Impact of Down Spinning Reserve on Operation Reliability of Power Systems  PDF

  • Yang Yang 1
  • Minglei Bao 1
  • Yi Ding 1
  • Heping Jia 1
  • Zhenzhi Lin 1
  • Yusheng Xue 2
1. College of Electrical Engineering, Zhejiang University, Hangzhou, China; 2. State Grid Electric Power Research Institute, Nanjing, China

Updated:2020-07-10

DOI:10.35833/MPCE.2019.000110

  • Full Text
  • Figs & Tabs
  • References
  • Authors
  • About
OUTLINE

Abstract

The development of renewable energy and the increasing peak-valley difference of load demand lead to an increasing requirement of spinning reserve (SR). However, the traditional operation reliability analysis of power system mainly focuses on the up SR and neglects the down SR. Therefore, the operation reliability of power system considering the impacts of down SR is investigated in this paper. Firstly, the constraints of down SR are incorporated into the day-ahead unit commitment (UC) model to obtain the generation scheduling and reserve allocation of power systems. Based on the dispatch results of UC model, the re-dispatched energy and load interruption can be determined using optimal power flow (OPF) model in the real-time operation in various contingency states. Operation reliability indices are calculated based on the load curtailment to represent the reliability performances of power systems. The proposed approaches are validated using the modified IEEE reliability test system. Case studies demonstrate that down SR can improve the operation reliability of power systems.

I. Introduction

THE penetration of renewable energy sources (especially wind power) in power system is increasing around the world. In the United States, 20% of the energy production will be provided by wind power at 2030 [

1]. According to plan of European Union, renewable power will account for 20% of the total energy production by 2020 [2]. The increasing integration of thermostatically controlled load such as air conditioner has also increased the peak-valley difference of power system load [3]. Both the high penetration of fluctuating renewable energy and the huge peak-valley difference of load have largely increased the difficulties for system operators (SOs) to balance the generation and demand during the real-time operation [4]. In Denmark, more than half of the system imbalances are caused by wind power fluctuation [5], which leads to an increasing requirement of spinning reserve (SR). SR is an important resource utilized by SOs to compensate for the power imbalances and to maintain the reliable operation of power system [6]. Generally, SR can be divided into up SR and down SR according to the adjustment direction of power output. The up SR is utilized to provide an increasing rate of generation and compensate for the deficit of production. In contrast, the down SR is used to provide a decreasing rate of generation output without shutting down the units, when there is a surplus of generation [7].

Traditional operation of power system usually takes account of the effects of up SR more than the effects of down SR. As an important resource to power system operation, down SR can increase the flexibility to re-dispatch power system, relieve congestion and increase renewable energy consumption. In some extreme circumstances, there might be a huge decrease of system load, following with a rapid increase of system load during a very short period in power systems such as “duck curve” [

8]. Without enough down SR, the SO must firstly switch off units and rapidly switch on units afterward to maintain the simultaneous balance between power generation and demand. However, it is costly to frequently switch on/off generators than implementing down SR [9] and there might not be enough time to switch on/off generators. Furthermore, down SR can improve the consumption of renewable energy by decreasing the output of traditional generators when renewable energy increases suddenly. In the northwest power grid of China, down SR is implemented to increase the consumption of renewable energy [10]. Therefore, down SR should be incorporated into the unit commitment (UC) model to schedule the generation and guarantee the reliable operation of power system.

The results of generation scheduling and reserve allocation obtained from UC model may vary greatly with different levels of SR requirement, which further affect the operation reliability of power system. A number of proposals to incorporate up SR constraints into UC model have been proposed for the joint scheduling of generation and SR. In [

11], the unavailability of the generation units and the uncertainty of load forecasting are incorporated into the UC model to schedule up SR. Reference [12] proposes a method to schedule up SR more reasonably based on probabilistic criterions. Reference [13] proposes a method to schedule up SR considering the reliability choice of customer. On the basis of these UC models, the influence of up SR on power system reliability is widely studied. References [14], [15] show that the power system must increase the amount of up SR or will face a measurable decrease in reliability as wind capacity increases. Reference [16] shows that the up SR is necessary for keeping power system reliability under emergencies, whereas the cost of up SR should be traded off with the cost of energy not served. However, most of the previous researches mainly focus on the correlation between the up SR and the power system reliability without consideration of the effects of down SR. Thus, it is necessary to evaluate the impacts of down SR on power system reliability.

The researches on reliability analysis for power systems have been extensively done, including Monte Carlo simulation (MCS) approaches [

17], [18] and analytical methods [19]-[22]. However, the previous researches mainly focus on the long-term reliability evaluation of power system based on the steady-state probabilities of system components. Due to the high fluctuation of wind power generation in short periods, operation or short-term reliability of power system should be investigated.

This paper proposes an evaluation method for operation reliability of power system considering down SR and the uncertainty of wind power output. The main contributions of this paper are threefold:

1) The impacts of down SR on the operation reliability of power system are analyzed, which are seldom considered in other researches.

2) A modified UC model in the day-ahead market is proposed, which incorporates constraints of down SR provided by both generation units and loads.

3) Based on the results of the day-ahead market, the optimal power flow (OPF) model is proposed to re-dispatch power system considering random failures and output uncertainty of wind power during the real-time operation. Linearization methods for the OPF model are also implemented.

The remainder of this paper is organized as follows. Section II introduces the UC and OPF model considering down SR and the analytical method for operation reliability of power system. Illustrative examples using IEEE reliability test system are presented in Section III. Conclusions are given in Section IV.

II. Mathematical Model Formulation

The proposed method is formulated using a modified UC model considering down SR to co-optimize the generation scheduling and the dispatch of up and down reserves in the day-ahead electricity market. The dispatch results of UC model are utilized as the basic inputs of the OPF model during real-time operation, which is formulated to re-dispatch the power system and calculate the load interruption under different contingency states. With the results of load interruption, the operation reliability can be evaluated using expected energy not supplied (EENS) and loss of load probability (LOLP) indices. The structure for the simulation model is presented in Fig. 1.

Fig.1 Framework of simulation model.

A. Uncertainty Modeling of Wind Power Output

In this section, the model of multi-state wind power generation is developed to describe the uncertainty of wind power output. The generated power of a wind turbine varies with the wind speed, which can be formulated mathematically with:

Vw,tkw=Vw,t0+5δw,t3(kw-3)pw,tkw=Pr(Vw,tkw) (1)

where kw=1,2,,6; Vw,t0 and δw,t are the mean value in the normal state and the variance of wind speed distribution of wind turbine w at time period t, respectively; and Vw,tkw and pw,tkw are the wind speed and the corresponding probability of wind turbine w in state kw at time period t, respectively.

The output power of a wind turbine can be determined from its power curve, which is a plot of output power against wind speed and can be expressed as:

Pw,tkw=0          0Vw,tkw<Vwci and Vwco<Vw,tkwPwrate(Aw+BwVw,tkw+Cw(Vw,tkw)2)            VwciVw,tkw<VwrPwrate    VwrVw,tkwVwco (2)

where Vwci, Vwco and Vwr are the cut-in speed, cut-out speed and rated speed of wind turbine w, respectively; Pwrate is the rated power of wind turbine w when the wind speed is between the rated speed and the cut-out speed; and Aw,Bw,Cw are the constants of wind turbine w. These parameters in (2) can be found in [

23]. Thus, the wind power output uncertainty can be discretized and expressed with multi-state models.

B. UC Model Considering Down SR for Day-ahead Electricity Market

Based on the day-ahead forecasted load demand and wind power output, the multi-period UC model is implemented in the day-ahead electricity market for determining the states of generation units, hourly scheduling of units and the SR dispatch of units. The objective is to minimize the total cost, including no-load cost, energy production cost, start-up and shut-down cost, up SR cost of each unit. Generally, the cost is provided in quadratic form. For the simplification of calculation, the energy production cost is piecewise-linearized to reduce the complexity of calculation in various electricity markets [

24]. Traditional UC model without considering the constraints of down SR is presented as follows:

mintTiNgNGi(GCg(Pg,t0,xg,t)+RUg,tPRUg,t+RUd,tPRUd,t) (3)

where RUg,t and RUd,t are the up SRs dispatched for unit g and load d at time t, respectively; PRUg,t and PRUd,t are the costs of up SR dispatched for unit g and load d at time t, respectively; T is the set of time periods; NGi is the set of generators on bus i; N is the set of buses; Pg,t0 is the real power output of unit g at time t in the normal state; and GCg() is the generation cost of unit g, which can be expressed as:

GCg(Pg,t0,xg,t)=NLCgxg,t+sNSλg,tPs,g,t0+SUg,tyg,t+SDg,tzg,t (4)

where SUg,t and SDg,t are the startup and shutdown costs of unit g at time t, respectively; xg,t, yg,t, zg,t are the binary variables, and if unit g is online at time t, xg,t is equal to 1, if unit g is start-up at time t, yg,t is equal to 1, if unit g is shut-down at time t, zg,t is equal to 1; NLCg is the no-load cost of unit g; λg,s is the incremental cost of unit g for segment s; Ps,g,t0 is the real power output of unit g at time t at segment s in the normal state; and NS is the set of cost curve segments.

The UC model is subject to the following constraints.

1) Generation Constraints

Pgminxg,tPg,t0=sNSPs,g,t0Pgmaxxg,t (5)
0Ps,g,t0Ps,gmaxxg,t    g,s,t (6)

where Pgmax and Pgmin are the maximum and minimum real power outputs of unit g, respectively; and Ps,gmax is the maximum real power output of unit g for segment s.

Constraint (5) bounds the generation by the minimum power output and the maximum available power output of unit g. Constraint (6) specifies that the output of generation units in each linear segment s should be inferior to the output range of the segment.

2) Power Flow Constraints

gNGiPg,t0+wNWiPw,t0-dNLiPd,t0=kNVi0Vk0Yik0cos(θi0-θk0-δik0) (7)
gNGiQg,t0+wNWiQw,t0-dNLiQd,t0=kNVi0Vk0Yik0sin(θi0-θk0-δik0) (8)

where Vi0=Vi0θi0 and Vk0=Vk0θk0 are the bus voltages at bus i and bus k, respectively; Yik0=Yik0δik0 is the element of admittance matrix in the normal state; Qg,t0 is the reactive output of unit g at time t in the normal state; Pw,t0 and Qw,t0 are the active and reactive wind power outputs of wind turbine w in the normal state, respectively; Pd,t0 and Qd,t0 are the active and reactive power demands of load d at time t in the normal state, respectively; NWi is the set of wind turbines on bus i; and NLi is the set of loads on bus i.

3) Up SR Constraints

0RUg,t+Pg,t0Pgmaxxg,t (9)
0RUg,t(Pgmax-Pgmin)xg,t (10)
RUg,tmin(Δg,t+,Pgmax-Pg,t0) (11)
0RUd,tPd,t0-Pdmin (12)
iNgNGiRUg,t+iNdNLiRUd,tRUtreq (13)

where Pdmin is the minimum active power demand of load d; Δg,t+ is the maximum up ramping rate of unit g at time t; and RUtreq is the up SR requirement at time t.

Constraint (9) specifies that the summation of assigned up SR and output of each unit should be inferior to the maximum output. Constraint (10) specifies that up SR can be provided by unit g during period t only if it is in operation. Constraint (11) specifies that the up SR provided by generation units is limited by its maximum generation level and up ramping rates. Constraint (12) specifies that the up SR provided by load sector is limited by the minimum load demand. Constraint (13) specifies that the total up SR should be superior to the requirement of up SR in the whole system.

4) Ramping Up/Down Constraints

Pg,t-Pg,t-1Δg,t+ (14)
-Δg,t-Pg,t-Pg,t-1 (15)

where Pg,t is the real power output of unit g at time t; and Δg,t- is the maximum down ramping rate of unit g at time t.

Constraints (14) and (15) are inter-temporal constraints, which specify the ramping limits of generation units from time interval t-1 to time interval t.

5) Minimum Up and Down Time Constraints

(ug,t-1-UTg)(xg,t-1-xg,t)0 (16)
(ug,t-1-DTg)(xg,t-xg,t-1)0 (17)

where UTg and DTg are the minimum up time and down time of unit g, respectively; and ug,t is the number of hours that unit g has been on or off at the end of time t.

Constraints (16) and (17) represent the minimum time limits of generation units to switch on and off.

6) Line Flow Limits

Sl,t0Slmax (18)

where Sl,t0 is the apparent power of line l at time t in the normal state; and Slmax is the maximum apparent power of line l.

7) Voltage Limits

ViminVi,t0Vimax (19)

where Vimax and Vimin are the upper and lower limits of voltage at bus i, respectively; and Vi,t0 is the voltage of bus i at time t in the normal state.

8) Reactive Power Output Limits

Qgminxg,tQg,t0Qgmaxxg,t (20)

where Qgmax and Qgmin are the upper and lower output limits of reactive power of unit g, respectively.

9) Integer Constraints

yg,t-zg,t=xg,t-1-xg,t (21)
yg,t+zg,t1 (22)
xg,t,yg,t,zg,t0,1 (23)

Traditional UC models usually neglect the effects of down SR, which are considered in this paper. The cost of down SR should be supplemented into the objective of UC model, which is given as follows:

mintTiNgNGi(GCg(Pg,t0)+RUg,tPRUg,t+RUd,tPRUd,t+RDg,tPRDg,t+RDd,tPRDd,t) (24)

where RDg,t and RDd,t are the down SRs dispatched for unit g and load d at time t, respectively; and PRDg,t and PRDd,t are the costs of down SR dispatched for unit g and load d at time t, respectively.

The constraints of down SR should also be supplemented into the UC model, which are given as:

Pgminxg,tPg,t0-RDg,t (25)
0RDg,t(Pgmax-Pgmin)xg,t (26)
RDg,tmin(Δg,t-,Pg,t0-Pdmin) (27)
0RDd,tPdmax-Pd,t0 (28)
iNgNGiRDg,t+iNdNLiRDd,tRDtreq (29)

where Pdmax is the maximum active power demand of load d; and RDtreq is the down SR requirement at time t.

Constraint (25) specifies that the output of each unit minus the down SR should be superior to the minimum output. Constraint (26) specifies that down SR can be provided by unit g during period t only if it is in operation. Constraint (27) specifies that the down SR provided by generation units is limited by its minimum generation level and down ramping rates. Constraint (28) specifies that the down SR provided by load sector is limited by the maximum demand. Constraint (29) specifies that the total down SR should be superior to the requirement of down SR in the whole system.

C. Energy Re-dispatching Model Considering Down SR

Despite down SR and up SR are allocated in the day-ahead market, customer loads may still be interrupted in contingency states if wind power generation decreases or the generation units are failed to produce electricity. In real-time operation, the OPF model is implemented to re-dispatch generation within the reserve limits to maintain the system balance, as shown in Fig. 2, where Pg,tj and Pd,tj are the re-dispatched output power of unit g and the re-dispatched demand of load d in real-time operation in contingency state j, respectively; and LId,tj is the load interruption for load d at time t in contingency state j.

Fig. 2 Operation reserve in real-time market. (a) Up and down reserves provided by generation units. (b) Up and down reserves provided by loads.

The obtained results from the UC model such as the generation dispatching results, the up and down SR allocations, are used as the basic inputs for the OPF model. The objective function of OPF model is to minimize the total system operation cost considering the network and market constraints during the real-time operation [

25], [26]. The operation cost includes the energy production cost and customers’ interruption cost. If customers are called to provide reserve, they should change their consumption behavior without further remuneration. This is reasonable because the probability of contingency occurrence is low and customers already profit from their willingness to provide the corrective actions [5]. For contingency state j and wind power output state kw at time t, the objective function can be expressed as:

miniNgNGiGCg(Pg,t0+ΔPg,tj,kw,Cg,tj) +iNddNLiICd(LId,tj,kw) (30)

where ICd() is the interruption cost function of load d; LId,tj,kw is the load interruption for load d at time t in contingency state j and wind output state kw; Nd is the set of load buses; ΔPg,tj,kw is the active power generation re-dispatched from the reference point in the day-ahead market for of unit g at time t in contingency state j and wind output state kw; and Cg,tj is the binary variable, which is equal to 0 if the unit fails in contingency state j.

The interruption cost is a function of load curtailment and corresponding interruption characteristics, which can be represented as:

ICd(LId,tj,kw)=LId,tj,kwCDFd (31)

where CDFd is the customer damage function, which can be used to evaluate the interruption cost of different load sectors [

25].

The objective function (28) is subject to the following constraints.

1) Transmission Constraints

gNGi(ΔPg,tj,kw+Pg,t0)+wNWiPw,tkw-dNLiPd,tj,kw=kNVi,tj,kwVk,tj,kwYikj,kwcos(θi,tj,kw-θk,tj,kw-δik,tj,kw) (32)
gNGi(ΔQg,tj,kw+Qg,t0)+wNWiQw,tj,kw-dNLiQd,tj,kw=kNVi,tj,kwVk,tj,kwYikj,kwsin(θi,tj,kw-θk,tj,kw-δik,tj,kw) (33)

where ΔQg,tj,kw is the reactive power generation re-dispatched for unit g at time t in contingency j and wind output state kw; Vi,tj,kw=Vi,tj,kwθi,tj,kw and Vk,tj,kw=Vk,tj,kwθk,tj,kw are the bus voltages at bus i and bus k in contingency state j and wind output state kw, respectively; Yikj,kw=Yikj,kwδikj,kw is the element of admittance matrix in contingency state j and wind output state kw; and Pd,tj,kw and Qd,tj,kw are the re-dispatched active and reactive power demands of load d in contingency state j and wind output state kw, respectively.

2) Generation Constraints

(Pg,t0-RDg,t)Cg,tjPg,t0+ΔPg,tj,kw (34)
Pg,t0+ΔPg,tj,kw(Pg,t0+RUg,t)Cg,tj (35)
QgminCg,tjQg,t0+ΔQg,tj,kwQgmaxCg,tj (36)

Constraints (34), (35) and (36) specify that unit g can be re-dispatched within the limits of up and down SRs during the period t in contingency state j only if it is on.

3) Load Interruption Constraints

PdminPd,tj,kwPdmax (37)
LId,tj,kw=(Pd,t0-Pd,tj,kw-RUd,t)F(0Pd,t0-Pd,tj,kw-RUd,t) (38)

where F(0Pd,t0-Pd,tj,kw-RUd,t) is equal to 1 when 0Pd,t0-Pd,tj,kw-RUd,t is true, and 0 otherwise.

Other constraints include line flow constraints, voltage constraints, etc.

In the proposed model, constraint (38) is the product of continuous and binary variables and should be converted into linear expression. Assuming that τ is the product of a binary variable α and a bounded continuous variable β[-M,M], where M is a large positive number. The product can be replaced with:

-αMαβ=ταM (39)
β-M(1-α)τβ+M(1-α) (40)

Clearly, if α is equal to zero, β will vanish in constraint (39), while constraint (40) is inactive. Otherwise, if α is equal to one, τ must be equal to β, while constraint (40) is inactive. Thus, constraint (38) can be replaced with the following linear expression:

γd,tj,kw=F(0Pd,t0-Pd,tj,kw-RUd,t) (41)
(Pd,t0-Pd,tj,kw-RUd,t)/Mγd,tj,kw (42)
γd,tj,kw1+(Pd,t0-Pd,tj,kw-RUd,t)/M (43)
-Mγd,tj,kwLId,tj,kwMγd,tj,kw (44)
Pd,t0-Pd,tj,kw-RUd,t-M(1-γd,tj,kw)LId,tj,kw (45)
LId,tj,kwPd,t0-Pd,tj,kw-RUd,t+M(1-γd,tj,kw) (46)

D. Reliability Indices and Evaluation Process of Power Systems

The obtained results from the analysis of normal state and contingency state can be used to evaluate the power system reliability, according to the following steps.

Step 1:   implement the multi-period UC model in the day-ahead electricity market for determining the states of generation units and the corresponding generation scheduling, as well as the up and down SRs for each operation time interval. Forward the obtained results as the reference points to the energy re-dispatch model.

Step 2:   for each contingency state, solve the energy re-dispatching model formulated by the single-period OPF model to determine the generation re-dispatching results and the load interruption.

Step 3:   evaluate the probability of power system contingency state j and wind power output state kw with the following equations.

ptj,kw=gBj,tORRg,tgBj,t(1-ORRg,t)wpw,tkw (47)
ORRg,t=1-e-t/MTTFgt/MTTFg (48)

where ORRg,t is the failure probability of the unit g during the time interval t; Bj,t is the set of failed units in contingency state j during the time interval t; and MTTFg is the mean time to failure (MTTF) of unit g.

Step 4:  evaluate the two reliability indices LOLPt and EENSt, which are defined as LOLP and EENS in the power system for the time interval t, respectively. They can be calculated with the following equations:

LOLPt=jkwptj,kwF(0<LId,tj,kw,d) (49)
EENSt=jkw(ptj,kwΔtiNdNLiLId,tj,kw) (50)

where F(0<LId,tj,kw,d) is equal to 1 when 0<LId,tj,kw,d is true, and 0 otherwise; and Δt is the duration of the time interval t.

III. Illustrative Examples

To further illustrate the proposed models and techniques, the IEEE reliability test system [

27], as shown in Fig. 3, has been studied to demonstrate the proposed models and techniques.

Fig. 3 Diagram of IEEE reliability test system.

The ramping limits, minimum on/off time, piecewise linear cost, start-up and shut-down costs as well as the no-load cost are taken from [

28]. The transmission capacity of each line is set to be 60% of the initial capacity to increase the value of EENS and LOLP. The costs of providing up and down SRs at demand side are 100 $/MWh [7]. The minimum of the load is set to be zero and the maximum of the load is set to be 10% higher than the original load level. Besides, the minimum and maximum outputs of units are increased to emphasize the impact of down SR when the load demand decreases rapidly. The minimum and maximum outputs of units and the reserve prices are given in Table I.

Table I Parameters of Generation Units
Generation unit

Output level

(MW)

Reserve price

($/MWh)

LowerUpperUp SRDown SR
I1, I2, I5, I6, I15-I19, I24, I26-I29 12 69 48 48
I3, I4, I7, I8, I25 24 120 65 65
I9-I11, I20, I21, I30, I31 35 150 70 70
I12-I14 65 180 76 76
I22, I23, I32 150 350 88 88

To decrease the failure time of units and increase the values of EENS and LOLP, MTTF of each generation unit is decreased and provided in Table II.

Table II MTTF of Each Generation Unit
Generation unitMTTF (hour)
I1, I2, I5, I6 450
I12-I14, I20, I21 900
I29, I30, I32 1100
I9-I11 1200
I3, I4, I7, I8, I24-I28 1900
I15-I19, I22, I23, I31 2900

In the real-time operation, the compensation for load interruption is required in the energy re-dispatch model. Loads at the same node are assumed to have the same priority of interruption cost, which is given in Table III.

Table III Load Interruption Cost
Load locationInterruption cost ($/MWh)
Buses 2-4, 7-10, 19 200
Buses 5, 14-16, 18, 20 220
Buses 1, 6, 13 240

Considering that the operation reliability of power system is closely related to load levels, different load curves including the traditional load curve (case 1) and duck curve (case 2) are considered.

A. Case 1

In case 1, a typical load curve is utilized to illustrate the proposed models and techniques. The whole duration of study period is 24 hours. The peak load is 1850 MW and the valley load is 750 MW. The load increases rapidly between hour 6 and hour 8 and the load decreases rapidly between hour 22 and hour 24. The load curve is shown in Fig. 4.

Fig. 4 Load curve of case 1.

With the data mentioned above, the results of UC considering different levels of down SRs (scenario 1, 0 MW; scenario 2, 200 MW; scenario 3, 400 MW) can be calculated. In scenario 1, the constraint of down SR is not considered. In the study, the up SR is set to be 200 MW, which is about 10% of the maximum load. Based on the UC results of different down SR levels, the reliability indices during different simulation periods can be calculated. The results of EENS and LOLP with different levels of down SRs are shown in Fig. 5 and Fig. 6, respectively.

Fig. 5 EENS of case 1.

Fig. 6 LOLP of case 1.

It can be observed from Fig. 5 and Fig. 6 that the system reliability indices (EENS and LOLP) without consideration of the impacts of down SR are larger than those in other scenarios where the down SR is considered. Moreover, the reliability of systems with more down SRs is improved with an increase of down SRs.

From Fig. 7, it can be observed that with the increasing requirement of down SR, there are more on-line generation units. For instance, between hour 1 and hour 6, there are more units switched on with 400 MW down SR than the other two scenarios with less down SRs. This result can be explained by down SR constraint (23). In general, units with higher generation capacity always have a higher minimum generation level Pgmin. If the system requires a higher amount of down SR, the total minimum generation level gPg,tminxg,t of the whole system should be lower. Thus, when the load level is low, one large unit with high minimum generation capacity is more likely to be replaced with several other smaller units. For example, there are three units on (I22, I23 and I32) at the first study period for scenario 1 and scenario 2. Four generation units are online in scenario 3, because the total minimum generation capacity of the three units (I22, I23 and I32) is 450 MW and the load demand is just 820 MW. Hence, one of the units of (I22, I23 and I32) is shut down, and other two smaller generation units are switched on. During the real-time operation, failed generators are not able to provide SR. With more on-line generation units, the expected up SRs of all contingency states jpjg(RUg,tCg,tj) in scenario 1 are less than those in scenario 2 and scenario 3. As a result, the whole power system is more reliable with more expected up SRs.

Fig. 7 Number of online units with different down SRs.

Furthermore, it can also be observed in Fig. 7 that between hour 19 and hour 22 when the demand decreases rapidly, the units are shut down less rapidly in scenario 3 (2 units are shut down) than that in scenario 1 (6 units are shut down) and scenario 2 (5 units are shut down). This is because there are more down SRs in scenario 3 and the units are not necessary to shut down immediately as the load demand decreases. With more online units, the power system of scenario 1 is more reliable than those of the other two scenarios. It can be proved from Fig. 5 and Fig. 6 that EENS increases less rapidly in scenario 3 than those in scenario 1 and scenario 2, which means scenario 3 is more reliable than scenario 1 and scenario 2.

The down SR can improve power system operation reliability in two aspects. On the one hand, down SR leads to a higher number of small units to replace large units, which further leads to less loss of up SR under contingency states and indirectly improves the operation reliability of power system. On the other hand, down SR enables the power system to slowly shut down generation units, when the load decreases rapidly. This leads to a higher number of online generation units and a higher level of up SR in real-time operation, which improves the operation reliability of power system.

B. Case 2

With large amount of renewable energy integrated into power systems, the shape of net load curve may change dramatically into duck curve, where the peak of electricity production occurs at the night and the valley of electricity production occurs in the day time. In case 2, a typical duck curve is considered to illustrate the proposed models and techniques. Due to the uncertainty of wind power generation, the realistic net load may vary greatly from the forecasted net load demand. The forecasted net load curve and the realistic load curve is shown in Fig. 8.

Fig. 8 Forecasted net load curve and realistic net load curve.

Based on the data mentioned above and the proposed simulation method, the UC results of different scenario with different levels of down SRs (scenario 1, 0 MW; scenario 2,100 MW; scenario 3, 200 MW) can be calculated. The up SR is set to be 200 MW. The number of online units during hour 7 and hour 14 in two load demand curves are shown in Table IV.

Table IV Number of Online Units
Time (hour)Number of online units
Scenario 1Scenario 2Scenario 3
ForecastedRealisticForecastedRealisticForecastedRealistic
7 7 5 8 6 8 8
8 5 3 6 4 5 5
9 5 3 6 4 5 5
10 5 3 6 3 5 5
11 5 3 5 3 5 5
12 4 3 4 3 5 5
13 4 3 4 3 5 5
14 4 3 4 3 5 5

From Table IV, it can be observed that with the increasing requirement of down SR, there are more on-line generation units in scenario 3 than those in scenario 2 and scenario 1 between hour 7 and hour 14. Besides, it can also be observed that the number of online units during hour 7 and hour 14 with the day-ahead forecasted load demand and with realistic load demand of scenario 3 is identical. However, in scenario 1, the number of online units during hour 7 and hour 14 with realistic load demand is less than that with day-ahead forecasted load demand. This is because the generation units in scenario 3 are not necessary to be shut down and can decrease the output to follow the sudden net load demand decrease with sufficient down SRs. On the contrary, several generation units are forced to be shut down to keep the power balance. As a result, the overall up SR provided by online units is reduced due to the shut down of generation units and the operation reliability of power system will worsen. Figure 9 presents the online up SRs and EENSs of scenario 1 and scenario 3 in real-time operation.

Fig. 9 Comparison of up SR and EENS with different down SRs.

As can be seen from Fig. 9, EENS in scenario 1 is higher than that in scenario 3, which means that the operation reliability of scenario 3 is better. Therefore, when system load demand decreases suddenly to a very low level, the down SR enables the power system to keep the units operate at a low output level rather than being shut down. This indirectly maintains the quantity of up SR in power system, which can improve the operation reliability of power systems.

C. Case 3: Impacts of Wind Power Uncertainty on Operation Reliability of Power Systems

The effect of the uncertainty of wind power output on the operation reliability of power systems is studied. Six wind turbines have been added on buses 2, 14, 16, 17, 18, 19. The capacities of these wind turbines are all set to be 300 MW. Their outputs and the corresponding probabilities of the multi-state models are taken from [

19]. The forecasted net load is the same as in case 2, while the realistic net load fluctuates around the forecasted net load due to the uncertainty of wind power output. Three scenarios with different down SR requirements are studied, as shown in Fig. 10.

Fig. 10 Effects of wind power uncertainty on operation reliability.

It can be observed from Fig. 10 that the wind power uncertainty reduces the operation reliability of power system. This is because the load may be curtailed if the wind power output is smaller than the forecasted value. By increasing the quantity of down SR in power system that indirectly maintains the quantity of up SR, the operation reliability of power system with large uncertainty of wind power output can be improved.

D. Case 4: Comparison of Proposed Method and MCS

To validate the accuracy of the proposed method, the MCS approach is also developed to compare the results obtained by the proposed method. The convergence error for MCS is set to be 0.05. The proposed method and MCS approach are tested based on different scenarios of case 2, and the EENS results of the two methods are given in Fig. 11.

Fig. 11 Comparison of proposed method and MCS.

Figure 11 shows that the results of the proposed method are close to those of the MCS approach. The average percentage error of the proposed method and MCS is 3.9%, which is relatively low.

IV. Conclusion

This paper proposes an operation reliability evaluation method of power system considering the down SR and wind power uncertainty. Case studies show that the uncertainty of wind power output reduces the operation reliability of power systems, which also demonstrate that down SR can improve the operation reliability of power system with large uncertainty of wind power output. The constraints of down SR enforce the power system to switch on smaller units instead of large units and enable a slower shut down of the generation units when the load decreases rapidly, which increases the number of online units. With the increased number of online units, the loss of up SR in contingency states will decrease and the operation reliability of power system will be improved. Furthermore, when load demand decreases to a very low level, the down SR enables the power system to keep the units operate at a low output level rather than being shut down. Thus, the quantity of up SR is maintained and the operation reliability of power systems is kept.

References

1

US Department of Energy, “20% wind energy by 2030: increasing wind energy’s contribution to US electricity supply,” Golden, USA, Jul.2008. [百度学术

2

European Commission, “Communication from the Commission to the European Parliament and the Council: renewable energy: progressing towards the 2020 target,” Brussels, Italy, Oct.2011. [百度学术

3

K. Geoffrey and K. Kelvin, “A study of domestic energy usage patterns in Hong Kong,” Energy, vol. 28, no. 15, pp. 1671-1682, Dec.2003. [百度学术

4

H. Jia, Y. Ding, Y. Song et al., “Operating reliability evaluation of power systems considering flexible reserve provider in demand side,” IEEE Transactions on Smart Grid, vol. 10, no. 3, pp. 3452-3464, Apr.2018. [百度学术

5

Y. Ding, L. Cheng, Y. Zhang et al., “Operational reliability evaluation of restructured power systems with wind power penetration utilizing reliability network equivalent and time-sequential simulation approaches,” Journal of Modern Power Systems and Clean Energy, vol. 2, no. 4, pp. 329-340, Dec.2014. [百度学术

6

S. Lu, Y. Wu, S. Lou et al., “A model for optimizing spinning reserve requirement of power system under low-carbon economy,” IEEE Transactions on Sustainable Energy, vol. 5, no. 4, pp. 1048-1055, Oct.2014. [百度学术

7

J. Arroyo and F. Galiana, “Energy and reserve pricing in security and network-constrained electricity markets,” IEEE Transactions on Power Systems, vol. 20, no. 2, pp. 634-643, Jun.2005. [百度学术

8

Wikipedia. (2019, Jan.). Duck curve. [Online]. Available: https://en.wikipedia.org/w/index.php?title=Duck_curve&oldid=877899502 [百度学术

9

J. Wang, N. Redondo, F. Galiana et al., “Demand-side reserve offers in joint energy/reserve electricity markets,” IEEE Transactions on Power Systems, vol. 18, no. 4, pp. 1300-1306, Dec.2003. [百度学术

10

State Grid Northwest Branch. (2018, Nov.). Down spinning reserve helps to consume renewable energy in north-west power grid of China. [Online]. Available: http://www.cpnn.com.cn/dw/201802/t20180201_1048253.html [百度学术

11

D. Simopoulos, S. Kavatza, C. Vournas et al., “Reliability constrained unit commitment using simulated annealing,” IEEE Transactions on Power Systems, vol. 21, no. 4, pp. 1699-1706, Dec.2006. [百度学术

12

F. Aminifar, M. Fotuhi-Firuzabad, M. Shahidehpour et al., “Unit commitment with probabilistic spinning reserve and interruptible load considerations,” IEEE Transactions on Power Systems, vol. 24, no. 1, pp. 388-397, Mar.2009. [百度学术

13

M. Jaefari-Nokandi and H. Monsef, “Scheduling of spinning reserve considering customer choice on reliability,” IEEE Transactions on Power Systems, vol. 24, no. 4, pp. 1780-1789, Dec.2009. [百度学术

14

R. Doherty and M. O’Malley, “A new approach to quantify reserve demand in systems with significant installed wind capacity,” IEEE Transactions on Power Systems, vol. 20, no. 2, pp. 587-595, Jun.2005. [百度学术

15

M. Ortega-Vazquez and D. Kirschen, “Estimating the spinning reserve requirements in systems with significant wind power generation penetration,” IEEE Transactions on Power Systems, vol. 24, no. 1, pp. 114-124, Feb.2009. [百度学术

16

A. Abiri-Jahromi, M. Fotuhi-Firuzabad, and E. Abbasi, “Optimal scheduling of spinning reserve based on well-being model,” IEEE Transactions on Power Systems, vol. 22, no. 4, pp. 2048-2057, Nov.2007. [百度学术

17

W. Wangdee and R. Billinton, “Considering load-carrying capability and wind speed correlation of WECS in generation adequacy assessment,” IEEE Transactions on Energy Conversion, vol. 21, no. 3, pp. 734-741, Sept. 2006. [百度学术

18

P. Wang and R. Billinton, “Time-sequential simulation technique for rural distribution system reliability cost/worth evaluation including wind generation as alternative supply,” IEE Proceedings C - Generation, Transmission and Distribution, vol. 148, no. 4, pp. 355-360, Jul.2011. [百度学术

19

R. Karki, P. Hu, R. Billinton et al., “A simplified wind power generation model for reliability evaluation,” IEEE Transactions on Energy Conversion, vol. 21, no. 2, pp. 533-540, Jul.2006. [百度学术

20

A. Dobakhshari and M. Fotuhi-Firuzabad, “A reliability model of large wind farms for power system adequacy studies,” IEEE Transactions on Energy Conversion, vol. 24, no. 3, pp. 792-801, Oct.2009. [百度学术

21

R. Karki and R. Billinton, “Cost-effective wind energy utilization for reliable power supply,” IEEE Transactions on Energy Conversion, vol. 19, no. 2, pp. 435-440, Jul.2004. [百度学术

22

S. Wang, Y. Ding, C. Ye et al., “Reliability evaluation of integrated electricity-gas system utilizing network equivalent and integrated optimal power flow techniques,” Journal of Modern Power Systems and Clean Energy, vol. 7, no. 6, pp. 1523-1535, Nov.2019. [百度学术

23

P. Giorsetto and K. Utsurogi, “Development of a new procedure for reliability modeling of wind turbine generators,” IEEE Transactions on Power Apparatus and Systems, vol. 102, no. 1, pp. 134-143, Jan.1983. [百度学术

24

H. Ahmadi, J. Marti, and A. Moshref, “Piecewise linear approximation of generators cost functions using max-affine functions,” in Proceedings of IEEE PES General Meeting, Vancouver, Canada, Jul.2013, pp. 1-7. [百度学术

25

Y. Ding, M. Xie, J. Østergaard et al., “Development of energy and reserve pre-dispatch and re-dispatch models for real-time price risk and reliability assessment,” IET Generation, Transmission & Distribution, vol. 8, no. 7, pp. 1338-1345, Jul.2014. [百度学术

26

Q. Bian, Y. Qiu, W. Wu et al., “Generation dispatch method based on maximum entropy principle for power systems with high penetration of wind power,” Journal of Modern Power Systems and Clean Energy, vol. 6, no. 6, pp. 1213-1222, Dec.2018. [百度学术

27

P. Subcommittee, “IEEE reliability test system,” IEEE Transactions on Power Apparatus and Systems, vol. 98, no. 6, pp. 2047-2054, Nov.1979. [百度学术

28

H. Pandzic, Y. Dvorkin, T. Qiu et al. (2018, Nov.). Unit commitment under uncertainty - GAMS models. [Online]. Available:http://www.ee.washington.edu/research/real/gams_code.html [百度学术