Journal of Modern Power Systems and Clean Energy

ISSN 2196-5625 CN 32-1884/TK

网刊加载中。。。

使用Chrome浏览器效果最佳,继续浏览,你可能不会看到最佳的展示效果,

确定继续浏览么?

复制成功,请在其他浏览器进行阅读

Bi-level Multi-objective Joint Planning of Distribution Networks Considering Uncertainties  PDF

  • Shouxiang Wang
  • Yichao Dong
  • Qianyu Zhao
  • Xu Zhang
the Key Laboratory of Smart Grid of Ministry of Education, Tianjin University, Tianjin, 300072, China; State Grid Tianjin Electric Power Company Economic and Technological Research Institute, Tianjin 300171, China; the State Grid Tianjin Electric Power Company, Tianjin, 300010, China

Updated:2022-11-20

DOI:10.35833/MPCE.2020.000930

  • Full Text
  • Figs & Tabs
  • References
  • Authors
  • About
CITE
OUTLINE

Abstract

With the increasing penetration of photovoltaics in distribution networks, the adaptability of distribution network under uncertainties needs to be considered in the planning of distribution systems. In this paper, the interval arithmetic and affine arithmetic are applied to deal with uncertainties, and an affine arithmetic based bi-level multi-objective joint planning model is built, which can obtain the planning schemes with low constraint-violation risk, high reliability and strong adaptability. On this basis, a bi-level multi-objective solution methodology using affine arithmetic based non-dominated sorting genetic algorithm II is proposed, and the planning schemes that simultaneously meet economy and adaptability goals under uncertainties can be obtained. To further eliminate bad solutions and improve the solution qualities, an affine arithmetic based dominance relation weakening criterion and a deviation distance based modification method are proposed. A 24-bus test system and a 10 kV distribution system of China are used for case studies. Different uncertainty levels are compared, and a sensitivity analysis of key parameters is conducted to explore their impacts on the final planning schemes. The simulation results verify the advantages of the proposed affine arithmetic based planning method.

I. INTRODUCTION

THE increasing penetration of photovoltaics (PVs) in distribution network (DN) has inevitably induced some operational issues such as voltage violation [

1]-[3], increased thermal stress [4], and degraded power quality [5]. To solve these issues, the adaptive planning of active distribution network (ADN) has become one of the research hotspots. In the traditional DN planning model, the cost concerning investment, reliability, network loss, and grid power purchase is taken as the main objective [6]. On this basis, some improvements have been made in recent years. In [7], the DN planning problem is formulated as second-order cone programming by the linearization technique. Some researchers have focused on multistage planning considering geographical locations, environmental benefits, and multistage needs. In [8], the DN multistage planning considering different types, locations and installation cycles of DN devices is proposed to minimize the total economic cost. In [9], the linearization technique is used to build a multistage mixed-integer linear programming (MILP) model, and the total cost is minimized by voltage regulator installation and network reconfiguration.

However, the objectives of the above models are mainly economy or reliability while the PV hosting capacity is rarely considered, which will restrict the enhancement of adaptability. Therefore, a DN planning model with discrete variables and nonlinear power flow is presented in [

10] to maximize the PV hosting capacity. In [11], the network reconfiguration is formulated as a nonlinear and non-differentiable optimization model for hosting capacity improvement. In [12], a two-stage planning model for adaptability enhancement is proposed, where the first stage solves static investment problem and the second stage solves operational issue. Moreover, the PV and load uncertainties have great impacts on the safe and stable operation of DN as well as DN planning schemes. Although some researchers have tried to reduce impacts of uncertainties by the artificial intelligence approaches [13], the applicability of the above deterministic methods will be limited for lacking consideration of multiple uncertainties.

Currently, the probabilistic methods, robust methods, and interval methods are the three commonly used methods for dealing with uncertainty problems. Generally, the probabilistic methods [

14]-[16] describe various uncertainties depending on the probability density functions (PDFs) generated by massive scenario simulations. In [14], a stochastic planning model with techno-economic and environmental indices is built, where the intermittency of PV and load is quantified by K-means based probabilistic method. In [15], the uncertainties of heat and electricity demands as well as PV outputs are quantified by massive scenario simulations. In [16], the Latin hypercube sampling and scenario reduction techniques are used to build a probabilistic planning model. Although the probabilistic methods can effectively quantify multiple uncertainties, their performances are heavily dependent on the accuracy of PDFs. In reality, it is generally intractable to obtain accurate PDFs of PVs or loads, especially with limited measurement data, which restricts the application of probabilistic methods [17].

For addressing the drawbacks of probabilistic methods in dealing with uncertainties, the robust methods and interval methods are two feasible methods. The robust methods usually characterize uncertainties through the polyhedral uncertainty sets, and the solution robustness can be effectively controlled by the budget of uncertainty [

18]-[20]. However, the robust optimization model is generally a nonlinear and non-convex min-max-min problem, which cannot be solved directly by commercial optimization packages [18]. Hence, a bi-level or tri-level decomposition strategy comprising primal and dual cuts is essential, and the convexification of power flow equation is needed to guarantee convergence [19], [20], which increases the model complexity and computational burden.

In comparison, the interval methods are more applicable in dealing with uncertainty problems because all uncertain variables are expressed by their upper and lower bounds, which are relatively easier to obtain in most cases. The superiority of interval methods becomes more obvious, especially under the environment of insufficient meter configurations [

21]-[23]. Generally, the interval methods can be realized in two ways, namely interval arithmetic (IA) and affine arithmetic (AA). IA usually has the drawback of conservative computation when various uncertain variables are interrelated, which can be overcome by AA. AA can keep track on the dependencies of multiple uncertain variables and reduce the computation conservativeness by the complex operations of multiple affine polynomials. In a sense, AA is an advanced interval method with higher computation accuracy and lower conservativeness.

At present, some references [

24], [25] have used IA for DN uncertainty planning, while AA has not been applied for DN planning considering uncertainties in the existing literatures. Therefore, an AA-based adaptability-oriented bi-level multi-objective joint planning model is built in this paper, and the AA-based non-dominated sorting genetic algorithm II (AA-NSGA-II) is used to calculate the AA-based Pareto optimal front (AA-POF). With an expanded analysis scope of DN adaptive planning and a comprehensive coverage on uncertainties, the proposed method can obtain more rational planning schemes with better economy and adaptability goals under uncertainties. The main contributions of this paper are as follows.

1) To realize the goal of DN adaptability enhancement, two indices, namely network structural adaptability and operational adaptability, are proposed. Meanwhile, the concept of uneven degree of PV configuration is introduced to adequately improve the PV hosting capacity through a more even PV configuration instead of the extreme one. On this basis, an adaptability-oriented bi-level multi-objective joint planning model is established, which can obtain the planning schemes with low constraint-violation risk, high reliability, and strong adaptability.

2) IA and AA are applied to precisely quantify uncertainty fluctuations of PVs and loads, and the deterministic planning model has been improved by incorporating affine parameters. On this basis, an AA-NSGA-II-based bi-level multi-objective solution methodology is proposed to calculate AA-POF. The obtained AA-POF represents a set of optimal planning schemes that can simultaneously meet the economy and adaptability goals of DN considering uncertainties, which is of great significance for practical DN planning in the complex uncertain environment.

3) To further eliminate bad solutions in AA-POF and improve the solution qualities, an AA-based dominance relation weakening criterion and a deviation-distance-based AA-POF modification method are proposed. The comparison analysis of different uncertainty levels is conducted to explore their diverse interval variations. The results of AA-based planning method are compared with IA and Monte Carlo simulation (MCS) methods to demonstrate its advantages. In addition, a sensitivity analysis is conducted to explore the impacts of key parameters on the final planning schemes.

The remaining parts of this paper are organized as follows. Section II presents the problem formulation, which establishes the AA-based bi-level multi-objective joint planning model. Section III proposes the AA-NSGA-II-based solution methodology. Section IV conducts the case study and sensitivity analysis. Finally, the main conclusions are drawn in Section V.

II. PROBLEM FORMULATION

In reality, the PV power outputs are inevitably affected by various uncertain factors such as variable solar radiations and temperatures, and load demands also constantly change with weather variations and electricity price adjustment [

17]. The uncertainty fluctuations of PVs and loads can directly affect the uncertain power injections of all buses and then affect the uncertain power flow of DN, which has great impacts on the safe and stable operation of DN as well as DN planning schemes. To this end, IA and AA are applied in this paper to deal with uncertainties. IA is a numerical method where all uncertain variables are expressed in interval forms with the upper and lower bounds. AA is an advanced interval method where the dependencies of uncertain variables are considered, and the computation conservativeness can be effectively reduced by the complex operations of affine polynomials. The detailed arithmetical operations of IA and AA can be found in [26]. On this basis, the AA-based adaptability-oriented bi-level multi-objective joint planning model is built as follows.

A. Objective Functions

The bi-level multi-objective joint planning model includes four objectives in total. In the upper-level model, the construction and upgrade strategy of substation and line is optimized for minimizing the total economic cost and maximizing the network structural adaptability. In the lower-level model, the configuration strategy of PV and static var compensation (SVC) is optimized for maximizing the operational adaptability and minimizing the uneven degree of PV configuration.

1) AA-based Total Economic Cost

The AA-based total economic cost f̂1 in (1) is defined as the weighted sum of affine net present value of investment cost, operation and maintenance cost, network loss cost, and PV generation profit formulated by (2)-(5). The objective f̂1 is the fundamental objective for DN multistage planning.

min f̂1=hΩh1+λ11+λ2h(finv,h+fo&m,h+floss,h-fpro,h) (1)
f̂inv,h=iΩsscΩc(css,cconsσi,c,hcons+css,cupσi,c,hup)+ijΩlkΩk(cl,kconsδij,k,hconslij+cl,kupδij,k,huplij)+iΩncPVconsβi,hP̂PV,i,hcap+iΩncSVCconsγi,h (2)
f̂o&m,h=iΩsscΩccss,co&mτi,c,h+ijΩlkΩkcl,ko&mμij,k,hlij+g=1hiΩncPVo&mβi,gP̂PV,i,gcap+g=1hiΩncSVCo&mγi,g (3)
f̂loss,h=αlossεt,htΩt,hi,jΩnGij,h(V̂i,h(t))2+(V̂j,h(t))2-2V̂i,h(t)V̂j,h(t)cosθ̂ij,h(t) (4)
f̂pro,h=αproεt,htΩt,hiΩnβi,hP̂PV,i,h (t) (5)

2) Network Structural Adaptability

The network structural adaptability f2 in (6) is defined as the weighted sum of two indices. The first index is the tie-line connection degree (TCD) in (7), which is quantified by the distribution density of tie-lines between different power supply areas. Dtcd=0 means there is no tie-line in operation and the corresponding power supply reliability is poor. The second index is the network cohesion degree (NCD) in (8) and (9), which is quantified by the strength of network cohesion between different geographical regions. Dncd=0 means all substations supply power in their own geographical regions without interconnection. The objective f2 can effectively reflect the flexibility and adaptability of DN network structure, which is also important during the whole planning horizon.

maxf2=1NΩhhΩh(α1Dtcd,h+α2Dncd,h) (6)
Dtcd,h=1NΩssdΩssijΩl,hd,tieμij,hijΩl,hdμij,h (7)
Dncd,h=i,jΩn,jΩni1eij,hi,jΩn,ji1eij,h (8)
eij,h=kΩkμij,k,hzl,klij    cij,h=1                          cij,h=0 (9)

3) AA-based Operation Adaptability

The high penetration of PVs has great impacts on the overall level of bus voltage and line current. The AA-based operational adaptability f̂3 in (10) is defined as the weighted sum of voltage violation margin V̂hmar and current violation margin Îhmar formulated by (11) and (12). f̂3 can effectively reflect the comprehensive constraint violation risk and DN operational adaptability under uncertainties. The larger f̂3 is, the more abundant space for further PV installation there will be, and the DN will present larger PV hosting capacity and stronger operational adaptability accordingly.

maxf̂3=1NΩhhΩh(α3V̂hmar+α4Îhmar) (10)
V̂hmar=1NΩssNΩn,hddΩssiΩn,hdminp=a,b,ctΩt,hVmax-V̂i,p,h(t)Vmax (11)
Îhmar=1NΩssdΩssminp=a,b,c,kΩkijΩl,hd,tΩt,hIl,kmax-Îij,p,k,h(t)Il,kmax (12)

4) AA-based PV Configuration Uneven Degree

When a centralized PV with a large capacity is installed at the most distant terminal bus, which is called the extreme PV configuration, the voltage violation is most likely to occur. In this condition, the PV configuration presents an uneven characteristic and the PV hosting capacity will be restricted. To this end, the AA-based PV configuration uneven degree f̂4 is defined by (13)-(15) to quantify the uneven degree of PV configuration during all planning stages considering uncertainties. By optimizing the objective f̂4, the PV hosting capacity can be adequately improved through a more even PV configuration instead of the extreme PV configuration.

min f̂4=1NΩhNΩsshΩhdΩssD̂PV,hdP̂PV,hcap,d (13)
D̂PV,hd=1NΩn,hdiΩn,hdβi,hP̂PV,i,hcap-P̂PV,hcap,dNΩn,hd2 (14)
P̂PV,hcap,d=iΩn,hdβi,hP̂PV,i,hcap (15)

B. Constraint Conditions

1) AA-based Three-phase Power Flow Constraints

To describe the three-phase unbalance characteristics of DN and influences of various uncertain factors, the AA-based three-phase power flow is constrained by (16)-(21), where the AA-based forward-backward sweep power flow method [

22] is used for analysis.

P̂i,p,h(t)=V̂i,p,h(t)jΩnf=ac(Gij,pf,hV̂j,f,h(t)cosθ̂ij,pf,h(t)+Bij,pf,hV̂j,f,h(t)sinθ̂ij,pf,h(t)) (16)
Q̂i,p,h(t)=V̂i,p,h(t)jΩnf=ac(Gij,pf,hV̂j,f,h(t)sinθ̂ij,pf,h(t)-Bij,pf,hV̂j,f,h(t)cosθ̂ij,pf,h(t)) (17)
P̂i,p,h(t)=βi,hP̂PV,i,p,h(t)-P̂L,i,p,h(t) (18)
Q̂i,p,h(t)=βi,hQ̂PV,i,p,h(t)+γi,hQ̂SVC,i,p,h-Q̂L,i,p,h(t) (19)
P̂PV, i,p,h(t)=P̂PV,i,p,hcapη̂PV,h(t) (20)
Q̂PV,i,p,h(t)=P̂PV,i,p,h(t)tan(arccosφPV,i,h) (21)

2) Radial Topology Constraints

The DN radial topology should be maintained during the whole planning horizon as formulated by (22) and (23).

ψij,h+ψji,h=μij,h    ijΩl,hΩh (22)
ψij,h=0    jΩss,hΩh (23)
iΩnψij,h=1    jΩn\Ωss,hΩh (24)

3) AA-based Steady-state Operation Constraints

The AA-based steady-state operation constraints concerning bus voltage, line current, and apparent power should be satisfied for each time slot as formulated by (25)-(27), which can ensure the normal operation of DN under uncertainties. The PV installation capacity, SVC compensation capacity, and substation capacity also need to be constrained by (28)-(30).

VminV̲i,p,h(t)<V¯i,p,h(t)Vmax    iΩn,p=a,b,c (25)
I¯ij,p,k,h(t)Il,kmax    ijΩl,kΩk,p=a,b,c (26)
S¯ij,p,k,h (t)Sl,kmax    ijΩl,kΩk,p=a,b,c (27)
P¯PV,i,hcapPPV,i,hcap,max    iΩn (28)
Q¯SVC,i,hQSVC,i,hmax    iΩn (29)
Sss,i,c,h (t)Sss,cmax    iΩss,cΩc (30)

where the horizontal lined superscript ()¯ and subscript ()̲ represent the upper and lower bounds of uncertain variable, respectively.

4) Multistage Planning Constraints

During the whole planning horizon, NPVmax and NSVCmax should be restricted by (31) and (32), respectively. Other multistage planning constraints for substations and lines are described in (33)-(36).

hΩhiΩnβi,hNPVmax (31)
hΩhiΩnγi,hNSVCmax (32)
hΩhcΩc(σi,c,hcons+σi,c,hup)1    iΩss (33)
hΩhkΩk(δij,k,hcons+δij,k,hup)1    ijΩl (34)
τi,h=g=1hcΩcσi,c,gcons    iΩssa,hΩh1                       iΩss\Ωssa,hΩh (35)
μij,hg=1hkΩkδij,k,gcons    ijΩla,hΩh (36)

III. SOLUTION METHODOLOGY

With the properties of fast non-dominated sorting and elitist strategy, NSGA-II has received a lot of attentions in solving multi-objective optimization problems [

27]. By incorporating affine parameters in NSGA-II, AA-NSGA-II is proposed in [23]. In AA-NSGA-II, the objectives of all feasible solutions are compared in affine forms to reflect uncertainties. Based on AA-NSGA-II, an AA-based dominance relation weakening criterion and a deviation distance based AA-POF modification method are presented in this section, which can effectively eliminate bad solutions in the AA-POF and improve the solution qualities. On this basis, an AA-NSGA-II-based bi-level multi-objective solution methodology is proposed.

A. AA-NSGA-II Improvement

1) AA-based Dominance Relation and AA-POF

The comparison of affine variables is usually conducted based on the confidence level. The detailed calculation method of confidence level can be found in [

23]. On this basis, the AA-based dominance relations between all feasible solutions in the solution space S={xk|k=1,2,,K} can be determined. For an N-dimensional multi-objective minimization problem, the solution xi dominates xj in S if:

Φf̂a(xi)<f̂a(xj)0.5    a{1,2,,N}Φf̂b(xi)<f̂b(xj)>0.5    b{1,2,,N} (37)

When no other solutions in S dominate xk, xk becomes an AA-based Pareto optimal solution. Thus, the set of Pareto optimal solutions containing Knd solutions can be defined as Pnd={xk|k=1,2,,Knd}. On this basis, the AA-POF is defined as the affine multi-objective vector of all AA-based Pareto optimal solutions as shown in (38).

AA-POF=F̂(xk)=[f̂1(xk),f̂2(xk),,f̂N(xk)]TxkPnd (38)

With the increase of N, the dimension of AA-POF will get larger accordingly. When N=2, the AA-POF is a set of rectangles. When N=3, the AA-POF is a set of cubes. When N4, the AA-POF will become a set of hypercubes.

2) AA-based Dominance Relation Weakening Criterion

When N is large, there will be some bad solutions in the AA-POF which only have one non-dominated objective, while other objectives are all dominated by other solutions. These bad solutions will become less feasible with the increase of N because their ratios of non-dominated objective are getting lower, which makes their infeasibility closer to those solutions without any non-dominated objective. In this case, the strict dominance relation criterion in (37) seems less applicable, and it is necessary to eliminate bad solutions by appropriately weakening the dominance relation. To this end, an AA-based dominance relation weakening criterion is proposed in this paper. Under this criterion, the solution xi dominates xj if:

Φf̂a(xi)<f̂a(xj)0.5    aN-log2(N-2)Φf̂b(xi)<f̂b(xj)<0.5    b>N-log2(N-2) (39)

where [] is the rounding operation.

3) Deviation Distance Based AA-POF Modification

After adopting the AA-based dominance relation weakening criterion, there may still exist bad solutions with certain objectives deviated far from the average level. These solutions are also infeasible and should be eliminated although they are non-dominated. To this end, a deviation distance based AA-POF modification method is proposed in this paper. If the affine objectives of all Pareto optimal solutions are denoted as (40), the average central value fi,AVG0 can be calculated by (41).

f̂i(xk)=fi(0)(xk)+m=1Mfim(xk)εm    xkPnd,i=1,2,,N (40)
fi,AVG(0)=1KndxkPndfi(0)(xk)    i=1,2,,N (41)

On this basis, the deviation distance DAVG(xk) between F̂(xk) and average level F̂AVG=[f̂1,AVG,f̂2,AVG,,f̂N,AVG]T is calculated by (42)-(46).

DAVG(xk)=dAVG(xk)OAVG(xk)+VAVG+V(xk)+1    xkPnd (42)
dAVG(xk)=i=1Nfi(0)(xk)-fi,AVG(0)    xkPnd (43)
OAVG(xk)=i=1NLf̂i(xk)f̂i,AVG    xkPnd (44)
VAVG=i=1N2KndxkPndm=1Mfim(xk) (45)
V(xk)=i=1N2m=1Mfim(xk)    xkPnd (46)

where the hypercubes F(xk) and FAVG can be derived from the affine polynomials of F̂(xk) and F̂AVG according to (47) and (48), respectively.

f̂i(xk)=fi(0)(xk)-m=1Mfim(xk),fi(0)(xk)+m=1Mfim(xk) (47)
f̂i,AVG=[fi,AVG(0)-Ri,AVG,fi,AVG(0)+Ri,AVG]Ri,AVG=1KndxkPndm=1Mfim(xk) (48)

By comparing the deviation distances of all Pareto optimal solutions, i.e., DAVG(xk) (xkPnd) with the predefined maximum allowable deviation distance Dmax, the bad solutions in AA-POF can be effectively eliminated.

The deviation distance DAVG(xk) only considers the affine objectives but ignores the deterministic objectives. To this end, the comprehensive deviation distance D˜AVG(xk) considering all affine objectives and deterministic objectives is defined as:

D˜AVG(xk)=DAVG(xk)expi=1Ndfi(xk)fi,AVG-1    xkPnd (49)
fi,AVG=1KndxkPndfi(xk) (50)

B. AA-NSGA-II-based Bi-level Solution Methodology

By applying the basic theories of AA-NSGA II, AA-based dominance relation weakening criterion and deviation distance-based AA-POF modification method, an AA-NSGA-II-based bi-level multi-objective solution methodology is proposed. Through the joint optimization of bi-level model, the multi-objective planning problem can be solved more effectively. The main solution flowchart is depicted in Fig. 1, and the detailed solution procedure is introduced as follows.

Fig. 1  Main solution flowchart.

Step 1:   initialize the chromosome codes at the upper level for construction and upgrade the strategy of substation and line, and filtrate them by (22)-(24) and (33)-(36). Then, a total of NPup feasible individuals are generated, and the population Pup only containing upper-level codes is formed.

Step 2:   select the ith individual of Pup, i.e., Iiup for replicating, and keep their upper-level codes consistent. Then, initialize the lower-level codes for configuration strategy of PV and SVC, and filtrate them by (16)-(21) and (25)-(32). A total of NPdown individuals are generated and the population P1(Iiup) containing upper- and lower-level codes is constituted.

Step 3:   calculate the lower-level objectives f̂3 and f̂4 for each individual of P1(Iiup). Then, analyze the dominance relations of f̂3 and f̂4 between different individuals by (41). Thus, the set of AA-based non-dominated solutions corresponding to P1(Iiup), i.e., F1opt(Iiup), is determined.

Step 4:   conduct the selection, crossover and mutation operations for P1(Iiup) (only for the lower-level codes) to form P2(Iiup), and F2opt(Iiup) is ascertained. After Nmax iterations, the set of non-dominated solutions corresponding to Iiup, i.e., FNopt(Iiup) is obtained. Then, calculate the upper-level objectives f̂1, f2, and analyze the AA-based weakening dominance relations of all objectives to determine the AA-POF Fopt(Iiup).

Step 5:   repeat Steps 1-4 for all individuals of Pup and form Pfull containing all sets of non-dominated solutions, where Pfull={Fopt(Iiup)|i=1,2,,NPup}. Then, analyze the AA-based weakening dominance relations of all objectives and obtain AA-POF Fopt(Pfull). The final AA-POF Ffinalopt can be determined by the deviation distance based modification.

IV. CASE STUDY

A. Case Description and Parameter Setting

To verify effectiveness of the proposed method, a modified 24-bus test system [

8] shown in Fig. 2 is used to conduct case study. This is a 20 kV distribution system consisting of 4 substation buses, 20 load buses, and 33 lines (including 9 tie-lines marked in red). The whole system is divided into four geographical regions, namely Z1-Z4. The reference voltage is set as 1.00 p.u.. Vmax and Vmin are set as 1.05 p.u. and 0.95 p.u., respectively. All buses are assumed as PQ-type bus.

Fig. 2  Initial topology of modified 24-bus test system.

The planning horizon is divided into 3 stages, each lasting for 5 years. The data of line and peak load (power factor equals 0.9) are derived from [

8] and [9], respectively. The interval construction of PV outputs and load demands with reference to [17] is depicted in Fig. 3. There are three available types of substations and conductors, and the existing substations and conductors are all type one. The data of substations and conductors are shown in Table I and Table II, respectively. The economic parameters are given in Table III. α1, α2, α3 and α4 are set as 0.5, 0.5, 0.8, and 0.2, respectively. The crossover rate and mutation rate are set as 0.5 and 0.1, respectively. In addition, all SVCs are assumed in inductive compensations. NPVmax and NSVCmax are both set as the total number of buses. PPV,i,hcap,max and QSVC,i,hmax are set as 1 MW and 500 kvar, respectively.

Fig. 3  Interval construction. (a) PV active power. (b) Load active power. (c) Load reactive power.

TABLE I  DATA OF DIFFERENT TYPES OF SUBSTATIONS
ΩcSss,cmax (kVA)css,ccons (k$)css,cup (k$)css,co&m (k$/a)
1 12000 750 2.0
2 15000 950 720 3.0
3 20000 1350 1020 4.5
TABLE II  DATA OF DIFFERENT TYPES OF CONDUCTORS
Ωkzl,k (Ω/km)Sl,kmax (kVA)Il,kmax (A)cl,kcons($/km)cl,kup($/km)cl,ko&m($/(km·a))
1 1.268+j0.422 2260 136 10000 25
2 0.576+j0.393 4350 261 15000 11400 35
3 0.215+j0.334 9210 445 23000 17480 50
TABLE III  DATA OF NECESSARY ECONOMIC PARAMETERS
cPVcons($/kW)cSVCcons ($)cPVo&m($/kW·a)cSVCo&m($/a)αloss($/kWh)αpro($/kWh)λ1λ2
1000 3000 50 100 0.08 0.06 0.03 0.10

All simulation tests are implemented in C++ environment on a Dell laptop with Intel Core i7-7700HQ CPU running at 2.80 GHz with 8 GB RAM.

B. Simulation Analysis

1) AA-based Pareto Optimal Solutions

By using the bi-level multi-objective solution methodology, a total of ten Pareto optimal solutions are obtained. The planning schemes of Pareto optimal solutions No. 2 and No. 8 are shown in Fig. 4, and the interval objective values of all Pareto optimal solutions are listed in Table IV and Table V.

Fig. 4  Planning schemes of Pareto optimal solutions No. 2 and No. 8. (a) No. 2. (b) No. 8.

TABLE IV  INTERVAL VALUES OF f̂1, f2, f̂3, f̂4, PV INSTALLATION CAPACITY, AND SVC COMPENSATION CAPACITY
No.f̂1 (M$)f2 (%)f̂3 (%)f̂4 (%)NPVP̂PVcap (kW)NSVCQ̂SVC (kvar)
1 [12.41,12.96] 18.11 [18.58,19.47] [12.83,14.24] 15 [11188,12924] 14 [4213,4810]
2 [11.90,12.52] 19.57 [17.03,17.92] [14.30,15.61] 12 [7900,9112] 18 [5350,5962]
3 [8.56,9.22] 18.38 [18.21,19.19] [18.56,20.21] 10 [6827,7820] 13 [4914,5543]
4 [9.74,10.17] 22.13 [16.62,17.84] [15.35,16.62] 11 [5104,5361] 15 [3884,4195]
5 [9.82,10.33] 19.53 [16.93,18.03] [18.80,20.20] 10 [6955,7956] 16 [5164,5890]
6 [13.26,13.92] 13.17 [19.14,19.88] [12.46,13.74] 16 [10775,12241] 18 [5913,6651]
7 [7.58,8.22] 17.62 [18.70,19.44] [22.25,23.71] 9 [5831,6562] 8 [3337,3741]
8 [9.45,10.04] 31.90 [13.80,15.46] [16.46,17.56] 11 [7431,7849] 9 [2887,3184]
9 [8.42,9.15] 16.47 [18.53,19.64] [18.65,20.05] 9 [6889,7698] 17 [5484,6207]
10 [10.16,10.79] 26.02 [15.81,17.17] [15.64,16.93] 11 [7145,8101] 16 [5283,6109]
TABLE V  INTERVAL VALUES OF COSTS AND PROFITS, TCD AND NCD, AND VOLTAGE AND CURRENT VIOLATION MARGINS
No.f̂inv (M$)f̂o&m (M$)floss (M$)f̂pro (M$)Dtcd (%)Dncd (%)V̂ mar (%)Πmar (%)
1 [13.70,14.38] [2.78,2.95] [1.09,1.18] [5.08,5.67] 19.50 16.73 [4.83,4.85] [73.60,77.96]
2 [11.12,11.79] [2.15,2.34] [2.60,2.79] [3.91,4.37] 15.08 24.06 [4.95,5.00] [65.32,69.60]
3 [9.37,9.95] [2.55,2.69] [1.55,1.66] [4.69,5.20] 13.77 23.00 [4.91,4.94] [71.43,76.18]
4 [8.63,8.77] [2.14,2.19] [2.96,3.20] [3.87,4.15] 13.99 30.27 [4.98,5.02] [63.18,69.13]
5 [9.72,10.15] [1.66,1.77] [1.53,1.68] [3.05,3.37] 19.44 19.62 [4.93,4.97] [64.93,70.29]
6 [12.66,13.32] [2.35,2.51] [2.91,3.14] [4.66,5.03] 13.08 13.27 [4.85,4.88] [76.29,79.89]
7 [8.85,9.17] [2.54,2.71] [1.10,1.19] [4.65,5.16] 15.65 19.58 [4.86,4.88] [74.07,77.68]
8 [9.59,9.82] [3.01,3.11] [2.76,2.94] [5.66,6.10] 22.78 41.02 [5.04,5.09] [48.86,56.94]
9 [9.98,10.54] [3.32,3.54] [1.53,1.66] [6.18,6.78] 13.30 19.64 [4.88,4.91] [69.43,74.67]
10 [9.97,10.51] [2.28,2.44] [2.32,2.49] [4.19,4.71] 19.64 32.41 [4.97,5.01] [59.20,65.79]

In Fig. 4, the letters C and U represent the lines to be constructed and upgraded, respectively. The letter T represents the substations to be constructed or upgraded. The numbers 1, 2 or 3 in bracket represent the corresponding type.

It can be observed that with the increase of total PV installation capacity, the investment cost, operation and maintenance cost as well as PV generation profit will rise up accordingly, while the network loss cost decreases in general. The solution No. 3 has larger PV capacity but lower total cost compared with solution No. 4, which means an adequate PV capacity can reduce the total cost. For the solutions with similar PV capacity, the PV configuration seems important.

Specifically, a more even PV configuration, i.e., a lower PV configuration uneven degree can lead to a better power flow distribution, which is beneficial for reducing network loss and constraint violation risk. In this case, the voltage and current violation margin is increased, and the DN operational adaptability and PV hosting capacity can be effectively improved.

Meanwhile, each planning scheme corresponds to a certain network structural adaptability. The solutions No. 4, No. 8, and No. 10 have more tie-lines in operation and tighter interconnections between geographical regions, so their power supply reliability and adaptability are stronger. The index of network structural adaptability is equally important for DN planning, so these three solutions may be feasible in practice although most of their objectives are not optimal.

In addition, the variation amplitude of current violation margin is much larger than that of voltage violation margin. This is because the 24-bus system is of small scale and power supply radius, which makes the voltage rise less obvious. In this case, the DN operational adaptability is mainly dependent on current violation margin, and the ratio of α3 and α4 can be set smaller. With the increase of network scale and power supply radius, the variation of voltage violation margin will be more obvious. Especially in the rural DN with long lines, the voltage violation risk is much higher, and the DN operational adaptability is mainly determined by voltage violation margin, which means the ratio of α3 and α4 should be enlarged.

2) AA-POF Analysis

The AA-POF is depicted as a set of cubes (the length, width and height correspond to f̂3, f̂4, and f̂1 in order, respectively) with the mass f2 in the multi-dimensional objective space, as shown in Fig. 5. To compare different objective values more intuitively, the projections of AA-POF on f̂3-f̂4 plane, f̂3-f̂1 plane, and f̂4-f̂1 plane are depicted in Fig. 6(a), (b), and (c), respectively.

Fig. 5  AA-POF in multi-dimensional objective space.

Fig. 6  Projections of AA-POF on different planes. (a) f^3-f^4 plane. (b) f^3-f^1 plane. (c) f^4-f^1 plane.

Following the AA-based dominance relation weakening criterion, all of the ten Pareto optimal solutions obtained have two non-dominated objectives. For instance, the solution No. 6 of Fig. 6(a) has better f̂3 and f̂4 values in the two-dimensional objective space, while its f̂1 and f2 values are both dominated by other solutions in region A. Meanwhile, solution No. 7 of Fig. 6(b) has better f̂1 and f̂3 values while its f2 and f̂4 values are both dominated by other solutions in region B. All other solutions also show the multi-objective mutual dominance characteristics. The final Pareto optimal solutions to be adopted in practice should be selected by the DN planners based on the specific demand of each objective.

3) Deviation Distance Analysis

The deviation distances of all Pareto optimal solutions from the average level are calculated, as shown in Table VI. When only considering affine objectives f̂1, f̂3, and f̂4, solutions No. 6 and No. 7 have greater deviation distances compared with other solutions.

TABLE VI  DEVIATION DISTANCES OF ALL PARETO OPTIMAL SOLUTIONS
kdAVG(xk)OAVG(xk)VAVGV(xk)DAVG(xk)
1 7.0825 0 0.8747 0.6902 2.7613
2 4.4275 0 0.8747 0.7229 1.7045
3 4.5475 0 0.8747 1.0672 1.5458
4 2.3395 0 0.8747 0.6662 0.9206
5 3.0375 0.0005 0.8747 0.7854 1.1419
6 8.9075 0 0.8747 0.6252 3.5631
7 9.5025 0 0.8747 0.6915 3.7029
8 4.1245 0 0.8747 1.0956 1.3886
9 5.0025 0 0.8747 1.1242 1.6681
10 2.3475 0 0.8747 1.1053 0.7878

If the maximum allowable deviation distance Dmax is set as 3.5, solutions No. 6 and No. 7 can be regarded as bad solutions and should be eliminated from the AA-POF. When further considering the deterministic objective f2, the comprehensive deviation distance D˜AVG(xk) can be calculated by (51) and (52), which is compared with DAVG(xk) as shown in Fig. 7.

Fig. 7  Comparison of deviation distances D˜AVG(xk) and DAVG(xk).

After considering the objective f2, the comprehensive deviation distances of solutions No. 6 and No. 8 are enlarged more obviously, because their f2 values are farther from the average level. At this time, only the solutions No. 6 and No. 7 have D˜AVG(xk) values greater than 4.

Therefore, the solutions No. 6 and No. 7 can still be regarded as bad solutions if Dmax is set as 4 or less. And the modified AA-POF consists of eight feasible non-dominated solutions in total, which effectively improves the solution qualities.

D˜AVG(xk)=DAVG(xk)expf2(xk)f2,AVG-1    k=1,2,,10 (51)
f2,AVG=110k=110f2(xk) (52)

C. Result Comparison

1) Different Uncertainty Levels

To quantify the influences of different uncertainty levels, the objectives f^1, f^3, and f^4 of Pareto optimal solutions at the uncertainty levels of ±5%, ±10%, and ±20% are compared in Fig. 8. As can be observed, the interval range of each objective gets wider with the increase of uncertainty level. For the same objective, the interval variations of different solutions at three uncertainty levels are basically the same, while the variation characteristics for different objectives are diverse. Therefore, the selection of uncertainty level is important for the rationality of planning schemes. If the uncertainty level is set too high, the final interval will be too wide, which is of less reference significance. If the uncertainty level is too low, the interval will be too narrow, which cannot quantify the impacts of uncertainties. In reality, multiple planning objectives should be comprehensively considered to determine a reasonable uncertainty level.

Fig. 8  Comparison of interval objective values under different uncertainty levels. (a) f̂1. (b) f̂3. (c) f̂4.

2) Different Uncertainty Analysis Methods

To demonstrate the advantages of the AA-based planning method, the objectives f^1, f^3, and f^4 of all ten Pareto optimal solutions obtained by the AA-, IA-, and MCS-based methods are compared in Fig. 9. As can be observed from Fig. 9, the simulation results of AA-based planning method are nearly close to the MCS-based method. This is because the AA-based planning method can keep track on the dependencies of multiple uncertain variables, so the computation conservativeness can be effectively reduced. In comparison, the IA-based method will obtain less accurate and conservative results for lacking the consideration of dependencies of various uncertain variables. Therefore, the AA-based method has great application values and advantages in the proposed bi-level multi-objective joint planning for its high computation accuracy and low conservativeness.

Fig. 9  Comparison of interval objective values by AA, IA, and MCS methods with uncertainty level of ±10%. (a) f̂1. (b) f̂3. (c) f̂4.

D. Test on Real Chinese 10 kV Distribution System

A real Chinese 10 kV distribution system shown in Fig. 10 is used for another case study to further validate the effectiveness of the proposed method. This system consists of 3 substation buses, 51 load buses, and 56 lines (including 5 tie-lines), which is divided into three geographical regions Z1-Z3. The whole planning horizon is divided into 2 stages, each lasting for 5 years. The data of peak load active power (power factor equals 0.9) and line length are shown in Table VII and Table VIII, respectively. The values of PPV,i,hcap,max and QSVC,i,hmax are set as 300 kW and 150 kvar, respectively. All other parameters are set the same as those of the 24-bus test system.

Fig. 10  Initial topology of real Chinese 10 kV distribution system.

TABLE VII  PEAK LOAD ACTIVE POWER OF CHINESE 10 KV DISTRIBUTION SYSTEM
Bus No.Power (kW)Bus No.Power (kW)Bus No.Power (kW)
Stage 1Stage 2Stage 1Stage 2Stage 1Stage 2
1 112 168 18 0 103 35 55 104
2 86 132 19 104 176 36 107 153
3 116 157 20 128 183 37 116 144
4 87 133 21 101 161 38 95 126
5 92 142 22 124 175 39 108 143
6 0 78 23 75 144 40 84 115
7 0 143 24 83 138 41 65 124
8 0 89 25 0 123 42 0 83
9 75 154 26 123 178 43 0 75
10 0 94 27 0 148 44 74 126
11 0 123 28 0 156 45 0 105
12 0 146 29 0 88 46 0 121
13 106 142 30 0 121 47 0 85
14 74 134 31 105 204 48 105 133
15 0 133 32 127 165 49 0 136
16 0 88 33 0 107 50 0 54
17 0 112 34 0 84 51 0 73
TABLE VIII  LINE LENGTH OF CHINESE 10 KV DISTRIBUTION SYSTEM

Line

No.

lij (km)

Line

No.

lij (km)

Line

No.

lij (km)

Line

No.

lij (km)
1 0.63 15 0.82 29 0.76 43 0.46
2 0.85 16 1.06 30 0.94 44 0.65
3 1.06 17 0.89 31 0.62 45 0.91
4 1.12 18 0.65 32 0.92 46 0.62
5 0.64 19 0.85 33 0.24 47 0.75
6 0.36 20 0.88 34 0.55 48 0.36
7 1.15 21 0.69 35 0.88 49 0.52
8 0.65 22 0.36 36 0.77 50 0.84
9 0.76 23 0.75 37 0.68 51 0.76
10 1.08 24 0.89 38 0.57 52 1.08
11 0.72 25 0.44 39 0.89 53 0.58
12 0.88 26 0.69 40 0.74 54 0.76
13 0.65 27 0.93 41 0.54 55 0.84
14 0.47 28 0.44 42 0.48 56 0.67

1) Bi-level Multi-objective Joint Planning

By using the AA-based dominance relation weakening criterion and bi-level multi-objective solution methodology, a total of five Pareto optimal solutions are obtained. The interval objective values of all Pareto optimal solutions are listed in Table IX and Table X. The planning scheme of Pareto optimal solution No. 1 is shown in Fig. 11.

TABLE IX  INTERVAL OBJECTIVE VALUES OF f̂1, f2, f̂3, AND f̂4
No.f̂1 (M$)f2 (%)f̂3 (%)f̂4 (%)
1 [4.96,5.11] 14.18 [17.59,18.08] [7.49,7.61]
2 [6.54,6.73] 11.19 [18.28,18.65] [5.61,5.66]
3 [6.47,6.67] 16.95 [16.99,17.56] [5.78,5.80]
4 [5.10,5.36] 16.24 [17.12,17.55] [6.80,6.87]
5 [5.61,5.78] 21.83 [15.47,16.12] [6.53,6.57]
TABLE X  INTERVAL OBJECTIVE VALUES OF Dtcd, Dncd, V̂ mar, AND Πmar
No.Dtcd (%)Dncd (%)V̂ mar (%)Πmar (%)
1 6.65 21.71 [4.25,4.34] [70.99,73.03]
2 6.86 15.51 [4.40,4.47] [73.83,75.36]
3 5.64 28.25 [4.36,4.47] [67.53,69.92]
4 6.86 25.61 [4.36,4.45] [68.16,69.97]
5 8.67 34.99 [4.16,4.27] [60.70,63.54]

Fig. 11  Planning scheme of Pareto optimal solution No. 1.

As is observed from Table IX and Table X, solution No. 1 has the smallest f̂1 value and relatively large f̂3 value among five Pareto optimal solutions, while its f2 and f̂4 objectives are poor. In comparison, solution No. 2 has the best f̂3 and f̂4 objectives while its f̂1 and f2 objectives are the worst, which further validates the multi-objective mutual dominance characteristics. The five Pareto optimal solutions obtained represent the non-dominated optimal planning schemes that can simultaneously meet DN economy and adaptability goals considering uncertainties, which is of great significance for practical DN planning in uncertain environment.

On this basis, the deviation distances DAVG(xk) and D˜AVG(xk) of all Pareto optimal solutions are calculated as shown in Table XI. Obviously, solution No. 2 has relatively larger D˜AVG(xk) compared with other solutions. If Dmax is set as 4, solution No. 2 will be a bad solution and should be eliminated. In this way, the final AA-POF can be effectively modified and the solution qualities can be greatly improved.

TABLE XI  DEVIATION DISTANCES OF ALL PARETO OPTIMAL SOLUTIONS
kdAVG(xk)OAVG(xk)VAVGV(xk)DAVG(xk)D˜AVG(xk)
1 2.370 0 0.0058 0.0088 2.3359 2.6704
2 2.763 0 0.0058 0.0035 2.7375 4.2370
3 1.485 0 0.0058 0.0023 1.4731 1.5509
4 0.972 0 0.0058 0.0078 0.9590 0.9686
5 1.762 0 0.0058 0.0044 1.7442 2.2700

2) Parameter Sensitivity Analysis

In the proposed model, the weight coefficients α1 and α2 can quantify the contribution degrees of TCD and NCD to the DN network structural adaptability. Meanwhile, α3 and α4 can quantify contribution degrees of voltage violation margin and current violation margin to the DN operational adaptability. The tuning of these key parameters has more or less impacts on the final planning schemes, so a parameter sensitivity analysis is conducted for the real Chinese 10 kV distribution system as follows.

1) Sensitivity of α1 and α2

Three scenarios are used to analyze the sensitivity of weight coefficients α1 and α2.Scenario 1 is when α1=α2=0.5. Scenario 2 is when α1=0.8 and α2=0.2. Scenario 3 is when α1=0.3 and α2=0.7. The number of final Pareto optimal solutions and average objective values in scenarios 1, 2, and 3 are compared in Table XII.

TABLE XII  COMPARISON OF PLANNING SCHEMES BETWEEN SCENARIOS 1, 2, AND 3
ScenarioKndf̂1avg (M$)f2avg (%)f̂3avg (%)f̂4avg (%)
1 5 [5.74,5.93] 16.08 [17.09,17.59] [6.44,6.50]
2 4 [5.55,5.75] 10.70 [17.12,17.60] [6.61,6.68]
3 5 [5.74,5.93] 19.73 [17.09,17.59] [6.44,6.50]

As can be observed from Table XII, the number of final Pareto optimal solutions Knd in scenario 2 is smaller than those in scenarios 1 and 3. This is because there are obvious differences of NCD values between various solutions while the TCD values have little differences, which means the optimality of objective f2 is more sensitive to the NCD variation.

In scenario 2 with small α2 value, the objective f2 of original Pareto optimal solution No. 3 has a significant decrease due to its large NCD value, which makes solution No. 3 dominated by other solutions. In comparison, all Pareto optimal solutions in scenario 3 can remain optimality due to a larger α2 value than 0.5. Moreover, the objective f2 presents obvious variation between different scenarios, while little change occurs for the other three objectives.

2) Sensitivity of α3 and α4

Three scenarios are used to analyze the sensitivity of weight coefficients α3 and α4. Scenario 1 is when α3=0.8 and α4=0.2. Scenario 4 is when α3=α4=0.5. Scenario 5 is when α3=0.3 and α4=0.7. The final planning schemes in three scenarios are compared in Table XIII. As can be observed from Table XIII, the value of Knd in scenarios 1, 4, and 5 are the same. This is because the test system used is of small scale and power supply radius, which makes the voltage rise less obvious. In this condition, the optimality of objective f̂3 is more sensitive to the current violation margin Πmar rather than voltage violation margin V̂ mar. In the whole solution space, the original five Pareto optimal solutions shown in Table X all have relatively large Πmar values compared with other solutions, so the increase of α4 value will make their optimality stronger. Therefore, the number of final Pareto optimal solutions will remain unchanged.

TABLE XIII  COMPARISON OF PLANNING SCHEMES BETWEEN SCENARIOS 1, 4, AND 5
ScenarioKndf̂1avg (M$)f2avg (%)f̂3avg (%)f̂4avg (%)
1 5 [5.74,5.93] 16.08 [17.09,17.59] [6.44,6.50]
4 5 [5.74,5.93] 16.08 [36.28,37.39] [6.44,6.50]
5 5 [5.74,5.93] 16.08 [49.06,50.57] [6.44,6.50]

V. CONCLUSION

In this paper, IA and AA are applied to quantify PV and load uncertainties, and an AA-based adaptability-oriented bi-level multi-objective joint planning model is built, which can obtain the planning schemes with low constraint violation risk, high reliability, and strong adaptability under uncertainties. On this basis, an AA-NSGA-II-based bi-level multi-objective solution methodology is proposed to calculate AA-POF. The obtained AA-POF represents a set of optimal planning schemes that can simultaneously meet DN economy and adaptability goals considering uncertainties, which is of great significance for practical DN planning in the complex uncertain environment. In addition, an AA-based dominance relation weakening criterion and a deviation distance based AA-POF modification method are proposed to eliminate bad solutions and improve the solution qualities. The simulation results in a modified 24-bus system show the multi-objective mutual dominance characteristics. The comparison of different uncertainty levels shows their diverse interval variations. The comparison of different methods demonstrates the advantages of proposed AA-based planning method for its high computation accuracy and low conservativeness. Moreover, the sensitivity analysis for a real Chinese 10 kV distribution system explores the impacts of key parameters on the final planning schemes.

NOMENCLATURE

Symbol —— Definition
A. —— Sets
Ωn, Ωss, Ωl —— Sets of buses, substation buses, and lines
Ωssa, Ωla —— Sets of candidate substation buses and candidate lines to be constructed
Ωc, Ωk —— Sets of types of substation and conductor
Ωh, Ωt,h —— Sets of stages and time slots in stage h
Ωn,hd, Ωl,hd, Ωl,hd,tie —— Sets of all buses, lines, and tie-lines at substation d in stage h
B. —— Parameters
αloss, αpro —— Network loss cost and photovoltaic (PV) generation profit per unit of electricity
α1, α2 —— Weight coefficients of tie-line connection degree and network cohesion degree
α3, α4 —— Weight coefficients of voltage violation margin and current violation margin
εt,h —— Duration of each time slot in stage h
λ1, λ2 —— Inflation rate and interest rate
css,ccons, cl,kcons, —— Construction costs of type-c substation, unit length conductor-k line, unit PV power, and unit static var compensator (SVC)
cPVcons, cSVCcons
css,cup, cl,kup —— Upgrade costs of type-c substation and unit length conductor-k line
css,co&m, cl,ko&m, —— Operation and maintenance costs of type-c substation, unit length conductor-k line, unit PV power, and unit SVC
cPVo&m, cSVCo&m
Il,kmax, Sl,kmax —— The maximum allowable current magnitude and apparent power for conductor-k line
lij —— Length of line ij
NPVmax, NSVCmax —— The maximum numbers of buses with PV and SVC installations
NΩh, NΩss, NΩn,hd —— Sizes of sets Ωh, Ωss, and Ωn,hd
PPV,i,hcap,max, QSVC,i,hmax —— The maximum PV installation capacity and SVC compensation capacity at bus i in stage h
Ri,AVG —— Average radius of affine polynomial of the ith affine objective
Sss,cmax —— The maximum allowable substation capacity
Vmax —— The maximum allowable voltage magnitude
zl,k —— Unit impedance of conductor-k line
C. —— Variables
σi,c,hcons, δij,k,hcons —— Binary decision variables representing whether constructing type-c substation at bus i and conductor-k line ij in stage h
σi,c,hup, δij,k,hup —— Binary decision variables representing whether upgrading type-c substation at bus i and conductor-k line ij in stage h
βi,h, γi,h —— Binary decision variables representing whether installing PV and SVC at bus i
τi,c,h, μij,k,h —— Binary decision variables representing whether type-c substation at bus i and conductor-k line ij are in operation
η̂PV,h(t) —— Affine PV output efficiency at time t
φPV,i,h —— PV power factor at bus i in stage h
ψij,h, ψji,h —— Binary decision variables representing whether bus i is the parent of bus j
εm —— The mth noise element of affine polynomial
cij,h —— Binary decision variable representing whether bus i and bus j are connected
Dtcd,h, Dncd,h —— Tie-line connection degree and network cohesion degree in stage h
D̂PV,hd —— Affine standard deviation of PV installation capacity for substation d
dAVG(xk) —— Distance between fi0(xk) and fi,AVG0
eij,h —— Electrical distance between buses i and j
f̂inv,h, f̂o&m,h, f̂loss,h, f̂pro,h —— Affine investment cost, operation and maintenance cost, network loss cost, and PV generation profit in stage h
f̂i(xk) —— The ith affine objective of solution xk
fi(0)(xk), fim(xk) —— Central value and the mth noise coefficient of f̂i(xk)
fi,AVG(0), fi,AVG —— Average central value of the ith affine objective and average value of the ith deterministic objective
F̂(xk), F(xk) —— Affine and interval multi-objective vectors of solution xk
F̂AVG, FAVG —— Affine and interval multi-objective vectors of average level
Gij,pf,h, Bij,pf,h —— Line conductance and susceptance between phase-p of bus i and phase-f of bus j in stage h
Îij,p,k,h (t) —— Affine phase-p current magnitude of conductor-k line at time t in stage h
L(), —— Interval length and intersection operation
Nd —— Number of deterministic objectives
OAVG(xk) —— Overlapping volume between hypercubes F(xk) and FAVG
P̂PVcap, Q̂SVC —— Affine PV installation capacity and SVC compensation capacity
P̂i,h(t), Q̂i,h(t) —— Affine active power and reactive power injections of bus i at time t in stage h
P̂PV, i,h (t), Q̂PV, i,h (t) —— Affine PV active power and reactive power of bus i at time t in stage h
P̂L, i,h (t), Q̂L, i,h (t) —— Affine load active power and reactive power of bus i at time t in stage h
Sij,p,k (t) —— Apparent power of conductor-k at time t
Sss,i,c,h (t) —— Capacity of type-c substation at time t
V̂i,h(t), θ̂ij,h(t) —— Affine voltage magnitude of bus i and voltage angle difference between bus i and bus j at time t in stage h
V̂hmar, Îhmar —— Affine voltage violation margin and current violation margin in stage h
VAVG, V(xk) —— Volumes of hypercubes F(xk) and FAVG

REFERENCES

1

F. Olivier, P. Aristidou, D. Ernst et al., “Active management of low-voltage networks for mitigating overvoltages due to photovoltaic units,” IEEE Transactions on Smart Grid, vol. 7, no. 2, pp. 926-936, Mar. 2016. [Baidu Scholar] 

2

H. Wu, Y. Yuan, J. Zhu et al., “Potential assessment of spatial correlation to improve maximum distributed PV hosting capacity of distribution networks,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 4, pp. 800-810, Jul. 2021. [Baidu Scholar] 

3

Y. Chai, L. Guo, C. Wang et al., “Network partition and voltage coordination control for distribution networks with high penetration of distributed PV units,” IEEE Transactions on Power Systems, vol. 33, no. 3, pp. 3396-3407, May 2018. [Baidu Scholar] 

4

A. Kumar and P. Kumar, “Power quality improvement for grid-connected PV system based on distribution static compensator with fuzzy logic controller and UVT/ADALINE-based least mean square controller,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 6, pp. 1289-1299, Nov. 2021. [Baidu Scholar] 

5

A. Luo, Q. Xu, F. Ma et al., “Overview of power quality analysis and control technology for the smart grid,” Journal of Modern Power Systems and Clean Energy, vol. 4, no. 1, pp. 1-9, Jan. 2016. [Baidu Scholar] 

6

A. Keane, L. F. Ochoa, C. L. T. Borges et al., “State-of-the-art techniques and challenges ahead for distributed generation planning and optimization,” IEEE Transactions on Power Systems, vol. 28, no. 2, pp. 1493-1502, May 2013. [Baidu Scholar] 

7

M. Nick, R. Cherkaoui, M. Paolone et al., “Optimal allocation of dispersed energy storage systems in active distribution networks for energy balance and grid support,” IEEE Transactions on Power Systems, vol. 29, no. 5, pp. 2300-2310, Sept. 2014. [Baidu Scholar] 

8

G. Muñoz-Delgado, J. Contreras, and J. M. Arroyo, “Joint expansion planning of distributed generation and distribution networks,” IEEE Transactions on Power Systems, vol. 30, no. 5, pp. 2579-2590, Sept. 2015. [Baidu Scholar] 

9

A. Tabares, J. F. Franco, M. Lavorato et al., “Multistage long-term expansion planning of electrical distribution systems considering multiple alternatives,” IEEE Transactions on Power Systems, vol. 31, no. 3, pp. 1900-1914, May 2016. [Baidu Scholar] 

10

S. Jothibasu, A. Dubey, and S. Santoso, “Two-stage distribution circuit design framework for high levels of photovoltaic generation,” IEEE Transactions on Power Systems, vol. 34, no. 6, pp. 5217-5226, Nov. 2019. [Baidu Scholar] 

11

Y. Fu and H. Chiang, “Toward optimal multiperiod network reconfiguration for increasing the hosting capacity of distribution networks,” IEEE Transactions on Power Delivery, vol. 33, no. 5, pp. 2294-2304, Oct. 2018. [Baidu Scholar] 

12

N. N. Mansor and V. Levi, “Integrated planning of distribution networks considering utility planning concepts,” IEEE Transactions on Power Systems, vol. 32, no. 6, pp. 4656-4672, Nov. 2017. [Baidu Scholar] 

13

Y. Li, W. Gao, W. Yan et al., “Data-driven optimal control strategy for virtual synchronous generator via deep reinforcement learning approach,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 4, pp. 919-929, Jul. 2021. [Baidu Scholar] 

14

S. Sannigrahi, S. R. Ghatak, and P. Acharjee, “Multi-scenario based bi-level coordinated planning of active distribution system under uncertain environment,” IEEE Transactions on Industry Applications, vol. 56, no. 1, pp. 850-863, Jan.-Feb. 2020. [Baidu Scholar] 

15

M. Jooshaki, H. Farzin, A. Abbaspour et al., “A model for stochastic planning of distribution network and autonomous DG units,” IEEE Transactions on Industrial Informatics, vol. 16, no. 6, pp. 3685-3696, Jun. 2020. [Baidu Scholar] 

16

Y. Gao, X. Hu, W. Yang et al., “Multi-objective bilevel coordinated planning of distributed generation and distribution network frame based on multiscenario technique considering timing characteristics,” IEEE Transactions on Sustainable Energy, vol. 8, no. 4, pp. 1415-1429, Oct. 2017. [Baidu Scholar] 

17

S. Wang, Y. Dong, L. Wu et al., “Interval overvoltage risk based PV hosting capacity evaluation considering PV and load uncertainties,” IEEE Transactions on Smart Grid, vol. 11, no. 3, pp. 2709-2721, May 2020. [Baidu Scholar] 

18

S. He, H. Gao, H. Tian et al., “A two-stage robust optimal allocation model of distributed generation considering capacity curve and real-time price based demand response,” Journal of Modern Power Systems and Clean Energy, vol. 9, no. 1, pp. 114-127, Jan. 2021. [Baidu Scholar] 

19

S. Wang, S. Chen, L. Ge et al., “Distributed generation hosting capacity evaluation for distribution systems considering the robust optimal operation of OLTC and SVC,” IEEE Transactions on Sustainable Energy, vol. 7, no. 3, pp. 1111-1123, Jul. 2016. [Baidu Scholar] 

20

X. Chen, W. Wu, B. Zhang et al., “Data-driven DG capacity assessment method for active distribution networks,” IEEE Transactions on Power Systems, vol. 32, no. 5, pp. 3946-3957, Sept. 2017. [Baidu Scholar] 

21

C. Zhang, H. Chen, K. Shi et al., “An interval power flow analysis through optimizing-scenarios method,” IEEE Transactions on Smart Grid, vol. 9, no. 5, pp. 5217-5226, Sept. 2018. [Baidu Scholar] 

22

S. Wang, L. Han, and L. Wu, “Uncertainty tracing of distributed generations via complex affine arithmetic based unbalanced three-phase power flow,” IEEE Transactions on Power Systems, vol. 30, pp. 3053-3062, Nov. 2015. [Baidu Scholar] 

23

S. Wang, K. Wang, F. Teng et al., “An affine arithmetic-based multi-objective optimization method for energy storage systems operating in active distribution networks with uncertainties,” Applied Energy, vol. 223, pp. 215-228, Apr. 2018. [Baidu Scholar] 

24

F. S. Seta, L. W. de Oliveira, and E. J. de Oliveira, “Comprehensive approach for distribution system planning with uncertainties,” IET Generation, Transmission & Distribution, vol. 13, no. 24, pp. 5467-5477, Nov. 2019. [Baidu Scholar] 

25

L. W. De Oliveira, F. D. S. Seta, and E. J. De Oliveira, “Optimal reconfiguration of distribution systems with representation of uncertainties through interval analysis,” International Journal of Electrical Power & Energy Systems, vol. 83, pp. 382-391, Dec. 2016. [Baidu Scholar] 

26

G. Manson, “Calculating frequency response functions for uncertain systems using complex affine analysis,” Journal of Sound & Vibration, vol. 288, no. 3, pp. 487-521, Aug. 2005. [Baidu Scholar] 

27

K. Deb, A. Pratap, S. Agarwal et al., “A fast and elitist multiobjective genetic algorithm: NSGA-II,” IEEE Transactions on Evolutionary Computation, vol. 6, no. 2, pp. 182-197, Apr. 2002. [Baidu Scholar]