Abstract
Electric boilers (EBs) provide an alternative method to deal with the accommodation of curtailed wind power. To pursue the minimum coal consumption in the system, a dispatching model integrating combined-heat-and-power (CHP) plants and EBs in different locations is developed, and the penalty of wind power curtailment and cost of EB employment are also incorporated in the model. The transmission loss and transportation lag of heat-supply network as well as the elasticity of heat load are considered in this paper. A kind of constrained programming with stochastic and fuzzy parameters is applied to deal with the uncertainties. A case in East Inner Mongolia in China demonstrates that the EBs are able to absorb curtailed wind power and supply the heat. The results indicate that the utility of EBs in the primary or secondary heat-supply network to accommodate curtailed wind power is mainly related to the efficiency of heat transmission and the elasticity of heat load.
IN recent years, the installed capacity of wind power in China increased rapidly, with an average annual growth of 25.7% from 2010 to 2018.
Based on coordinated operation of thermal system and power system, wind power consumption is promoted and can adapt to the difference between the peak load and valley load. In the literature, there are lots of research works, which review the operation and applications of energy storage technologies [
In a power system with CHP units, the allocation of electric heat pumps or EBs could relax the heat-electric constraints of CHP units and allow more wind power integrated into the power grid. A few studies have demonstrated the superiorities of EB in increasing wind power penetration in different countries [
Previous studies indicate that the curtailed wind power declines with the enlargement of EBs for heating. The flexible start-up and convenient installation endow EBs with a natural feature to adapt to the fluctuation of heat load. Reference [
The above studies mainly concentrate on discussing the effectiveness of EBs in consuming high penetration of wind power. However, the equipped location of EBs has been hardly investigated, which is important because the equipped location of EBs would influence the accommodation of wind power directly or indirectly when the heat network characteristics are considered. Reference [
Hence, we develop an alternative scheme by introducing EBs into EIM power grid to reduce curtailed wind power and discuss how the different locations of EBs in heat-supply network influence the utility to accommodate curtailed wind power.
In comparison with the current research works, the main contributions of this paper can be summarized as follows.
1) A novel scheme of installing EBs in secondary heat-supply network (SHSN) or in primary heat-supply network (PHSN) is proposed to integrate with high penetration of wind power. Four different schemes considering no EBs, EBs only in PHSN, EBs only in SHSN, and EBs both in PHSN and in SHSN are designed to accommodate curtailed wind power in power systems containing a coal-fired CHP.
2) Considering the transmission loss and transportation lag of heat-supply network, the uncertainties of wind power and power load, and elasticity of heat load, an economic dispatching model combining power load, heat load, and wind power is constructed to achieve the aim of least coal consumption for the developed four schemes.
3) To deal with the uncertainties, the existing literature mostly regards the wind power generation or power load as single random variables or single fuzzy variables. Considering different characteristics of wind power and power load, a kind of constrained programming with stochastic and fuzzy parameters is applied.
The rest of this paper is organized as follows. Section II analyzes the mechanism of accommodating curtailed wind power in a power system with CHPs. Section III designs the scheme for accommodating curtailed wind power through equipping EBs in different locations of heat-supply network. The dispatching model aiming at obtaining minimum coal consumption is constructed in Section IV. A case in EIM power grid is analyzed in Section V, and the conclusion is drawn in Section VI.
The relation of heat-power coupling in CHP plants impacts on the accommodation of wind power in power grid directly. Considering the commonly used air-extraction CHP plant, its operation characteristic between heat and power is shown in [

Fig. 1 Load and generation curves of various units.
At night, the power load of EIM power grid is very low, but the output of wind power is usually the largest in the day. Additionally, the increasing heat load in winter raises the forced output of CHP plants. Hence, combining the two types of plants leads to a lot of redundant power. To maintain the security and stability of power grid, some TP plants may need to be shut down. Once the generated power is higher than the power load of the power grid, wind power has to be curtailed to avoid the shut down of some TP plants, as shown in

Fig. 2 Load and generation curves of various units in power system including EBs.
For wind power curtailment, the configuration of EBs in the heat-supply network can decouple the heat-power coupling for CHP plants and enhance the ability to accommodate wind power. For the installation location of the EBs, we design a scheme of the EBs installed at the supply side or load side to accommodate wind power, which is shown in

Fig. 3 Schematic diagram of EBs deployed to accommodate wind power curtailment.

Fig. 4 Specific diagram of EBs configured in PHSN and SHSN.
The purpose of the proposed scheme is to increase the EBs in PHSN or in SHSN for peak-shaving, and the effectiveness of the four schemes will be evaluated. The main heat sources are CHP plants, which are responsible for basic heat load. As another kind of heat sources, the EBs offer the regulation of peak load in the heating system. Owing to the lower power load, higher heat load, and larger output of wind power at night in winter, wind power curtailment occurs more frequently. Hence, heat load provided by CHP plants can be reduced at night with the increasing power load consumed by the EBs, which may free up more space for higher penetration of wind power. Furthermore, the proposed scheme also has the following advantages.
1) The EBs are able to satisfy the fluctuant heat load rapidly and precisely with the merits of fast start-up feature.
2) Practically, the residential heat network is naturally composed of several SHSNs. The capacity of each EB allocated in these SHSNs is relatively small, and the scheme including multiple EBs in SHSNs is more practical than that including single EB with a huge capacity.
3) The objective of EBs working together in PHSN and SHSN is similar to accomplish coarse and fine adjustments of the heat load. EBs dispersedly installed in some heat exchange stations (HESs) of SHSN are close to the center of heat load, which are able to accurately adjust the heat load with lower thermal losses. Whereas EBs deployed in PHSN can coordinately work with CHP plants and achieve the adjustment of the heat load in the whole heat network.
The power system contains three primary kinds of power plants including TP plants, CHP plants and wind power plants. The simple structure of the 3-node power grid is shown in

Fig. 5 Simplified structure of power grid.
(1) |
(2) |
where is the coal consumption of TP unit; a1i, a2i, and a3i are the parameters indicating coal consumption; is the coal consumption of CHP unit; b1i, b2i, b3i, b4i, b5i, and b6i are the parameters describing coal consumption; and are the generated power at time t for the
The output of TP plants must be bounded between the maximum and minimum power values.
(3) |
where and are the minimum and maximum power at time t for the
Additionally, the rates of ramp-up and ramp-down for TP plants within a certain time interval should be controlled in a reasonable range.
(4) |
where and are the rates of ramp-up and ramp-down at time t for the
During the start-up process, the power output of TP plant satisfies the following condition:
(5) |
where describes the running status for the
The outputs of power and TP are within the ranges of the minimum value and the maximum value, respectively.
(6) |
(7) |
(8) |
where and are the minimum and the maximum power at time t for the CHP unit, respectively; and are the minimum and the maximum quantities of stream extraction at time t for the CHP unit, respectively; is the number of CHP units; and kd is the coefficient depicting the relation between power and the quantity of extraction stream.
Similarly, the rates of ramp-up and ramp-down for CHP plant should also be restricted.
(9) |
where and are the rates of ramp-up and ramp-down at time t for the CHP unit, respectively.
For each bus at time t, the power consumed by power load and EBs is balanced with the sum of the power transmitted from other buses, and the power generated by TP plants, CHP plants and wind farms.
(10) |
where is the consumed wind power; is the power load at time t; n is the number of the transmission lines at bus v; and is the power transmitted by transmission lines connected to bus .
Meanwhile, the transmission power on each transmission line should be limited by:
(11) |
where is the transmission limit of the transmission line . A linear DC power flow model [
The predicted wind power should be equal to the sum of the curtailed wind power and the consumed wind power.
(12) |
where is the predicted power of wind power at time t; and is the curtailed wind power at time t.
The consumed power for EBs should be lower than the maximum value of power.
(13) |
(14) |
where and are the maximum power for the
The constraint of the power indicated in (10) disregards the uncertainties of wind power generation and power load. If the prediction values of wind power generation and power load are regarded as definite values, the uncertainties of wind power generation and power load can be embodied by their prediction errors. Then, the condition of equality constraint for bus 1 can be updated and rewritten as below through the introduction of related chance constraints.
(15) |
where is the prediction error of wind power at time t; is the prediction error of power load at time t; is the confidence level of random variable ; is the predetermined confidence level of fuzzy variable ; and denotes the possibility of the event in .
Influenced by various environmental factors such as air temperature and humidity, the output error of wind power is frequently difficult to be expressed by statistical property. Hence, the prediction error of wind power is given as a fuzzy variable, which is more consistent with its characteristic. In practice, the prediction error is represented as a triangular fuzzy variable and its triangular fuzzy parameter and membership function can be expressed as:
(16) |
(17) |
where is the threshold value of the prediction error.
Furthermore, one of the features for the power load is the periodicity to some extent. The prediction error of the power load is insensitive to the prediction time and is proportional to the size of power load. Therefore, the prediction error is represented as a Gaussian statistical variable, which is given as:
(18) |
(19) |
where is the variance.
For the fuzzy case, we use the fuzzy simulation method [
The heat production of a CHP plant can be calculated as:
(20) |
where is the quantity of stream extraction at time t in the
(21) |
(22) |
where and are the heat production of the EB in PHSN and the EB in SHSN at time t, respectively; and and are the conversion efficiencies from electricity to heat for the
HESs are modeled as the isolation device between the PHSN and SHSN. The heat loss in HES is neglected and the transmission loss of primary heat-supply network is considered.
The heat network has been simplified to the line networks, where all consumers receive hot water from a single supply pipe and direct the cooled water to a single return pipe as shown in
Since the scale of SHSN is smaller than that of PHSN, we mainly consider the characteristics of PHSN in two aspects: the transportation lag and transmission loss. is the time required for the water moving from the producer to the consumers [
(23) |
where r is the hydraulic radius; is the density of the fluid; and is the mass flow rate.
The transmission loss in the water pipeline of length L is:
(24) |
where is the outside diameter of the
When the heating temperature changes within a certain range, it will not affect the user comfort. In this paper, we provide more space for wind power accommodation by utilizing the elasticity of demand for the heat load.
(25) |
where and are the minimum and maximum heat loads that satisfy the user comfort, respectively; and and are the coefficients of the elasticity of the heat load.
For a PHSN, the heat exchange power of HES is equal to the heat production of CHP plants and EBs minus the transmission loss. Considering the characteristics of PHSN, the relation is given as:
(26) |
where l1, l2, and l3 are the numbers of CHP units, EBs in PHSN, and EBs in SHSN, respectively; is the coefficient of the transmission loss, which varies between 0 and 1; A is the number of heat supply area; is the heat production of the CHP by the CHP units at time t in the
For an SHSN, the heat load is balanced with heat production of HES and EBs in SHSN, which is described as:
(27) |
(28) |
(29) |
where is the heat load at time t in the
This subsection establishes an economic dispatching model for wind power accommodation by EBs, which aims to pursue the minimum coal consumption considering multi-energy and the loss of heat-supply network.
CHP plants undertake the heating task and cannot be started up or shut down arbitrarily. Compared with CHP plants, the start-up costs for EBs and wind farm are relatively low.Hence, the costs of which are disregarded. The objective function in economic accommodation of curtailed wind power is constructed as:
(30) |
where , , , and are the numbers of TP units, CHP units, EBs in PHSN, and EBs in SHSN, respectively; is the start-up cost at time for the
1) Constraints of power balance: the generation and demand of electricity are balanced during each period. The constraints of the power balance are defined as related chance constraints in (15)-(19).
2) Constraints of the heat balance are defined in (26)-(28) and can be rewritten as:
(31) |
3) Constraints of TP plants are defined in (3)-(5).
4) Constraints of CHP plants are defined in (6)-(9).
5) Constraints of transmission lines are defined in (11).
6) Constraints of EBs are defined in (13), (14), (21) and (22).
7) Constraints of wind power are defined in (12).
The experiment data are originated from the EIM power grid in China, which includes three TP plants (TP1, TP2, TP3), three CHP plants (CHP4, CHP5, CHP6), and a wind farm with 150 MW rated power. The parameters of TP and CHP plants are shown in Tables

Fig. 6 Original data of heat load, power load, and wind power.
The case is simulated through four schemes as follows.
1) Scheme 1: there are no EBs in the heat-supply network.
2) Scheme 2: there are EBs only in PHSN.
3) Scheme 3: there are EBs only in SHSNs.
4) Scheme 4: there are EBs both in PHSN and in SHSNs.
The first scheme implies that the heat load is satisfied only by CHPs. In this situation, the coupling between the heat and power is rigid, which leads to curtailed wind power. The last three schemes increase EBs to supply heat and accommodate the curtailed wind power coordinated with CHPs. EBs are installed at different locations in every scheme. Due to the heat transportation lag of the primary heat network, the heat load is meant to be moved in the time scale, which may lead to different utilities of the EBs to accommodate the wind power. Besides, we discuss how the heat transmission loss affects the accommodation results by introducing the coefficient .
Coal consumptions with different losses of heat-supply network in the four schemes are compared in

Fig. 7 Comparison of coal consumptions in four schemes.
The optimized results at different confidence levels are compared in

Fig. 8 Curtailed wind power curve with different heat loss coefficients.
In the four schemes, the total outputs of TP plants, CHP plants and wind farm are shown in

Fig. 9 Comparison of outputs of TP plant, CHP plant and wind power in four schemes. (a) Output of TP plant. (b) Output of CHP plant. (c) Output of wind power.
To further analyze the differences between the two schemes where the EBs are equipped at different locations, two more sets of cases considering different elasticity coefficients of heat load and transmission loss are simulated. The results are shown in

Fig. 10 Comparison of coal consumptions in four schemes. (a) . (b) .
The main difference between schemes 2 and 3 is that EBs are equipped in PHSN and SHSN, respectively. The heat outputs of CHP plants, EBs, and heat load in schemes 2 and 3 are presented in

Fig. 11 Heat outputs of CHP plant, EBs, and heat load in schemes 2 and 3. (a) Heat output of CHP plant in case 1. (b) Heat output of CHP plant in case 2. (c) Heat output of EB in case 1. (d) Heat output of EB in case 2. (e) Heat load in case 1. (f) Heat load in case 2.

Fig. 12 Power outputs of TP plant, CHP plant, EB, and wind power in schemes 2 and 3. (a) Output of TP plant in case 1. (b) Output of TP plant in case 2. (c) Power output of CHP plant in case 1. (d) Power output of CHP plant in case 2. (e) Output of EB in case 1. (f) Output of EB in case 2. (g) Output of wind power in case 1. (h) Output of wind power in case 2.
The coal consumption cost of the two modes is directly related to the utilization of the EBs. Furthermore, the utilization is mainly affected by the heat load elasticity and heat transmission. As the heat transmission efficiency decreases, the heat power transferred by the EBs equipped in PHSN and CHP plants will be partly lost in the transmission process. To compensate for the heat loss, CHP plants have to increase its heat output, which causes an increase in operation cost. The influence of heat load elasticity on operation cost can be analyzed through the comparison between cases 1 and 2. When the heat load is fixed, the operation constraint for the EBs in SHSN is stricter than those in PHSN. This is because the EBs in PHSN can provide heat to multiple heating areas, while the EBs in SHSN has to follow the heat load curve of its own heating area separately.
We address the issue of wind power accommodation with CHP plants and EBs at different locations. The conclusions are given as follows.
1) The allocation of EBs is able to accommodate curtailed wind power. With no loss of heat-supply network, all the three schemes equipped with EBs succeed to achieve the accommodation of wind power curtailment. The curtailed wind power declines as the transmission efficiency of heat-supply network increases.
2) Coal consumptions in four schemes with no EBs, EBs only in PHSN, EBs only in SHSN, and EBs in both PHSN and SHSN all decrease with the enhancement of transmission efficiency of heat-supply network and the elasticity of heat load. And these two factors have different influences on the utility of the EBs at different locations. With the decrease of elasticity coefficient and the increase of heat transmission efficiency, the advantage of EBs in PHSN becomes more and more prominent. Similarly, with the increase of elasticity coefficient of and the decrease of heat transmission efficiency, the utilization of EBs in SHSN will be more than that in PHSN.
3) Curtailed wind power absorbed by EBs is converted into heat energy to supply heat, which results in the reduction of heat output for CHPs. Hence, with the connection of EBs, the total power outputs of CHPs decline, trending with the variation of heat load.
4) The elasticity of heat load is not specific enough and the flexibility of heat demand may be more complex during the actual operation process, which can be further studied in the future. More constraints of the heat network such as the transmission capacity limitation will be considered further.
References
National Bureau of Statistics. (2019.Jan.). National data. [Online]. Available: http://data.stats.gov.cn/easyquery.htm?cn=C01 [Baidu Scholar]
Inner Mongolia People’s Government. (2017. Apr.). “Thirteenth Five-Year” industrial development plan of inner Mongolia Autonomous Region. [Online]. Available: http://www.elht.gov.cn/tzel/zszn/yhzc/201808/t20180824_157547.html [Baidu Scholar]
R. Amirante, E. Cassone, E. Distaso et al., “Overview on recent developments in energy storage: mechanical, electrochemical and hydrogen technologies,” Energy Conversion and Management, vol. 132, no. 15, pp. 372-387, Jan. 2017. [Baidu Scholar]
F. Geth, T. Brijs, J. Kathan et al., “An overview of large-scale stationary electricity storage plants in Europe: current status and new developments,” Renewable and Sustainable Energy Reviews, vol. 52, pp. 1212-1227, Dec. 2015. [Baidu Scholar]
X. Luo, J. Wang, M. Dooner et al., “Overview of current development in electrical energy storage technologies and the application potential in power system operation,” Applied Energy, vol. 137, no. 1, pp. 511-536, Jan. 2015. [Baidu Scholar]
F. Geth, T. Brijs, J. Kathan et al., “A review of energy storage technologies for wind power applications,” Renewable and Sustainable Energy Reviews, vol. 16, no. 4, pp. 2154-2171, Dec. 2012. [Baidu Scholar]
B. Zakeri and S. Syri, “Electrical energy storage systems: a comparative life cycle cost analysis,” Renewable and Sustainable Energy Reviews, vol. 42, pp. 569-596, Feb. 2015. [Baidu Scholar]
S. Sichilalu, T. Mathaba, and X. Xia, “Optimal control of a wind-PV-hybrid powered heat pump water heater,” Applied Energy, vol. 185, pp. 1173-1184, Jan. 2017. [Baidu Scholar]
S. J. G. Cooper, G. P. Hammond, M. C. Mcmanus et al., “Detailed simulation of electrical demands due to nationwide adoption of heat pumps, taking account of renewable generation and mitigation,” IET Renewable Power Generation, vol. 10, no. 3, pp. 380-387, Mar. 2016. [Baidu Scholar]
P. Mancarella, “Cogeneration systems with electric heat pumps: energy-shifting properties and equivalent plant modelling,” Energy Conversion and Management, vol. 50, no. 8, pp. 1991-1999, Aug. 2009. [Baidu Scholar]
S. Sichilalu, T. Mathaba, and X. Xia, “Optimal control of a wind-PV-hybrid powered heat pump water heater,” Applied Energy, vol. 185, pp. 1173-1184, Jan. 2017. [Baidu Scholar]
T. S. Pedersen, P. Andersen, K. M. Nielsen et al., “Using heat pump energy storages in the power grid,” in Proceedings of 2011 IEEE International Conference on Control Applications (CCA), Denver, USA, Sept. 2011, pp. 1106-1111. [Baidu Scholar]
J. Deng, L. Hu, and J. Li, “Analysis on mechanism of curtailed wind power accommodation and its economic operation based on electric boiler for peak-load regulation at secondary heat supply network,” Automation of Electric Power Systems, vol. 40, no. 18, pp. 41-46, Sept. 2016. [Baidu Scholar]
X. Chen, C. Kang, and M. O. Malley, “Increasing the flexibility of combined heat and power for wind power integration in China: modeling and implications,” IEEE Transactions on Power Systems, vol. 30, no. 4, pp. 1848-1857, Jul. 2015. [Baidu Scholar]
P. Meibom, J. Kiviluoma, and R. Barth, “Value of electric heat boilers and heat pumps for wind power integration,” Wind Energy, vol. 10, no. 4, pp. 321-337, Jul. 2007. [Baidu Scholar]
M. B. Blarke, “Towards an intermittency-friendly energy system: comparing electric boilers and heat pumps in distributed cogeneration,” Applied Energy, vol. 91, no. 1, pp. 345-365, Mar. 2012 [Baidu Scholar]
N. Zhang, X. Lu, and M. B. Mcelroy, “Reducing curtailment of wind electricity in China by employing electric boilers for heat and pumped hydro for energy storage,” Applied Energy, vol. 184, no. 15, pp. 987-994, Dec. 2016. [Baidu Scholar]
X. Jiang, Z. Jing, Q. H. Wu et al., “Modeling of a central heating electric boiler integrated with a stand-alone wind generator,” in Proceedings of 2013 IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC), Hong Kong, China, Dec. 2013, pp. 1-6. [Baidu Scholar]
M. G. Nielsen, J. M. Morales, and M. Zugno, “Economic valuation of heat pumps and electric boilers in the Danish energy system,” Applied Energy, vol. 167, no. 1, pp. 189-200, Apr. 2016. [Baidu Scholar]
S. Rong, Z. Li, and W. Li, “Investigation of the promotion of wind power consumption using the thermal-electric decoupling techniques,” Energies, vol. 8, no. 8, pp. 8613-8629, Aug. 2015. [Baidu Scholar]
J. Li and L. Hu, “Research on accommodation scheme of curtailed wind power based on peak-shaving electric boiler in secondary heat supply network,” Power System Technology, vol. 39, no. 11, pp. 3286-3291, Nov. 2015. [Baidu Scholar]
Z. Gu, C. Kang, and X. Chen, “Optimization of integrated power and heat energy systems and the benefit on wind power accommodation considering heating network constraints,” Proceedings of the CSEE, vol. 35, no. 14, pp. 3596-3603, Jul. 2015. [Baidu Scholar]
Z. Li, W. Wu, M. Shahidehpour et al., “Combined heat and power dispatch considering pipeline energy storage of district heating network,” IEEE Transactions on Sustainable Energy, vol. 7, no. 1, pp. 12-22, Jan. 2016. [Baidu Scholar]
C. Wu, W. Gu, P. Jiang et al., “Combined economic dispatch considering the time-delay of district heating network and multi-regional indoor temperature control,” IEEE Transactions on Sustainable Energy, vol. 9, no. 1, pp. 118-127, Jan. 2018. [Baidu Scholar]
L. Lin, J. Gu, and L. Wang, “Optimal dispatching of combined heat-power system considering characteristics of thermal network and thermal comfort elasticity for wind power accommodation,” Power System Technology, vol. 43, no. 10, pp. 3648-3655, Oct. 2019. [Baidu Scholar]
J. Li and L. Hu, “Research on accommodation scheme of curtailed wind power based on peak-shaving electric boiler in secondary heat supply network,” Power System Technology, vol. 39, no. 11, pp. 3286-3291, Nov. 2015. [Baidu Scholar]
B. Stott, J. Jardim, and O. Alsac, “DC power flow revisited,” IEEE Transactions on Power Systems, vol. 24, no. 3, pp. 1290-1300, Aug. 2009. [Baidu Scholar]
B. Liu and K. Iwamura, “Chance constrained programming with fuzzy parameters,” Fuzzy Sets and Systems, vol. 94, no. 2, pp. 227-237, Mar. 1998. [Baidu Scholar]
H. V. Larsen, B. Bohm, and M. Wigbels, “A comparison of aggregated models for simulation and operational optimisation of district heating networks,” Energy Conversion and Management, vol. 45, no. 7, pp. 1119-1139, May 2004. [Baidu Scholar]
S. Yuan, “Research on dynamic performance of centralized Heat-supply System,” M.S. thesis, Environment College, Tianjin University, Tianjin, China, 2010. [Baidu Scholar]