Abstract
Relieving congestion significantly influences the operation and security of the transmission network. Consequently, the congestion alleviation of transmission network in all power systems is imperative. Moreover, it could prevent price spikes and/or involuntary load shedding and impose high expenses on the transimission network, especially in case of contingency. Traditionally, the increasing or decreasing generation rescheduling has been used as one of the most imperative approaches for correctional congestion management when a contingency occurs. However, demand response programs (DRPs) could also be a vital tool for managing the congestion. Therefore, the simultaneous employment of generation rescheduling and DRPs is proposed for congestion management in case of contingency. The objective is to reschedule the generation of power plants and to employ DRPs in such a way so as to lessen the cost of congestion. The crow search algorithm is employed to determine the solution. The accuracy and efficiency of the proposed approach are assessed through the tests conducted on IEEE 30-bus and 57-bus test systems. The results of various case studies indicate the better performance of the proposed approach in comparison with different approaches presented in the literature.
THE advent of the smart grid has enabled the customers to play a vital role in the electricity market and change their power consumption when called upon or when the security of the power system is endangered. To participate in the electricity market, the customers should enroll in the programs called demand response (DR) provided by the aggregators. Fast response time is benificail for the DR in congestion management in case of a contingency.
The restructuring of the power system has been proposed to raise the competition in production, resulting in lower prices, increased efficiency, and improved service in the power system. On one hand, in this environment, the investment in the production sector and operation decisions are left to competitive mechanisms while, on the other hand, the transmission network remains a shared and non-competitive service. As a result, in today’s electricity market, the transmission systems are usually utilized at their near full capability. Therefore, they are susceptible to congestion, especially in case of a contingency. The congestion is the use of a power grid outside the permitted range of operation. From the perspective of transmission system, any overload on the transmission lines that occurs in the peak load or under other emergency conditions such as the outage of lines and generators is referred to as a congestion. The combination of the competitive generation sector and the public transmission system has made congestion management arduous. This difficulty will increase as the congestion swells due to the higher rate of increase in transactions of the electricity market compared with that in transmission system expansion.
In the traditional structure, the congestion is resolved using certain instructions. Since the transmission lines prone to congestion are known and their required amount of capacity at a given period depending on the load is almost constant, the main solution to alleviate the congestion increases the installed capacity of transmission lines and/or generation rescheduling. However, in the restructuring era and with the open-access scheme of the transmission network, the congestion has become acuter and its occurrence from a fixed state in traditional systems has altered to an obscure and uncertain state, with extra costs imposed to the power system and sometimes in the places not expected. Under these new conditions, the power system operator has faced many limitations to relieve the congestion, which has eventually resulted in new and different ways of congestion management.
The most common approach for congestion management in case of a contingency has been generation rescheduling. However, the environmental concerns and limited fossil fuel resources have required and motivated the electricity market to fully employ the potentials of DR programs. One of the areas that DR could be implemented is for congestion management. Although there are many studies for utilizing the DR in the day-ahead market for congestion management, only a few studies explore the use of these resources for real-time deployment of DR for congestion management, especially in case of a contingency. Therefore, we mainly aim to simultaneously utilize the generation rescheduling and DR programs (DRPs) for relieving the congestion in case of a contingency in a way that reduces the operation costs.
Considering the importance and significance of congestion mitigation in the restructured power systems, several schemes have been proposed in the literature. These approaches include flexible AC transmission system (FACTS) devices [
Reference [
Generation rescheduling for congestion management using evolutionary algorithms is the subject of many researchers in recent years. The differential evolution algorithm is proposed in [
In [
Approaches are involved by DRPs to lessen power consumption. Furthermore, enough motivations could entice customers to participate in the electricity market and lead to a completely competitive market. DRPs have designed exceptional chances for consumers to be a part of the market and play an essential role [
DRPs are used for congestion management in several studies. In [
Recent decades have been the realm of evolutionary algorithms, and many approaches are introduced that have evolved the optimization process in many subjects, especially in engineering, and many of these approaches are used in practical cases. Crow search algorithm (CSA) is one of the latest and sturdiest evolutionary algorithms [
The main contributions of this study are twofold.
1) As discussed in the literature review, on one hand, the DRPs are previously applied in day-ahead electricity markets to mitigate transmission network congestion [
2) A novel formulation is proposed for DRPs to develop a relationship between the value of incentive paid to customers and the value of their participations in DRPs using the concept of price elasticity. Employing this relationship, the proposed approach evaluates the value of incentive which allows for the exploitation of customers’ participation in DRPs. The best buses for the deployment of DRPs are also discovered. In most of the studies of utilizing DRPs for congestion management, the location of DRPs or the value of the incentive is presumed. While in this paper, the best location for the deployment of incentive-based DRPs and the proper value of incentive paid to the customers are determined.
Other features of this paper are as follows.
1) The CSA is employed as a powerful optimization tool [
2) The overload in the transmission lines arisen by several studied contingencies is efficiently eliminated with the DRPs and the least alteration in the generation schedule.
3) The total quantity of rescheduling and losses is depreciated for different considered crises.
4) Several security restrictions including line loading and bus voltage are considered while modeling and solving this optimization problem.
5) An effective penalty mechanism is deployed to penalize constraint violations and at the same time prevent the elimination of good solutions that slightly infringe one or a few limits. Therefore, with a slight modification, they could become free of constraint contravention.
6) The effectiveness of the proposed approach is proven over other approaches.
The rest of this paper is organized as follows. The problem modeling and formulation are provided in Section II. Section III deals with the optimization procedure and the obtained results are provided and discussed in detail in Section IV. Concluding remarks are drawn in Section V.
This section provides the problem formulation of congestion management. Primarily, the objective function for generation rescheduling without DRPs is mathematically delineated and then the equality and inequality constraints are presented. Afterward, the model of DRPs developed for this paper is explained. Finally, the objective function for generation rescheduling with DRPs is provided.
The primary purpose of congestion management is to minimize the costs while meeting the constraints of power system and units. In this paper, the generation rescheduling is used to mitigate the congestion caused by contingencies such as transmission line outages. However, the generation companies (GenCos) change their output active power at a cost, which is provided in their offers. Therefore, the objective function is to minimize the congestion costs [
(1) |
This optimization problem is subjected to various equality and inequality constraints presented in the following subsection.
The following equations provide the equality constraints of the optimization problem under study. Equations (
(2) |
(3) |
(4) |
(5) |
It should be noted that index k is for all the buses of the system, and if there is no generation at a given bus, the values of and will be zero. If there is more than one unit at a bus, the values of and will be the sum of active and reactive generations at that bus, respectively.
The inequality constraints are those related to operation and physical limitations of the transmission facilities and generators as provided in (6)-(10) [
(6) |
(7) |
(8) |
(9) |
(10) |
(11) |
We aim to deploy the incentive-based DRPs along with generation rescheduling to manage the congestion in case of contingency. For a sufficiently high remuneration, it is assumed that customers enlisted in DRPs will reduce their power consumption when needed. However, the relationship between the participation level of customers in DRPs and the value of incentive that they receive should be determined.
References [
(12) |
Therefore, the consumption of customers after the deployment of DRPs is as follows [
(13) |
Since the real-time congestion management in case of contingency is considered, the parameter t could be ignored. Moreover, the proper value of incentive and the best level of participation of DRPs are determined. The participation level of DRPs at each bus should be lower than a predefined value.
(14) |
The cost of employing DRPs could be calculated using the value of incentive and the participation level of DRPs.
(15) |
CostDRP indicates the total value of incentive paid to customers. Therefore, neglecting the penalties, A could be written as (16) using (13).
(16) |
Combining the constant indices, A(t) can be rewritten as:
(17) |
(18) |
(19) |
Furthermore, D and E(t,t) are pre-specified and constant. Consequently, the total value of incentive paid to the customers in (15) could be rewritten as:
(20) |
(21) |
It should be noted that the higher the value of the incentive is, the more customers are enticed to participate in the electricity market.
Considering that DRPs for congestion management changes the formulation of the objective function, the cost of deploying DRPs should also be considered to realize the contributions. Therefore, the objective function considering DRPs is to minimize total costs related to generation rescheduling and the implementation of DRP and could be formulated as:
(22) |
The objective is to simultaneously minimize the cost of generation rescheduling and the cost of DRPs . The variables optimized are the increment and decrement of active power for generators and the amount of load reduction for DRPs at each bus of the power system. With (17), the value of incentive paid to the customers that are employed for DR provision is determined by using the values found for load reductions in the optimization problem. The constraints are the same as those presented in Section II-B along with the constraint related to DRPs in (14).
One of the foremost inspirations of this paper is to create a user-friendly evolutionary approach with a simple concept and easy implementation that can achieve satisfactory results while solving the optimization problem. In this regard, CSA [
For the optimization problem, there could be a solution that has great fitness but slightly violates a constraint. From the crisp perspective, this solution will be discarded. However, with a small modification, a good solution may result. Therefore, in this paper, a penalty approach is applied from [
The inequality limits, including power flow limit on transmission lines and constraints regarding the voltage of each bus, are turned into the penalty functions which in turn are combined with the objective function. The equality limits as well as reactive power inequality constraints are effectively managed by Newton-Raphson power flow [
(23) |
C is the objective function calculated using (1) and (22) without and with DRP, respectively, and PFT and PFV are calculated using (24) and (25), respectively, based on [
(24) |
(25) |
Note that the fitness function incorporating the constraints is determined, and the proposed approach based on CSA could be applied. This procedure is explained as follows.
Step 1: read the load, line, and bus data along with the price bids and the information of GenCos and DRPs.
Step 2: design a contingency by line outage and/or load increase.
Step 3: perform the load flow and determine the overloaded lines and violation of bus voltage.
Step 4: determine the permissible range of rescheduling of each generator using (11).
Step 5: determine the permissible range of each bus for participating in DRPs.
Step 6: initialize the first population of CSA and memory of crows, which is randomly resolved within the limits determined in the above steps.
Step 7: execute load flow for each member of the population and and check the equality and inequality constraints.
Step 8: using the data obtained from the load flow execution, penalty functions are determined using (24) and (25). Consequently, the fitness function is appraised by (23).
Step 9: create a new population of crows using the following equation.
(26) |
Employing (26), the position of the crow, when following crow n, is updated using its current location , the flight length FL, the memory of the crow , the awareness probability of the
Step 10: evaluate the fitness function for the new population and update the memory of crows. The new position of a crow has better fitness (lower objective function) compared with the current memory of the same crow.
Step 11: stop the optimization procedure if it arrives at the maximum number of iterations. Otherwise, it returns to Step 9.
To verify the effectiveness of the CSA in solving the congestion management problem, the proposed approach is carried out on the modified IEEE 30-bus and 57-bus test systems. The data of these test systems are extracted from [
The loads, offers of GenCos, and transmission network data for both test systems can be found in [
The best solution is reported out of 20 independent execution of the proposed approach. It should be noted that FL and AP are set to be 0.19 and 0.1, respectively. Besides, the maximum number of iterations is 100 for all cases.
For each test system, four different cases of congestion are considered. In cases 1 and 2, DRPs are not considered. The objective function is provided in (1). While in cases 3 and 4, DRPs are integrated in the electricity market for congestion management, and the objective function is provided in (22). Note that the fitness function should be evaluated using (23) in which C is calculated using (1) or (22).
This test system has 41 transmission lines, 24 load buses, and 6 generators. The cumulative active and reactive loads are 283.4 MW and 126.2 Mvar, respectively. The price bids provided by the GenCos for IEEE 30-bus test system are presented in
The primary market-clearing values are considered to be the same as the generation and load values in [
In case 1, it is assumed that line 1 that connects the buses 1 and 2 of the systems experiences an outage. Due to the disconnection of this line, the congestion occurs, and lines 2 (between buses 1 and 7) and 4 (between buses 7 and 8) are overloaded. Right after the outage of line 1, the flows of these lines are equivalent to 147.43 MW and 136.29 MW, respectively, which violates the line limit of 130 MW for both lines. Therefore, the generation rescheduling should be employed to mitigate the congestion. The best rescheduling arrangement obtained by the proposed approach to solve the congestion problem is illustrated in
From the results in
In case 2, it is assumed that line 2 that connects buses 1 and 7 of the systems encounters an outage. To exert more pressure on the transmission network, an increase in the system load by 50% is considered. It is assumed that the load of all buses is 1.5 times the base state and the load of each bus is proportional to its baseload. This increase is considered for both active and reactive power. After the outage of line 2, an overload is observed in lines 1 (connecting buses 1 and 2), 3 (connecting buses 2 and 8), and 6 (connecting buses 2 and 9). The power flow [
Therefore, the proposed approach is employed to alleviate the congestion. The obtained results using the proposed approach for this case are presented in
Case 3 is similar to case 1 and the only difference is the consideration of DRPs for congestion management. Therefore, it is assumed that line 1 ceases to connect buses 1 and 2 of the test system, which will lead to the congestion in the transmission network like case 1. Therefore, the generation rescheduling and DRPs should be utilized suitably to alleviate the congestion. The results for case 3 are shown in
It should be noted that in order to prevent the complications in managing the transmission network, only the buses that provide more than 0.5 MW in DRPs are considered here and all values for load reduction are not allowed. In case 3, DRP is employed in bus 4 and the participation level is 0.95 MW. The total congestion cost for case 3 is 446.2407 $/h, which shows about a 9% reduction compared with that of case 1.
In this case, the cost of generation rescheduling is 385.9101 $/h and the cost of the employment of DRP is 60.3306 $/h. The results obtained demonstrate that the deployment of DRP could effectively reduce the congestion cost. The value of incentive for this case is 63.4195 $/MWh, which is much higher than the cost of all generators’ increment, but it could reduce the total congestion cost of power system.
In case 4, line 2 fails to serve. A growth of 50% in the load of all buses of the power system is also taken into account, which is considered for both active and reactive power. In this case, generators along with DRPs are deployed to solve the problem of congestion in the transmission network. The results for case 4 are shown in
The proposed approach employs DRPs at buses 2-4 to help reduce the congestion. The amount of load reductions are 1.07 MW for bus 2, 3.26 MW for bus 3, and 1.02 MW for bus 4. Moreover, the total variation in generation scheduling is about 12% lower when DRPs are deployed. As shown in
The value of incentive paid to each customer is a function of the bus load and the amount of load reduction. In case 4, the values of incentive for customers 2, 3, and 4 are 65.82 $/h, 46.158 $/h, and 45.4317 $/h, respectively, which demonstrates that the proposed approach effectively determines the proper value of incentive and the best amount of load reduction at each bus for congestion mitigation.
This test system has 7 generators, 50 load buses, and 80 transmission lines. Aggregated active and reactive loads are 1250.8 MW and 336 Mvar, respectively. Four different cases are investigated for this test system.
In case 1, to create the congestion, the line limits are set to be 175 MW for line 8 (5-6) and 35 MW for line 10 (6-12), instead of 200 MW and 50 MW in the original test system, respectively. Due to these changes, the overload is observed in lines 5-6 and 6-12 that are transferring the electric power of 195.97 MW and 49.35 MW, respectively. Therefore, CSA is employed to eliminate the overloads in the transmission network. As a result, the congestion is entirely managed and the overloads are lifted. Details of the results are presented in
In case 2, to create the congestion, the capacity limit of line 2 (connecting buses 2 and 3) is set to be 20 MW (initial value is 85 MW). Under the base condition, 37.048 MW of electric power is flowing over this line, consequently, there will be an overload in this line after diminishing its limit. To relieve the congestion, active power rescheduling of GenCos is executed by applying the proposed approach.
The results of the proposed approach are tabulated in
Similar to case 1, in case 3, the transfer limits of lines 8 and 10 reduce to 175 MW and 35 MW, respectively. The proposed approach is employed to manage the congestion using generation rescheduling and DRPs. All buses are the candidates to provide demand reduction and 10% of the load of each bus is considered as the price responsive load that could diminish its power consumption regarding the incentive that they receive.
Similar to case 2 for the test system, there is a congestion in line 2 because of the capacity limit reduction. DRPs along with generation rescheduling of GenCos are employed together to alleviate the congestion. The proposed approach is utilized to find a proper strategy of the deployment of DRPs and a best approach of using GenCos to solve the congestion problem for this case. The best solution attained is provided in
In case 4, customers at buses 1, 4, and 5 are asked to reduce their power consumption by 1.82 MW, 3.12 MW, and 5.89 MW, respectively. The value of incentive paid to each customer is different so that the customer at bus 1 receives 66.017 $/MWh reduction in their power consumption. The value of 83.085 $/MWh is paid to the end-users at bus 4 for the same service, while customers at bus 5 receives 78.517 $/MWh.
We attempt to determine the suitable generation rescheduling of GenCos and the best strategy for deploying DRPs to minimize the congestion cost of transmission network. All restrictions regarding the power system, transmission lines, DRPs, and GenCos are also contemplated. Contingencies including sudden load variations and line outage are assumed to create the congestion, and CSA is executed for proper generation rescheduling and the implementation of DRPs. The proposed approach is carried out on the IEEE 30-bus and 57-bus test systems. The results obtained show that DRPs could be of great help to lessen the cost of congestion in case of contingencies. Moreover, the appropriate values of incentive paid to each customer for participation in DRPs and the their participation level are determined.
The proper value of the incentive is different for each bus which is accurately determined by the proposed approach. Different case studies indicate the better execution of the proposed approach in finding the solution. Comparing the results with those of other approaches presented in the literature, it is shown that the proposed approach shows a better performance in finding the solution, so that the cost of congestion is less than other approaches. The electric vehicles along with DRPs and the rescheduling could be the direction of future studies.
References
A. K. Sharma, R. K. Mittapalli, and Y. Pal, “FACTS devices cost recovery during congestion management in deregulated electricity markets,” Journal of The Institution of Engineers (India): Series B, vol. 97, pp. 339-354, Sept. 2016. [Baidu Scholar]
A. S. Siddiqui and T. Deb, “Application of multiple FACTS devices of similar type for congestion mitigation,” International Journal of System Assurance Engineering & Management, vol. 7, pp. 387-397, Sept. 2016. [Baidu Scholar]
M. T. Khan and A. S. Siddiqui, “Congestion management in deregulated power system using FACTS device,” International Journal of System Assurance Engineering & Management, vol. 8, pp. 1-7, Jan. 2017. [Baidu Scholar]
M. Afkousi-Paqaleh, A. A. T. Fard, and M. Rashidi-Nejad, “Distributed generation placement for congestion management considering economic and financial issues,” Electric Engineering, vol. 92, pp. 193-201, Nov. 2010. [Baidu Scholar]
M. Afkousi-Paqaleh, A. A.-T. Fard, M. Rashidinejad et al., “Optimal placement and sizing of distributed resources for congestion management considering cost/benefit analysis,” in Proceedings of IEEE PES General Meeting, Minneapolis, USA, Jul. 2010, pp. 1-7. [Baidu Scholar]
M. Afkousi-Paqaleh, A. R. Noory, A. Abbaspour et al., “Transmission congestion management using distributed generation considering load uncertainty,” in Proceedings of Asia-Pacific Power and Energy Engineering Conference, Chengdu, China, Mar. 2010, pp. 1-4. [Baidu Scholar]
Z. Liu, B. Tessema, G. Papaefthymiou et al., “Transmission expansion planning for congestion alleviation using constrained locational marginal price,” in Proceedings of IET Conference on Reliability of Transmission and Distribution Networks (RTDN 2011), London, UK, Jun. 2011, pp. 1-6. [Baidu Scholar]
J. A. C. Miclat, A. J. S. Patubo, R. D. del Mundo et al., “Using the transmission congestion expectation (TCE) in optimal transmission expansion planning,” in Proceedings of IEEE 16th International Conference on Environment and Electrical Engineering (EEEIC), Florence, Italy, Jul. 2016, pp. 1-4. [Baidu Scholar]
M. Pantos, “Market-based congestion management in electric power systems with increased share of natural gas dependent power plants,” Energy, vol. 36, no. 7, pp. 4244-4255, Jul. 2011. [Baidu Scholar]
S. Dutta and S. P. Singh, “Optimal rescheduling of generators for congestion management based on particle swarm optimization,” IEEE Transactions on Power Systems, vol. 23, no. 4, pp. 1560-1569, Nov. 2008. [Baidu Scholar]
P. Borkar, N. Kumar, and D. Choudhary, “Active power rescheduling of generator for congestion management using whale optimization technique,” in Proceedings of 2018 International Conference on Smart Electric Drives and Power System (ICSEDPS), Nagpur, India, Sept. 2018, pp. 142-146. [Baidu Scholar]
M. Esmaili, H. A. Shayanfar, and N. Amjady, “Multi-objective congestion management incorporating voltage and transient stabilities,” Energy, vol. 34 no. 9, pp.1401-1412, Sept. 2009. [Baidu Scholar]
M. Esmaili, N. Amjady, and H. A. Shayanfar, “Stochastic congestion management in power markets using efficient scenario approaches,” Energy Conversion Management, vol. 51, no. 11, pp. 2285-2293, Nov. 2010. [Baidu Scholar]
S. T. Suganthi, D. Devaraj, K. Ramar et al., “An improved differential evolution algorithm for congestion management in the presence of wind turbine generators,” Renewable and Sustainable Energy Reviews, vol. 81, no. 1, pp. 635-642, Jan. 2018. [Baidu Scholar]
S. Verma and V. Mukherjee, “Firefly algorithm for congestion management in deregulated environment,” Engineering Science and Technology, an International Journal, vol. 19, no. 3, pp. 1254-1265, Sept. 2016. [Baidu Scholar]
M. M. Esfahani, A. Sheikh, and O. Mohammed, “Adaptive real-time congestion management in smart power systems using a real-time hybrid optimization algorithm,” Electric Power Systems Research, vol. 150, pp. 118-128, Sept. 2017. [Baidu Scholar]
N. K. Yadav, “Rescheduling-based congestion management scheme using particle swarm optimization with distributed acceleration constants,” Soft Computing, vol. 23, pp. 847-857, Feb. 2019. [Baidu Scholar]
G. S. Jasmine and P. Vijayakumar, “Congestion management in deregulated power system using heuristic search algorithms incorporating wireless technology,” Wireless Personal Communications, vol. 94, pp. 2665-2680, Jun. 2017. [Baidu Scholar]
S. Verma, S. Saha, and V. Mukherjee, “Optimal rescheduling of real power generation for congestion management using teaching-learning-based optimization algorithm,” Journal of Electrical Systems and Information Technology, vol. 5, no. 3, pp. 889-907, Dec. 2018. [Baidu Scholar]
S. Balaraman and N. Kamaraj, “Transmission congestion management using particle swarm optimization,” Journal of Electric Systems, vol. 7, no. 1, pp. 54-70, Mar. 2011. [Baidu Scholar]
S. Verma and V. Mukherjee, “A novel flower pollination algorithm for congestion management in electricity market,” in Proceedings of 3rd International Conference on Recent Advances in Information Technology (RAIT), Dhanbad, India, Aug. 2016, pp. 203-208. [Baidu Scholar]
S. R. Salkuti and S. Kim, “Congestion management using multi-objective glowworm swarm optimization algorithm,” Journal of Electrical Engineering & Technology, vol. 14, pp. 1565-1575, Jul. 2019. [Baidu Scholar]
A. Narain, S. K. Srivastava, and S. N. Singh, “Congestion management approaches in restructured power system: key issues and challenges,” The Electricity Journal, vol. 33, no. 3, p. 106715, Apr. 2020. [Baidu Scholar]
Federal Energy Regulatory Commission. (2008, Dec.). Assessment of demand response and advanced metering. [Online]. Available: https://www.ferc.gov/sites/default/files/2020-04/demand-response_4.pdf [Baidu Scholar]
P. Faria, J. Spínola, and Z. Vale, “Reschedule of distributed energy resources by an aggregator for market participation,” Energies, vol. 11, no. 4, pp. 713-728, Mar. 2018. [Baidu Scholar]
A. Yousefi, T. T. Nguyen, H. Zareipour et al., “Congestion management using demand response and FACTS devices,” International Journal of Electric Power Energy Systems, vol. 37, no. 1, pp. 78-85, May 2012. [Baidu Scholar]
F. Shen, Q. Wu, S. Huang et al., “Two-tier demand response with flexible demand swap and transactive control for real-time congestion management in distribution networks,” International Journal of Electrical Power & Energy Systems, vol. 114, p. 105399, Jan. 2020. [Baidu Scholar]
J. Wu, B. Zhang, Y. Jiang et al., “Chance-constrained stochastic congestion management of power systems considering uncertainty of wind power and demand side response,” International Journal of Electrical Power & Energy Systems, vol. 107, pp. 703-714, May 2019. [Baidu Scholar]
E. Dehnavi and H. Abdi, “Determining optimal buses for implementing demand response as an effective congestion management method,” IEEE Transactions on Power Systems, vol. 32, no. 2, pp. 1537-1544, Mar. 2017. [Baidu Scholar]
F. Zaeim-Kohan, H. Razmi, and H. Doagou-Mojarrad, “Multi-objective transmission congestion management considering demand response programs and generation rescheduling,” Applied Soft Computing, vol. 70, pp. 169-181, Sept. 2018. [Baidu Scholar]
A. Askarzadeh, “A novel metaheuristic method for solving constrained engineering optimization problems: crow search algorithm,” Computers & Structures, vol. 169, pp. 1-12, Jun. 2016. [Baidu Scholar]
S. Makhdoomi and A. Askarzadeh, “Optimizing operation of a photovoltaic/diesel generator hybrid energy system with pumped hydro storage by a modified crow search algorithm,” Journal of Energy Storage, vol. 27, p. 101040, Feb. 2020. [Baidu Scholar]
M. Gharibi and A. Askarzadeh, “Size optimization of an off-grid hybrid system composed of photovoltaic and diesel generator subject to load variation factor,” Journal of Energy Storage, vol. 25, p. 100814,Oct. 2019. [Baidu Scholar]
A. Omar, H. M. Hasanien, M. A. Elgendy et al., “Identification of the photovoltaic model parameters using the crow search algorithm,” The Journal of Engineering, vol. 2017, no. 13, pp. 1570-1575, Jan. 2018. [Baidu Scholar]
A. M. Shaheen and R. A. El-Sehiemy, “Optimal allocation of capacitor devices on MV distribution networks using crow search algorithm,”CIRED-Open Access Proceedings Journal, vol. 2017, no. 1, pp. 2453-2457, Oct. 2017. [Baidu Scholar]
D. P. Kothari and J. S. Dhillon, Power System Optimization. New Delhi: Prentice-Hall of India, 2011. [Baidu Scholar]
D. S. Kirschen and G. Strbac, Fundamentals of Power System Economics. New York: John Wiley & Sons Ltd, 2004. [Baidu Scholar]
H. A. Aalami, M. P. Moghaddam, and G. R. Yousefi, “Demand response modeling considering interruptible/curtailable loads and capacity market programs,” Applied Energy, vol. 87, no. 1, pp. 243-250, Jan. 2010. [Baidu Scholar]
H. A. Aalami, M. P. Moghaddam, and G. R. Yousefi, “Modeling and prioritizing DRPs in power markets,” Electric Power Systems Research, vol. 80, no. 4, pp. 426-435, Jan. 2010. [Baidu Scholar]
M. Afkousi-Paqaleh and S. H. Hosseini, “Transmission constrained energy and reserve dispatch by harmony search algorithm,” in Proceedings of IEEE PES General Meeting, Calgary, Canada, Jun. 2009, pp. 1-8. [Baidu Scholar]
H. Saadat, Power System Analysis. New Delhi: Tata McGraw Hill Ltd, 2002. [Baidu Scholar]