —— | Sets of nodes in AC and DC grids |
—— | Set of dividing points | |
—— | Decision variables | |
—— | Differences of decision variables between rolling-plan dispatch and real-time feedback dispatch | |
, | —— | Apparent power of tie-line of real-time feedback dispatch and rolling-plan dispatch |
C. | —— | Variables |
, | —— | Start and end dividing points of the |
—— | Similar diameter | |
—— | Day-ahead dispatch divided into k segments | |
—— | Binary variables associated with ESS charging and discharging at node s during period t | |
—— | Square of current magnitude through branch (j,i) during period t | |
—— | Square of current magnitude through inside of VSC at node i during period t | |
—— | Actual line current rating calculated by dynamic thermal rating (DTR) | |
k | —— | Times of distribution network reconfiguration (DNR) in the day-ahead dispatch |
, | —— | Binary variables that indicate the power direction through branch (i,j) during period t |
—— | Equivalent load demand of active distribution system (ADS) in hour ,] | |
—— | Equivalent load average value in segment [,] | |
, | —— | Active and reactive power through branch (j,i) during period t |
, | —— | Active and reactive power injections at node i during period t |
—— | Active power injection at node n during period t | |
, , | —— | Active and reactive power injections at node i by substation and renewable distributed generators (RDGs) during period t |
—— | Active power injection at node n by RDGs duringperiod t | |
, | —— | Active and reactive power outflowing from node i to load, voltage source converter (VSC), and soft open point (SOP) during period t |
—— | Active power outflowing from node n to load during period t | |
—— | Active power injection at node i by the AC grid through VSC | |
—— | Active power injections from energy storage systems (ESSs) at node s, n, i during period t | |
, , | —— | Active power outflowing to ESSs at node s, n, i during period t |
—— | Dropout of RDG during period t | |
—— | Reactive power injection by static var generator (SVG) at node i during period t | |
—— | Reactive power flowing out from ideal VSC | |
, , | —— | Convection heat loss parameter, radiated heat loss parameter, and total solar and sky radiated heat parameter |
—— | AC resistance of conductor at temperature | |
—— | Micrometeorological variables of conductor temperature, ambient temperature, wind speed, and wind angle | |
—— | Voltage of the | |
—— | Voltage of the | |
—— | Square of voltage magnitude at node i during period t | |
—— | Voltage of conductor | |
—— | Binary variable associated with branch (i,j) on/off during period t | |
—— | Actual capacity of ESS at node s during period t | |
D. | —— | Parameters |
—— | Charging and discharging efficiencies of ESS | |
—— | Power factor of RDG | |
—— | Constant used to control the switching between economic and safety dispatch | |
—— | Charging and discharging unit time interval of ESS | |
, | —— | Time slots of day-ahead dispatch, rolling-plan dispatch, and real-time feedback dispatch |
, | —— | Costs of grid loss and RDG dropout |
—— | Forecasted active power generated by RDGs at node i during period t | |
—— | The maximum charging and discharging rates of ESS | |
, | —— | The maximum and minimum active power of VSC |
, | —— | The maximum and minimum values of static var compensator (SVC) |
, | —— | The maximum and minimum reactive power of VSC |
, | —— | The maximum and minimum reactive power of SOP |
, | —— | Resistance and reactance of branch (j,i) |
, | —— | Equivalent resistance and reactance of VSC |
—— | Actual and maximum capacity ratings of line | |
, | —— | The maximum capacities of VSC and SOP |
, | —— | The maximum and minimum voltages of nodes in AC grid |
, | —— | The maximum and minimum voltages of nodes in DC grid |
—— | The maximum capacity of ESS |
References
W. Wang, S. Huang, G. Zhang et al., “Optimal operation of an integrated electricity-heat energy system considering flexible resources dispatch for renewable integration,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 4, pp. 699-710, Jul. 2021. [Baidu Scholar]
S. Su, J. C. Jiang, and W. Wang, “An autonomous decentralized voltage control scheme in PEV charging devices on the distribution network – reactive power compensation for voltage decreases caused by household loads and charging devices,” International Transactions on Electrical Energy Systems, vol. 24, no. 3, pp. 412-432, Mar. 2014. [Baidu Scholar]
A. S. A. Awad, D. Turcotte, and T. H. M. El-Fouly, “Impact assessment and mitigation techniques for high penetration levels of renewable energy sources in distribution networks: voltage-control perspective,” Journal of Modern Power Systems and Clean Energy, vol. 10, no. 2, pp. 450-458, Mar. 2022. [Baidu Scholar]
X. Shi, R. Qiu, Z. Ling et al., “Spatio-temporal correlation analysis of online monitoring data for anomaly detection and location in distribution networks,” IEEE Transactions on Smart Grid, vol. 11, no. 2, pp. 995-1006, Mar. 2020. [Baidu Scholar]
V. Calderaro, G. Conio, V. Galdi et al., “Active management of renewable energy sources for maximizing power production,” International Journal of Electrical Power & Energy Systems, vol. 57, pp. 64-72, May 2014. [Baidu Scholar]
Y. Yang, C. Qin, Y. Zheng et al., “Optimal coordinated bidding strategy of wind and solar system with energy storage in day-ahead market,” Journal of Modern Power Systems and Clean Energy, vol. 10, no. 1, pp. 192-203, Jan. 2022. [Baidu Scholar]
J. Wu, B. Zhang, L. Hang et al., “Statistical distribution for wind power forecast error and its application to determine optimal size of energy storage system,” International Journal of Electrical Power & Energy Systems, vol. 55, pp. 100-107, Feb. 2014. [Baidu Scholar]
D. Liu and K. Sun, “Random forest solar power forecast based on classification optimization,” Energy, vol. 187, no. 15, p. 115940, Nov. 2019. [Baidu Scholar]
J. Zhang, J. Yan, D. Infield et al., “Short-term forecasting and uncertainty analysis of wind turbine power based on long short-term memory network and Gaussian mixture model,” Applied Energy, vol. 241, pp. 229-244, May 2019. [Baidu Scholar]
Z. Wang, T. Hong, and M. A. Piette, “Building thermal load prediction through shallow machine learning and deep learning,” Applied Energy, vol. 263, p. 114683, Apr. 2020. [Baidu Scholar]
A. Lorca and X. A. Sun, “Adaptive robust optimization with dynamic uncertainty sets for multi-period economic dispatch under significant wind,” IEEE Transactions on Power Systems, vol. 30, no. 4, pp. 1702-1713, Jul. 2015. [Baidu Scholar]
W. Hou, H. Wei, and R. Zhu, “Data-driven multi-time scale robust scheduling framework of hydrothermal power system considering cascade hydropower station and wind generation,” IET Generation, Transmission & Distribution, vol. 13, no. 6, pp. 896-904, Mar. 2019. [Baidu Scholar]
C. Ning and F. You, “A data-driven multistage adaptive robust optimization framework for planning and scheduling under uncertainty,” AIChE Journal, vol. 63, no. 10, pp. 4343-4369, May 2017. [Baidu Scholar]
C. Ning and F. You, “Optimization under uncertainty in the era of big data and deep learning: when machine learning meets mathematical programming,” Computers & Chemical Engineering, vol. 125, no. 9, pp. 434-448, Jun. 2019. [Baidu Scholar]
F. Rodríguez, A. Galarza, J. C. Vasquez et al., “Using deep learning and meteorological parameters to forecast the photovoltaic generators intra-hour output power interval for smart grid control,” Energy, vol. 239, p. 122116, Jan. 2022. [Baidu Scholar]
N. Gupta, “Probabilistic optimal reactive power planning with onshore and offshore wind generation, EV and PV uncertainties,” IEEE Transactions on Industry Applications, vol. 56, no. 4, pp. 4200-4213, Apr. 2020. [Baidu Scholar]
G. Zhang, J. Yuan, Z. Li et al., “Forming a reliable hybrid microgrid using electric spring coupled with non-sensitive loads and ESS,” IEEE Transactions on Smart Grid, vol. 11, no. 4, pp. 2867-2879, Jul. 2020. [Baidu Scholar]
M. Dorostkar-Ghamsari, M. Fotuhi-Firuzabad, M. Lehtonen et al., “Value of distribution network reconfiguration in presence of renewable energy resources,” IEEE Transactions on Power Systems, vol. 31, no. 3, pp. 1879-1888, May 2016. [Baidu Scholar]
N. V. Kovacki, P. M. Vidovic, and A. T. Saric, “Scalable algorithm for the dynamic reconfiguration of the distribution network using the Lagrange relaxation approach,” International Journal of Electrical Power & Energy Systems, vol. 94, pp. 188-202, Jan. 2018. [Baidu Scholar]
S. Chen, W. Hu, and C. Zhe, “Comprehensive cost minimization in distribution networks using segmented-time feeder reconfiguration and reactive power control of distributed generators,” IEEE Transactions on Power Systems, vol. 31, no. 2, pp. 983-993, Mar. 2016. [Baidu Scholar]
D. Kumar, A. Singh, S. K. Mishra et al., “A coordinated planning framework of electric power distribution system: intelligent reconfiguration,” International Transactions on Electrical Energy Systems, vol. 28, no. 6, p. 2543, Jun. 2018. [Baidu Scholar]
W. Cao, J. Wu, N. Jenkins et al., “Benefits analysis of soft open points for electrical distribution network operation,” Applied Energy, vol. 165, no. 1, pp. 36-47, Mar. 2016. [Baidu Scholar]
L. Peng, H. Ji, C. Wang et al., “Coordinated control method of voltage and reactive power for active distribution networks based on soft open point,” IEEE Transactions on Sustainable Energy, vol. 8, no. 4, pp. 1949-3029, Oct. 2017. [Baidu Scholar]
D. Sciano, A. Raza, R. Salcedo et al., “Evaluation of DC links on dense-load urban distribution networks,” IEEE Transactions on Power Delivery, vol. 31, no. 3, pp. 1317-1326, Jun. 2016. [Baidu Scholar]
A. Shekhar, L. M. Ramirez-Elizondo, T. B. Soeiro et al., “Boundaries of operation for refurbished parallel AC-DC reconfigurable links in distribution grids,” IEEE Transactions on Power Delivery, vol. 35, no. 2, pp. 549-559, May 2019. [Baidu Scholar]
M. Dabbaghjamanesh, A. Kavousi-Fard, and S. Mehraeen, “Effective scheduling of reconfigurable microgrids with dynamic thermal line rating,” IEEE Transactions on Industrial Electronics, vol. 66, no. 2, pp. 1552-1564, Feb. 2018. [Baidu Scholar]
Y. Li, Y. Wang, and Q. Chen, “Optimal dispatch with transformer dynamic thermal rating in ADNs incorporating high PV penetration,” IEEE Transactions on Smart Grid, vol. 12, no. 3, pp. 1989-1999, May 2021. [Baidu Scholar]
H. M. A. Ahmed and M. M. A. Salama, “Energy management of AC-DC hybrid distribution systems considering network reconfiguration,” IEEE Transactions on Power Systems, vol. 34, no. 6, pp. 4583-4594, Nov. 2019. [Baidu Scholar]
Y. Fu, Z. Zhang, Z. Li et al., “Energy management for hybrid AC/DC distribution system with microgrid clusters using non-cooperative game theory and robust optimization,” IEEE Transactions on Smart Grid, vol. 11, no. 2, pp. 1510-1525, Mar. 2020. [Baidu Scholar]
C. Qi, K. Wang, Y. Fu et al., “A decentralized optimal operation of AC/DC hybrid distribution grids,” IEEE Transactions on Smart Grid, vol. 9, no. 6, pp. 6095-6105, Nov. 2018. [Baidu Scholar]
A. Azizivahed, A. Arefi, S. Ghavidel et al., “Energy management strategy in dynamic distribution network reconfiguration considering renewable energy resources and storage,” IEEE Transactions on Sustainable Energy, vol. 11, no. 2, pp. 662-673, Apr. 2020. [Baidu Scholar]
H. Ji, P. Li, J. Ji et al., “MPC-based local voltage control strategy of DGs in active distribution networks,” IEEE Transactions on Sustainable Energy, vol. 11, no. 4, pp. 2911-2921, Oct. 2021. [Baidu Scholar]
W. Jiao, J. Chen, Q. Wu et al., “Distributed coordinated voltage control for distribution networks with DG and OLTC based on MPC and gradient projection,” IEEE Transactions on Power Systems, vol. 37, no. 1, pp. 680-690, Jan. 2022. [Baidu Scholar]
X. Liu, “Multiple time‐scale economic dispatching strategy for commercial building with virtual energy storage under demand response mechanism,” International Journal of Energy Research, vol. 45, no. 6, pp. 16204-16227, May 2021. [Baidu Scholar]
A. A. Eajal, M. F. Shaaban, K. Ponnambalam et al., “Stochastic centralized dispatch scheme for AC/DC hybrid smart distribution systems,” IEEE Transactions on Sustainable Energy, vol. 7, no. 3, pp. 1046-1059, Jul. 2017. [Baidu Scholar]
M. Isuru, M. Hotz, H. B. Gooi et al., “Network-constrained thermal unit commitment fortexhybrid AC/DC transmission grids under wind power uncertainty,” Applied Energy, vol. 258, p. 114031, Jan. 2020. [Baidu Scholar]
L. Zhang, J. Liang, W. Tang et al., “Converting AC distribution lines to DC to increase transfer capacities and DG penetration,” IEEE Transactions on Smart Grid, vol. 10, no. 2, pp. 1477-1487, Mar. 2019. [Baidu Scholar]
Y. Wang, D. Liu, X. Xu et al., “Cyber-physical power system modeling for timing-driven control of active distribution network,” Journal of Modern Power Systems and Clean Energy, vol. 8, no. 3, pp. 549-556, May 2020. [Baidu Scholar]
W. D. Fisher, “On grouping for maximum homogeneity,” Journal of the American Statistical Association, vol. 53, no. 284, pp. 789-798, Jan. 1958. [Baidu Scholar]
A. Costa, A. Crespo, J. Navarro et al., “A review on the young history of the wind power short-term prediction,” Renewable and Sustainable Energy Reviews, vol.12, no. 6, pp. 1725-1744, Aug. 2008. [Baidu Scholar]
L. Gan, N. Li, U. Topcu et al., “Exact convex relaxation of optimal power flow in radial networks,” IEEE Transactions on Automatic Control, vol. 60, no. 1, pp. 72-87, Jan. 2015. [Baidu Scholar]
T. Yuan, K. Wang, G. Li et al., “Affinely adjustable robust AC-DC optimal power flow considering correlation of wind power,” IET Renewable Power Generation, vol. 12, no. 13, pp. 1478-1485, May 2018. [Baidu Scholar]